SONGS 2 and 3 Summary of Meeting Dated 03/02/06
ML060690154
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 03/09/2006
From: Kalyanam N
Plant Licensing Branch III-2
To:
Office of Nuclear Reactor Regulation
Kalyanam N, NRR/DLPM, 415-1480
References
Download: ML060690154 (6)


Text

March 9, 2006 LICENSEE:

SOUTHERN CALIFORNIA EDISON (SCE)

FACILITIES:

SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 (SONGS 2 AND 3)

SUBJECT:

MEETING WITH REPRESENTATIVES OF SCE FOR SONGS 2 AND 3 A meeting was held on Thursday, March 2, 2006, between the Nuclear Regulatory Commission (NRC) staff and SCE, the licensee for SONGS 2 and 3. The meeting was held at the request of the licensee for it to present to the NRC staff its evaluation of the indications in the Unit 3 Control Element Drive Mechanism (CEDM) penetration 56 and repair alternatives. The notice for the meeting was issued on February 13, 2006.

During the Unit 3 outage in 2003, the inspection of the Unit 3 reactor vessel head (RVH) identified an indication on CEDM penetration 56 that was assumed to be a crack. Although SCE had approval to perform a weld overlay repair of RVH penetrations (ISI-3-8), this particular indication exceeded the generic 75 percent through-wall crack limit. Therefore, SCE submitted a specific relief request for CEDM penetration 56 (ISI-3-13). The NRC granted approval of this relief request for one cycle. SCE committed to evaluate repair alternatives for the long term.

With the Unit 3 refueling outage scheduled for October 2006, the licensee proposed its long-term disposition of penetration 56 by discussing repair alternatives, criteria for a contingency repair, appropriate contingency repair, planned actions, and implementation schedules. The NRC staff was appreciative of the presentation and stated it will perform a quick review on the general acceptability of SCEs approach and techniques and inform SCE of the staffs findings. is the list of attendees. Enclosure 2 is the material handed out by the licensee.

There was no handout from the NRC staff.

/RA/

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 50-362

Enclosures:

1. List of Attendees
2. Licensees Handout cc w/encls: See next page

LICENSEE:

SOUTHERN CALIFORNIA EDISON (SCE)

March 9, 2006 FACILITIES:

SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 (SONGS 2 AND 3)

SUBJECT:

MEETING WITH REPRESENTATIVES OF SCE FOR SONGS 2 AND 3 A meeting was held on Thursday, March 2, 2006, between the Nuclear Regulatory Commission (NRC) staff and SCE, the licensee for SONGS 2 and 3. The meeting was held at the request of the licensee for it to present to the NRC staff its evaluation of the indications in the Unit 3 Control Element Drive Mechanism (CEDM) penetration 56 and repair alternatives. The notice for the meeting was issued on February 13, 2006.

During the Unit 3 outage in 2003, the inspection of the Unit 3 reactor vessel head (RVH) identified an indication on CEDM penetration 56 that was assumed to be a crack. Although SCE had approval to perform a weld overlay repair of RVH penetrations (ISI-3-8), this particular indication exceeded the generic 75 percent through-wall crack limit. Therefore, SCE submitted a specific relief request for CEDM penetration 56 (ISI-3-13). The NRC granted approval of this relief request for one cycle. SCE committed to evaluate repair alternatives for the long term.

With the Unit 3 refueling outage scheduled for October 2006, the licensee proposed its long-term disposition of penetration 56 by discussing repair alternatives, criteria for a contingency repair, appropriate contingency repair, planned actions, and implementation schedules. The NRC staff was appreciative of the presentation and stated it will perform a quick review on the general acceptability of SCEs approach and techniques and inform SCE of the staffs findings. is the list of attendees. Enclosure 2 is the material handed out by the licensee.

There was no handout from the NRC staff.

/RA/

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 50-362

Enclosures:

1. List of Attendees
2. Licensees Handout cc w/encls: See next page DISTRIBUTION:

PUBLIC LPLIV Reading RidsNrrDorl (CHaney/CHolden)

RidsNrrDorlLplg (DTerao)

RidsNrrLALFeizollahi KGruss RidsNrrDciCpnb (TChan)

JCollins JTsao RidsNrrPMNKalyanam RidsOgcRp RidsRgn4MailCenter (TPruett)

RidsAcrsAcnwMailCenter RJasinski (Comm. Analyst)

JDixon-Herrity, RIV ADAMS ACCESSION NO. ML060690154 OFFICE LPL4/PM LPL4/LA LPL4/BC NAME NKalyanam LFeizollahi DTerao DATE 3/8/06 3/8/06 3/9/06 DOCUMENT NAME: E:\\Filenet\\ML060690154.wpd OFFICIAL RECORD COPY

LIST OF ATTENDEES AT THE MARCH 2, 2006, MEETING NAME AFFILIATION M. Short SCE A.E. Scherer SCE J. Rainsberry SCE T. Raidy SCE M. Devitt SCE W. Bramford Westinghouse J. Lareau Westinghouse D. Terao NRR/DORL/LPLIV K. Gruss NRR/DCI/CFEB T. Chan NRR/DCI/CPNB J. Collins NRR/DCI/CPNB J. Tsao NRR/DCI/CFEB N. Kalyanam NRR/DORL/LPLIV Where:

SCE

= Southern California Edison NRR

= Office of Nuclear Reactor Regulation DORL

= Division of Operating Reactor Licensing LPLIV

= Plant Licensing Branch IV DCI

= Division of Component Integrity CFNB

= Piping & NDE Branch CFEB

= Flaw Evaluation & Welding Branch ENCLOSURE 1

LICENSEE'S HANDOUT FOR MARCH 2, 2006, MEETING LONG-TERM DISPOSITION OF CONTROL ELEMENT DRIVE MOTOR PENETRATION # 56 SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 3 SOUTHERN CALIFORNIA EDISON ENCLOSURE 2

February 2006 San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Daniel P. Breig Southern California Edison Company San Onofre Nuclear Generating Station P. O. Box 128 San Clemente, CA 92674-0128 Mr. Douglas K. Porter, Esquire Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA 91770 Mr. David Spath, Chief Division of Drinking Water and Environmental Management P. O. Box 942732 Sacramento, CA 94234-7320 Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, CA 92101 Mark L. Parsons Deputy City Attorney City of Riverside 3900 Main Street Riverside, CA 92522 Mr. Gary L. Nolff Assistant Director - Resources City of Riverside 3900 Main Street Riverside, CA 92522 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Mr. Michael Olson San Diego Gas & Electric Company P.O. Box 1831 San Diego, CA 92112-4150 Mr. Ed Bailey, Chief Radiologic Health Branch State Department of Health Services Post Office Box 997414 (MS7610)

Sacramento, CA 95899-7414 Resident Inspector/San Onofre NPS c/o U.S. Nuclear Regulatory Commission Post Office Box 4329 San Clemente, CA 92674 Mayor City of San Clemente 100 Avenida Presidio San Clemente, CA 92672 Mr. James T. Reilly Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814 Mr. Ray Waldo, Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128 Mr. Brian Katz Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128

February 2006 San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA 95899 Mr. A. Edward Scherer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128