MONTHYEARML0524403982005-08-28028 August 2005 Supplemental Information Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 (License Amendment Request (LAR) 05-0002; TAC No. MC6888) Project stage: Supplement ML0525100472005-09-14014 September 2005 Davis-Besse, Unit 1 - Request for Withholding Information from the Public Disclosure Project stage: Withholding Request Acceptance ML0526402162005-09-15015 September 2005 Supplemental Information Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 (License Amendment Request (LAR) 05-0002; TAC No. MC6888) Project stage: Supplement ML0535500162005-12-22022 December 2005 Request for Additional Information Related to License Amendment Request Project stage: RAI ML0601802562006-01-12012 January 2006 Third Supplemental Letter Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 (License Amendment Request (LAR) 05-002) Project stage: Supplement ML0601802832006-01-13013 January 2006 Fourth Supplemental Letter Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 Project stage: Supplement ML0604400142006-02-0909 February 2006 Fifth Supplemental Letter Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 Project stage: Supplement ML0606100712006-02-28028 February 2006 Sixth Supplemental Letter Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 Project stage: Supplement ML0606700442006-03-0202 March 2006 Tech Spec Pages for Amendment 274 Framatome Mark B-HTP Fuel Design for Cycle 15 Project stage: Other ML0604005522006-03-0202 March 2006 License Amendment 274 Framatome Mark B-HTP Fuel Design for Cycle 15 Project stage: Approval 2006-01-12
[Table View] |
|
---|
Category:Letter
MONTHYEARML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant ML24045A0322023-10-26026 October 2023 L-23-221 Proposed Exam Submittal Cover Letter L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments 2024-09-06
[Table view] |
Text
FENOC 5501 North State Route 2 FirstEnergy Nuclear Operating Company Oak Harbor, Ohio 43449 Mark . Bezila 419-321-7676 Vice President - Nuclear Fax: 419-321-7582 Docket Number 50-346 10 CFR 50.90 License Number NPF-3 Serial Number 3226 February 9, 2006 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
Davis-Besse Nuclear Power Station Fifth Supplemental Letter Regarding License Amendment Application to Support Mark B-HTP Fuel Design for Cycle 15 (License Amendment Request (LAR) 05-0002; TAC No. MC6888)
Ladies and Gentlemen:
By letter dated May 2, 2005 (Serial Number 3131), as supplemented on August 28, 2005 (Serial Number 3166), September 15, 2005 (Serial Number 3183), January 12, 2006 (Serial Number 3213) and January 13, 2006 (Serial Number 3214), the FirstEnergy Nuclear Operating Company (FENOC) submitted License Amendment Request (LAR) 05-0002, an application for amendment of the Operating License, Appendix A, Technical Specifications (TS) for the Davis-Besse Nuclear Power Station (DBNPS). The proposed amendment would revise TS Section 2.1.1, "Safety Limits - Reactor Core," and TS Section 2.2.1, "Limiting Safety System Settings - Reactor Protection System Setpoints" to support use of the Framatome Mark B-HTP Fuel design for Cycle 15, which is scheduled to begin following refueling in March 2006. This letter provides a fifth supplement to the license amendment application, in response to the NRC's January 19, 2005 informal request for clarification of proposed licensing basis changes associated with FENOC Serial Number 3213.
FENOC will revise the Technical Specification Bases to add the following definition of the pre-defined as-found acceptance criteria band for Reactor Protection System Functional Unit 7: "The pre-defined as-found acceptance criteria band is determined by adding or subtracting (as applicable) credible uncertainties to the as-left value from the most recently completed surveillance test. Credible uncertainties include instrument uncertainties during normal operation including drift and measurement and test equipment uncertainties. In no case shall the pre-defined as-found acceptance criteria band overlap the Allowable Value. If one end of the pre-defined as-found acceptance criteria band
Docket Number 50-346 License Number NPF-3 Serial Number 3226 Page 2 is truncated due to its proximity to the Allowable Value, this does not affect the other end of the pre-defined as-found acceptance criteria band. If equipment is replaced, such that the previous as-left value is not applicable to the current configuration, the as-found acceptance criteria band is not applicable to calibration activities performed immediately following the equipment replacement."
A list of regulatory commitments made in this letter is included in Enclosure 1.
If there are any questions or if additional information is required, please contact Mr. Gregory A. Dunn, Manager - FENOC Fleet Licensing, at (330) 315-7243.
The statements contained in this submittal, including its associated enclosures are true and correct to the best of my knowledge and belief. I am authorized by the FirstEnergy Nuclear Operating Company to make this submittal. I declare under penalty of perjury that the foregoing is true and correct.
Executed on: _ _ _ _ _ _ _ _ _ _
Byf 4 M Bezi a, Vice President-Nuclear MSH Enclosure cc: Regional Administrator, NRC Region III Executive Director, Ohio Emergency Management Agency, State of Ohio (NRC Liaison)
DB-1 NRC/NRR Project Manager DB- 1 NRC Senior Resident Inspector Utility Radiological Safety Board
Docket Number 50-346 License Number NPF-3 Serial Number 3226 Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station, Unit Number 1, (DBNPS) in this document. Any other actions discussed in the submittal represent intended or planned actions by the DBNPS. They are described only for information and are not regulatory commitments. Please notify Gregory A. Dunn, Manager -
Fleet Licensing (330-315-7243) of any questions regarding this document or associated regulatory commitments.
COMMITMENTS DUE DATE
+
FENOC will revise the Technical Specification Bases to Concurrent with add the following definition of the pre-defined as-found implementation of License acceptance criteria band for Reactor Protection System Amendment Request Functional Unit 7: "The pre-defined as-found acceptance (LAR) 05-0002 criteria band is determined by adding or subtracting (as applicable) credible uncertainties to the as-left value from the most recently completed surveillance test. Credible uncertainties include instrument uncertainties during normal operation including drift and measurement and test equipment uncertainties. In no case shall the pre-defined as-found acceptance criteria band overlap the Allowable Value. If one end of the pre-defined as-found acceptance criteria band is truncated due to its proximity to the Allowable Value, this does not affect the other end of the pre-defined as-found acceptance criteria band. If equipment is replaced, such that the previous as-left value is not applicable to the current configuration, the as-found acceptance criteria band is not applicable to calibration activities performed immediately following the equipment replacement."