Duke Duke Energy Corporation Energy.
526 South Church St.
Charlotte, NC 28202 Apri 7,
006Mailing Address:
April 7, 2006 P0 Box 1006 Charlotte, NC 28201-1006 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION: Document Control Desk
Subject:
Duke Power Company LLC d/b/a Duke Energy Carolinas, LLC Oconee Nuclear Station, Units 1, 2, and 3 Docket Nos. 50-269, 50-270, 50-287 McGuire Nuclear Station, Units 1 and 2 Docket Nos. 50-369, 50-370 Catawba Nuclear Station, Units 1 and 2 Docket Nos. 50-413, 50-414 NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Request for Additional Information On September 13, 2004 the Nuclear Regulatory Commission (NRC) issued Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors." Duke Power, currently Duke Energy Carolinas (Duke) provided the required responses on March 1, 2005 and September 1, 2005.
On February 9, 2006, the NRC issued requests for additional information (RAI) for Oconee, McGuire and Catawba Nuclear Stations. RAls were also issued for other Pressurized Water Reactors (PWR) licensees regarding their responses to Generic Letter 2004-02.
Subsequent to these requests, on February 28, 2006, the Nuclear Energy Institute (NEI) submitted a request to extend the response dates to the RAls on behalf of PWR licensees. The requested relief was to provide supplements to the Generic Letter 2004-02 responses:
- by December 31, 2006 for units that complete their outage to incorporate strainer modifications on or before December 31, 2006, and
- within 90 days of outage completion, not to exceed December 31, 2007, for units that complete their outage to incorporate strainer modifications after December 31, 2006 but before December 31, 2007.
On March 3, 2006 the NRC provided a response to Anthony R. Pietrangelo of NEI granting the requested schedule relief.
This letter is being provided to inform the NRC that Duke will submit responses to RAIs contained in the February 9, 2006 letters by December 31, 2006.
www.duke-energy. con A
U. S. Nuclear Regulatory Commission April 7, 2006 Page 2 This correspondence contains no regulatory commitments. If any questions arise or additional information is needed, please contact Mary Shipley at (704) 382-5880.
Very truly yours, James R. Morris Vice President, Nuclear Support Nuclear Generation
e
.b I
U. S. IN'uclear Regulatory Commission April 7, 2006 Page 3 xc:
W. D. Travers, Region II Administrator U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center, 23 T85 61 Forsyth St., SW Atlanta, GA 30303-8931 L. N. Olshan, Senior Project Manager (ONS)
U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 G9A Rockville, MD 20852-2738 J. F. Stang, Jr., Senior Project Manager (CNS & MNS)
U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 H 4A Rockville, MD 20852-2738 M. C. Shannon NRC Senior Resident Inspector Oconee Nuclear Station J. B. Brady NRC Senior Resident Inspector McGuire Nuclear Station E. F. Giuthrie NRC Senior Resident Inspector Catawba Nuclear Station