ML060950065

From kanterella
Jump to navigation Jump to search

Issuance of Amendment Removal of Surveillance Requirement Performance Restrictions - Technical Specifications Reactivity Control Systems, Surveillance Requirement
ML060950065
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 04/04/2006
From: Stewart Bailey
Plant Licensing Branch III-2
To: Levis W
Public Service Enterprise Group
References
TAC MC8605
Download: ML060950065 (10)


Text

REACTIVITY CONTROL SYSTEMS SURVErLLANCE REQUIREMENTS (Continued)

b. At least once per 31 days by:
1. Verifying the continuity of the explosive charge.
2. Determining that the available weight of sodium pentaborate is greater than or equal to 5,776 lbs and the concentration of boron in solution is within the limits of Figure 3.1.5-1 by chemical analysis.*
3. Verifying that each valve (manual, power operated or automatic) in the flow path that is not locked, sealed, or otherwise secured in position, is in its correct position.
c. Demonstrating that, when tested pursuant to Specification 4.0.5, the minimum flow requirement of 41.2 gpm, per pump, at a pressure of greater than or equal to 1255 psig is met.
d. At least once per 18 months by:
1. Initiating one of the standby liquid control system subsystem, including an explosive valve, and verifying that a flow path from the pumps to the reactor pressure vessel is available by pumping demineralized water into the reactor vessel and verifying that the relief valve does not actuate. The replacement charge for the explosive valve shall be from the same manufactured batch as the one fired or from another batch which has been certified by having one of that batch successfully fired. Both injection subsystems shall be tested in 36 months.
2. **Demonstrating that all heat traced piping between the storage tank and the injection pumps is unblocked and then draining and flushing the piping with demineralized wate::.
3. Demonstrating that the storage tank heaters are OPERABLE by verifying the expected temperature rise of the sodium pentaborate solution in the storage tank after the heate::s are energized.
  • This test shall also be performed anytime water or boron is added to the solution or when the solution temperature drops below 700F.
    • "2his test shall also be performed whenever both heat tracing circuits have been found to be inoperable and may be performed by any series of sequential, overlapping or total flow path steps such that the entire!

flow path is included.

HOPE CREEK 3/4 1-20 Amendment No. 165

TABLE 4.3.2.1-1 (Continued)

ISOLATION ACTUATION INSTRUMENTATION SURVEILLANCE REQUIREMENTS CHANNEL OPERATIONAL CHANNEL FUNCTIONAL CHANNEL CONDITIONS FOR WHICH TRIP FUNCTION CHECK TEST CALIBRATION SURVEILLANCE REQUIRED HIGH PRESSURE COOLANT INJECTION SYSTEM ISOLATION (Continued)

h. HPCI Torus Compartment Temperature - High NA Q R 1, 2, 3
i. Drywell Pressure - High NA Q R 1, 2, 3
j. Manual Initiation NA R NA 1, 2, 3
7. RHR SYSTEM SHUTDOWN COOLING MODE ISOLATION
a. Reactor Vessel Water Level -

Low, Level 3 S Q R 1, 2, 3

b. Reactor Vessel (RHR Cut-in Permissive) Pressure - High NA Q R 1, 2, 3 C. Manual Initiation NA Q(a) NA 1, 2, 3
    • When any turbine stop valve is greater than 90% open and/or when the key-locked bypass switch is in the Norm position.

(a) Manual initiation switches shall be tested at least once per 18 months. All other circuitry associated with manual initiation shall receive a CHANNEL FUNCTIONAL TEST at least once per 92 days as part of circuitry required to be tested for automatic system isolation.

(b) Each train or logic channel shall be tested at least every other 92 days.

HOPE CREEK 3 /4 3-3 1 Amendment No. 165

TABLE 4.3.5.1-1 REACTOR CORE ISOLATION COOLING SYSTEM ACTUATION INSTRUMENTATION STIRVRTLLANTCE REQUIREMENS CHANNEL CHANNEL FUNCTIONAL CHANNEL FUNCTIONAL UNITS CHECK TEST CALIBRATION

a. Reactor Vessel Water Level -

Low Low, Level 2 S Q R

b. Reactor Vessel Water Level - High, Level 8 S Q R
c. Condensate Storage Tank Level - Low NA Q R
d. Manual Initiation NA Q(a) NA (a) Manual initiation switches shall be tested at least once per 18 months.

All other circuitry associated with manual initiation shall receive a CHANNEL FUNCTIONAL TEST at least once per 92 days as part of circuitry required to be tested for automatic system actuation.

HOPE CREEK 3 /4 3 -55 Amendment No. 165

CONTAINMENT SYSTEMS SURVEILLANCE REQUIREMENTS 4.6.3.1 Each primary containment isolation valve shown in Table 3.6.3-1 shall be demonstrated OPERABLE prior to returning the valve to service after maintenance, repair or replacement work is performed on the valve or its associated actuator, control or power circuit by cycling the valve through at least one complete cycle of full travel and verifying the specified isolation time.

4.6.3.2 Each primary containment automatic isolation valve shown in Table 3.6.3.-l shall be demonstrated OPERABLE at least once per 18 months by verifying that on a containment isolation test signal each automatic isolation valve actuates to its isolation position.

4.6.3.3 The isolation time of each primary containment power operated or automatic valve shown in Table 3.6.3-1 shall be determined to be within its limit when tested pursuant to Specification 4.0.5.

4.6.3.4 At least once per 18 months, verify that a representative sample of reactor instrumentation line excess flow check valves shown in Table 3.6.3-1 actuates to the isolation position on a simulated instrument line break signal.

4.6.3.5 Each traversing in-core probe system explosive isolation valve shall be demonstrated OPERABLE*:

c.. At least once per 31 days by verifying the continuity of the explosive charge.

b. At least once per 18 months by removing the explosive squib from at least one explosive valve such that each explosive squib in each explosive valve will be tested at least once per 90 months, and initiating the explosive squib. The replacement charge for the exploded squib shall be from the same manufactured batch as the one fired or from another batch which has been certified by having al:

least one of that batch successfully fired. No squib shall remain in use beyond the expiration of its shelf-life or operating life, as applicable.

HOPE C:REEK 3 /4 6-18 Amendment No. 155

CONTAINMENT SYSTEMS SECONDARY CONTAINMENT AUTOMATIC ISOLATION DAMPERS LIMIT-ING CONDITION FOR OPERATION 3.6.5.2 The secondary containment ventilation system (RBVS) automatic isolation dampers shown in Table 3.6.5.2-1 shall be OPERABLE with isolation times less than or equal to the times shown in Table 3.6.5.2-1.

APPLICABILITY: OPERATIONAL CONDITIONS 1, 2, 3 and *.

ACTION:

With one or more of the secondary containment ventilation system automatic isolation dampers shown in Table 3.6.5.2-1 inoperable, maintain at least cne isolation damper OPERABLE in each affected penetration that is open and within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> either:

a. Restore the inoperable dampers to OPERABLE status, or
b. Isolate each affected penetration by use of at least one deactivated damper secured in the isolation position, or
c. Isolate each affected penetration by use of at least one closed manual valve or blind flange.

Otherwise, in OPERATIONAL CONDITION 1, 2 or 3, be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Othenrise, in Operational Condition *, suspend handling of recently irradiated fuel in the secondary containment and operations with a potential for draining the reactor vessel. The provisions of Specification 3.0.3 are not applicable.

SURVE::LLANCE REQUIREMENTS 4.6.5.2 Each secondary containment ventilation system automatic isolation damper shown in Table 3.6.5.2-1 shall be demonstrated OPERABLE:

a. Prior to returning the damper to service after maintenance, repair o:r replacement work is performed on the damper or its associated actuator, control or power circuit by cycling the damper through at least one complete cycle of full travel and verifying the specified isolation time.
b. At least once per 18 months by verifying that on a containment isolation test signal each isolation damper actuates to its isolation position.
c. By verifying the isolation time to be within its limit at least once per 92 days.

HOPE CREEK 3/4 6-49 Amendment No. 165

PLANT SYSTEMS LIMITING CONDITION FOR OPERATION (Continued)

ACTION: (Continued)

,:. In OPERATIONAL CONDITION 4 or 5 with the SACS subsystem, which is associated with safety related equipment required OPERABLE by Specification 3.5.2, having two SACS pumps or one heat exchanger inoperable, declare the associated safety related equipment inoperable and take the ACTION required by Specification 3.5.2.

d. In OPERATIONAL CONDITION 5 with the SACS subsystem, which is associated with an RHR loop required OPERABLE by Specification 3.9.11.1 or 3.9.11.2, having two SACS pumps or one heat exchanger inoperable, declare the associated RHR system inoperable and take the ACTION required by Specification 3.9.11.1 or 3.9.11.2, as applicable.
e. In OPERATIONAL CONDITION 4, 5, or **, with one SACS subsystem, which is associated with safety related equipment required OPERABLE by Specification 3.8.1.2, inoperable, realign the associated diesel generators within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to the OPERABLE SACS subsystem, or declare the associated diesel generators inoperable and take the ACTION required by Specification 3.8.1.2. The provisions of Specification 3.0.3 are not applicable.

i-. In OPERATIONAL CONDITION 4, 5, or **, with only one SACS pump and heat exchanger and its associated flowpath OPERABLE, restore at least two pumps and two heat exchangers and associated flowpathas to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or, declare the associated safety related equipment inoperable and take the associated ACTION requirements.

SURVEILLANCE REQUIREMENTS 4.7.1.1 At least the above required safety auxiliaries cooling system subsystems shall be demonstrated OPERABLE:

e.. At least once per 31 days by verifying that each valve in the flow path that is not locked, sealed or otherwise secured in position.

is in its correct position.

b. At least once per 18 months by verifying that: 1) Each automatic valve servicing safety-related equipment actuates to its correct position on the appropriate test signal(s), and 2) Each pump starts automatically when its associated diesel generator automatically starts.

HOPE CREEK 3 /4 7-2 Amendment No. 165

PLANT SYSTEMS LIMITING CONDITION FOR OPERATION (Continued)

ACTIONg: (Continued)

b. In OPERATIONAL CONDITION 4 or 5:

With only one station service water pump and its associated flowpath OPERABLE, restore at least two pumps with at least one flow path to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or declare the associated.

SACS subsystem inoperable and take the ACTION required by Specification 3.7.1.1.

c. In OPERATIONAL CONDITION *:

With only one station service water pump and its associated flowpath OPERABLE, restore at least two pumps with at least one flow path to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or declare the associated SACS subsystem inoperable and take the ACTION required by Specification 3.7.1.1. The provisions of Specification 3.0.3 are not applicable.

SURVEILLANCE REQUIREMENTS 4.7.1.2 At least the above required station service water system loops shall be demonstrated OPERABLE:

a. At least once per 31 days by verifying that each valve (manual, power operated or automatic), servicing safety related equipment that is not locked, sealed or otherwise secured in position, is in its correct position.
b. At least once per 18 months, by verifying that:
1. Each automatic valve servicing non-safety related equipment actuates to its isolation position on an isolation test signal.
2. Each pump starts automatically when its associated diesel generator automatically starts.

HOPE CREEK 3/4 7-4 Amendment No. 165