February 17, 2006 Carolina Power and Light Company ATTN: Mr. James Scarola Vice President Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 28461

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER - BRUNSWICK STEAM ELECTRIC PLANT UNIT 2

Dear Mr. Scarola:

On February 7, 2006, we informed you in a letter from Charles A. Casto, Director, Division of Reactor Projects that we planned to conduct a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, during the week of February 27, 2006. The purpose of this inspection was to review the actions taken to address the Brunswick Unit 2 unplanned down-powers which resulted in Unit 2 crossing the threshold from Green to White for the Unplanned Power Changes per 7000 Critical Hours PI in the 4th Quarter of CY2005.

Specifically, the inspection was planned to review four of the seven risk significant performance issues that did not require a unit shutdown to complete your corrective action review. Currently, we understand that one of these four requires additional review on your part. Due to this additional review which may impact our February 27 inspection, plus several NRC inspection issues, we have decided to postpone this supplemental inspection until the week of June 5, 2006. We intend to complete the inspection at that time. However, if all of the involved issues cannot be fully inspected at that time due to the root cause(s) not being finalized, we will conduct another inspection after you notify us of their finalization.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

CP&L 2

Please contact me at (404) 562-4530 with any questions you may have regarding this letter.

Sincerely,

/RA/

Paul E. Fredrickson, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 50-324 License No: DPR-62 cc: (See page 3)

CP&L 3

cc:

T. P. Cleary, Director Site Operations Brunswick Steam Electric Plant Progress Energy Carolinas, Inc.

Electronic Mail Distribution Benjamin C. Waldrep Plant Manager Brunswick Steam Electric Plant Carolina Power & Light Company Electronic Mail Distribution James W. Holt, Manager Performance Evaluation and Regulatory Affairs PEB 7 Carolina Power & Light Company Electronic Mail Distribution Edward T. O'Neil, Manager Support Services Carolina Power & Light Company Brunswick Steam Electric Plant Electronic Mail Distribution Garry D. Miller, Manager License Renewal Progress Energy Electronic Mail Distribution Lenny Beller, Supervisor Licensing/Regulatory Programs Carolina Power and Light Company Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution James Ross Nuclear Energy Institute Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Acting Director Division of Radiation Protection N. C. Department of Environment and Natural Resources Electronic Mail Distribution Peggy Force Assistant Attorney General State of North Carolina Electronic Mail Distribution Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Public Service Commission State of South Carolina P. O. Box 11649 Columbia, SC 29211 David R. Sandifer Brunswick County Board of Commissioners P. O. Box 249 Bolivia, NC 28422 Warren Lee Emergency Management Director New Hanover County Department of Emergency Management P. O. Box 1525 Wilmington, NC 28402-1525 Distribution (See page 4)

OFFICE DRP:RII SIGNATURE PEF NAME PFredrickson DATE 02/17/2006 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO