MONTHYEARML0532602472005-11-21021 November 2005 Status of Unit 1 Restart Issues, Revision 4 Project stage: Request ML0535703642006-01-0303 January 2006 Request for Information Regarding Fire Protection Program Project stage: RAI ML0603701762006-02-0303 February 2006 (BFN) - Unit 1 - Response to NRC Request for Information Regarding Fire Protection Program Project stage: Response to RAI ML0606204242006-02-28028 February 2006 Response to NRC Request for Information Regarding Fire Protection Program. Rev. 35 Draft to Fire Protection Report Enclosed Project stage: Draft Response to RAI ML0611401972006-04-0505 April 2006 Enclosure 2 of 04/05/2006 Summary of Public Meeting with Tennessee Valley Authority Browns Ferry Fire Protection Program (TAC MC8826). TVA Handout on Fire Protection Program Project stage: Meeting ML0611401922006-05-30030 May 2006 Enclosure 3 of 04/05/2006 Summary of Public Meeting with Tennessee Valley Authority Browns Ferry Fire Protection Program (TAC MC8826). NRC Handout on Preliminary NRC Perspectives of the Bfnp Fire Protection Program Project stage: Meeting ML0610805062006-05-30030 May 2006 Summary of Public Meeting with Tennessee Valley Authority Browns Ferry Fire Protection Program Project stage: Meeting ML0615204882006-09-21021 September 2006 Letter, Status of Fire Protection Special Program Closeout Project stage: Other 2006-02-03
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24176A1252024-06-28028 June 2024 Summary of Partially Closed Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding the Hydrologic Analysis Updates ML24155A0422024-06-13013 June 2024 Meeting Summary: Public Scoping Webinars for the Environmental Review of the Subsequent License Renewal Application for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML24142A5152024-05-28028 May 2024 April 22, 2024, Summary of Public Mtg with Tennessee Valley Authority to Discuss Use of Risk-Informed Process Evaluation for a Proposed License Amendment Request Elimination of Limiting Condition for Operation Actions for the Rod Worth Mini ML24155A0432024-04-18018 April 2024 Meeting Summary ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0402024-02-27027 February 2024 Summary of February 7, 2024, Public Meeting with Tennessee Valley Authority to Preliminarily Discuss the Planned Approach for the Browns Ferry Nuclear Plant Hydrologic Analysis ML24043A0462024-02-16016 February 2024 Summary of Meeting with TVA to Discuss Use of Risk-Informed Process Evaluation (RIPE) for a Proposed LAR Regarding Elimination of Limiting Condition for Operation Actions for Rod Worth Minimizers ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23157A1272023-06-13013 June 2023 Meeting Summary for Environmental Pre-Submittal Meeting for Subsequent License Renewal Application on May 11, 2023 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML22319A1952022-12-0202 December 2022 Summary of October 13, 2022, Meeting with Tennessee Valley Authority to Discuss Planned Alternative Requests for the Fifth 10-Year Inservice Testing Program Interval for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22298A1612022-11-17017 November 2022 Summary of Public Meeting on SAMA with TVA ML22266A2742022-09-28028 September 2022 Summary of September 22, 2022, Public Meeting with Tennessee Valley Authority to Discuss a Request to Use a Later Edition of the ASME OM Code ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22103A2472022-04-14014 April 2022 Summary of April 12, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Revised Criticality Analysis License Amendment Request ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML22083A0762022-03-24024 March 2022 Summary of March 17, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Atrium 11 License Amendment Request (EPID L-2021-LLA-0132 ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21266A0532021-10-20020 October 2021 Summary of September 22, 2021, Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request to Adopt Technical Specifications Task Force (TSTF)-205 and TSTF-563 ML21273A1922021-10-12012 October 2021 September 27, 2021, Summary of Meeting with Browns Ferry Nuclear Plant, Units 1 & 2 Related to a Planned Alternative Request Per American Society of Mechanical Engineers (Asmee) Code Case N-526, Alternative Requirements for Successive Sect ML21251A1122021-09-14014 September 2021 Summary of September 7, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21155A0212021-06-0808 June 2021 Summary of Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20162A1532020-06-25025 June 2020 Summary of June 8, 2020, Partially Closed Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20094M9012020-04-13013 April 2020 Summary of April 2, 2020 Public Meeting with Tennessee Valley Authority Regarding the Future Submittal of a License Amendment Request Adoption of 10 CFR 50.69 ML19120A2882019-06-0606 June 2019 Summary of March 19, 2019, Closed Meeting with Tennessee Valley Authority a License Amendment Request to Implement Maximum Extended Line Limit Analysis Plus ML19120A3692019-04-30030 April 2019 Public Meeting Summary - Browns Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML18242A4882018-09-24024 September 2018 Summary of Pre-Application Conference Call with Tennessee Valley Authority to Discuss Proposed Changes to Modifications Associated with Approved NFPA 805 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML18101A1012018-04-13013 April 2018 Summary of March 16, 2018, Meeting with Tennessee Valley Authority Regarding a License Amendment Request to Implement Maximum Extended Load Line Limit Analysis Plus for Browns Ferry Nuclear Plant ML18068A0792018-03-15015 March 2018 Summary of Pre-Application Meeting with Tennessee Valley Authority Regarding a Planned License Amendment Request Associated with Modifications to the Control Bay Chillersystems at Browns Ferry Units 1, 2 and 3 ML18053A5362018-03-0101 March 2018 Summary of February 7, 2018, Pre-Application Conference Call with TVA a Planned License Amendment Request to Change the Emergency Response Organization Staffing ML17278A8972017-10-17017 October 2017 Summary of Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry, Units 1, 2, and 3, Sequoyah Nuclear, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2(EPID L2016-TOP-0011; CAC Nos. MF8391-MF8397 ML17227A5142017-09-0101 September 2017 Summary of August 1, 2017, Pre-Submittal Public Meeting with TVA Regarding a Class 1E Unbalanced Voltage Relay Licensing Amendment Request for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant ML17131A2512017-05-11011 May 2017 Summary of Public Meeting Concerning Annual Assessment of Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML17061A6722017-04-0606 April 2017 Summary of February 15, 2017, Meeting with Tennessee Valley Authority on Updates to the Transmission System Regarding Extended Power Uprate for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML17017A4552017-02-0303 February 2017 Summary of Meeting with Tennessee Valley Authority Regarding Maximum Extended Load Line Limit Plus Pre-Application Meeting for Browns Ferry Nuclear Plant ML16350A2962016-12-14014 December 2016 Enclosure 3- Reactor Oversight Process Task Force FAQ Log- November 16, 2016 ML16280A2912016-10-31031 October 2016 September 23, 2016, Summary of Public Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 & 2 and Watts Bar Nuclear Plant, Units 1 & 2 (CAC Nos. MF83 ML16279A2332016-10-0505 October 2016 Summary of Closed Pre-Decisional Enforcement Conference with Tennessee Valley Authority Regarding Browns Ferry Nuclear Plant ML16210A4532016-08-16016 August 2016 07/19/2016 Summary of Meeting with Tennessee Valley Authority Regarding Extended Power Uprate License Amendment Request for Browns Ferry Nuclear Plant (CAC Nos. MF6741, MF6742, and MF6743) ML16193A4602016-07-21021 July 2016 June 23, 2016, Summary of Closed Meeting with Tennessee Valley Authority Regarding the Structural Adequacy of Steam Dryers for Extended Power Uprate License Amendment Request for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (MF6741, MF6742 ML16153A1982016-06-0101 June 2016 2015 EOC Meeting Summary 2024-09-23
[Table view] |
Text
May 30, 2006 LICENSEE: Tennessee Valley Authority FACILITIES: Browns Ferry Nuclear Plant, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF APRIL 5, 2006, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING BROWNS FERRY FIRE PROTECTION PROGRAM (TAC MC8826)
On April 5, 2006, the U.S. Nuclear Regulatory Commission (NRC) staff conducted a Category 1 public meeting with Tennessee Valley Authority (TVA, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the licensees approach for updating the Fire Protection Program for Browns Ferry Nuclear Plant (BFN) to reflect three-unit operation and the recovery of BFN Unit 1. The meeting was open to the general public. Enclosure 1 contains a list of participants, Enclosure 2 is a copy of TVAs presentation materials, and Enclosure 3 is a copy of NRC<s presentation.
BACKGROUND By letter dated January 3, 2006, NRC requested that TVA provide information regarding the fire protection program that will be implemented at BFN to support the recovery of Unit 1. In a letter dated February 28, 2006, TVA provided a draft version of BFN, Units 1, 2, 3 Fire Protection Report. The NRC staff requested the meeting to communicate its comments from reviewing the draft version of BFN, Units 1, 2, 3 Fire Protection Report.
SUMMARY
Two of TVAs stated goals for the recovery of BFN, Unit 1 are to maintain operational fidelity among the three BFN units, and use the same methodology as BFN Units 2 and 3 (e.g., similar modifications, manual actions, same shutdown paths). TVA stated that the Appendix R modifications are scheduled to be complete in the fall of 2006. The licensee stated that the changes to the BFN fire protection program would be made in accordance with its fire protection License Condition. The License Condition has a provision that allows the licensee to make changes to the fire protection program that do not adversely affect the licensees ability to achieve and maintain safe shutdown of the units during a fire.
The NRC staff informed TVA that BFN Unit 1 will be held to the same regulations and safety standards that other nuclear plants are required to satisfy. The NRC and TVA discussed the Commission-approved enforcement discretion policies that currently exist for fire protection programs. To ensure consistency with criteria that allowed past enforcement discretion to be granted by the Commission, TVA will need to identify noncompliances at all three BFN units and initiate corrective actions before September 6, 2006. The NRC staff emphasized that this expectation applies to all nuclear plants. Furthermore, the NRC staff informed TVA that BFN Unit 1 must fix or mitigate any risk-significant noncompliances prior to the restart of Unit 1.
May 30, 2006 The NRC staff provided preliminary comments on several aspects of the draft version of BFN, Units 1, 2, 3 Fire Protection Report that may be inconsistent with current regulatory requirements.
At the conclusion of the meeting, the licensee stated that it will evaluate its options for ensuring compliance with the applicable regulations, and may request a meeting at a later date to inform the staff of its plan.
No commitments or regulatory decisions were made by the NRC staff during the meeting.
/RA/
DyLanne D. Duvigneaud, Project Engineer Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260 and 50-296
Enclosures:
- 1. List of Participants
- 2. TVA Handout
- 3. NRC Handout cc w/encls: See next page
ML061080506 Encl. 3: ML061140192 NRR-001 OFFICE LPL2-2/PE LPL2-2/PM LPL2-2/LA DRA/AFPB/BC LPL2-2/BC DORL/D NAME DDuvigneaud MChernoff BClayton SWeerakkody MMarshall CHaney DATE 5/15/06 5/15/06 5/15/06 5/ 2 /06 5/15/06 5/30/06 May 30, 2006
SUBJECT:
SUMMARY
OF APRIL 5, 2006, MEETING WITH TENNESSEE VALLEY AUTHORITY Date: May 30, 2006 DISTRIBUTION:
PUBLIC LPL2-2 R/F RidsNrrDraAfpb (SWeerakkody)
BClayton PQualls SLee, EDO RGallucci RidsNrrAdro (BBoger) CNolan RidsNrrDorl (CHaney) LLund RidsNrrDorlLpld (MMarshall) TQuay RidsNrrPMEBrown AKlein RidsNrrPMMChernoff DDuvigneaud RidsOpaMail RidsRgn2MailCenter (MWidmann, KClark, RJasinski LMellen, JShea, MLesser, CPayne, RidsOgcMailCenter (AHodgdon) SShaeffer, WBearden, TRoss)
RidsAcrsAcnwMailCenter RSubbaratnam YDiaz
May 30, 2006 List of Attendees Public Meeting with TVA April 5, 2006 U. S. NUCLEAR REGULATORY COMMISSION Catherine Haney, Director, Division of Operating Reactor Licensing (DORL)
Edwin Hackett, Associate Director, Division of Operating Reactor Licensing (DORL)
Michael Marshall, Branch Chief, LPLII-2, Division of Operating Reactor Licensing (DORL)
Sunil Weerakkody, Branch Chief, Fire Protection Branch Staff:
Margaret Chernoff Dylanne Duvigneaud Eva Brown Phil Qualls Ted Quay Chris Nolan Ray Gallucci Charles Payne Alex Klein TENNESSEE VALLEY AUTHORITY Masoud Bajestani - Unit 1 Vice President John Fornicola - Nuclear Assurance General Manager Bill Crouch - Site Licensing Manager Joe Valente - Unit 1 Engineering Manager Joe McCarthy - Unit 1 Licensing Supervisor David Burrell Rashid Abbas Stuart Kammer Steve Austin Rick Sampson Micky Heatherly Edward Vigluicci NUCLEAR ENERGY INSTITUTE Brandon Jamar Alex Marion Enclosure 1
May 30, 2006 Page 1 of 2 Tennessee Valley Authority BROWNS FERRY NUCLEAR PLANT cc:
Mr. Karl W. Singer Knoxville, TN 37902 Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, Tennessee 37402-2801 Mr. Ashok S. Bhatnagar, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, Vice President Nuclear Engineering & Technical Services Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Brian OGrady, Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Robert J. Beecken, Vice President Nuclear Support Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 General Counsel Tennessee Valley Authority ET 11A 400 West Summit Hill Drive
May 30, 2006 Mr. John C. Fornicola, Manager Nuclear Assurance and Licensing Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Bruce M. Aukland, Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Masoud Bajestani, Vice President Browns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Robert G. Jones, General Manager Browns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Scott M. Shaeffer Browns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.
Suite 23T85 Atlanta, GA 30303-8931 Mr. Larry S. Mellen Browns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.
Suite 23T85 Atlanta, GA 30303-8931 Page 2 of 2 Tennessee Valley Authority BROWNS FERRY NUCLEAR PLANT cc:
May 30, 2006 Mr. Glenn W. Morris, Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 Mr. William D. Crouch, Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Senior Resident Inspector U.S. Nuclear Regulatory Commission Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611 Tennessee Valley Authority