Letter Sequence Other |
---|
|
|
MONTHYEARML0601201042006-01-27027 January 2006 Request for Authorization to Extend the Third 10-Year ISI Interval for Reactor Vessel Visual Examination, MC6546 Project stage: Other 2006-01-27
[Table View] |
|
---|
Category:Code Relief or Alternative
MONTHYEARML21299A0032021-10-28028 October 2021 and Waterford Steam Electric Station, Unit 3 - Approval of Request for Alternative EN-20-RR-003 from Certain Requirements of the ASME Code ML20365A0012021-01-19019 January 2021 Relief Request 5-8 Related to ASME Code Case N-729-4 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles ML20282A7642020-10-16016 October 2020 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant - Relief Request 5-8 for Alternate Repair of Reactor Closure Head Penetration Nozzles ML20275A3432020-10-0101 October 2020 Verbal Authorization for Proposed Alternative (RR 5-8) Reactor Vessel Closure Head Penetration Repairs ML20272A1662020-09-30030 September 2020 Attachment 3 - Framatome Document No. ANP-3876, Revision 1Q1NP, Response to NRC Request for Additional Information of Palisades Relief Request Number RR 5-8, Repair of Reactor Pressure Vessel Head Penetration, Inservice Inspection Program, ML20267A3872020-09-23023 September 2020 Relief Request Number RR 5-8, Proposed Alternative to ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations ML20267A3882020-09-23023 September 2020 Attachment 1 - Relief Request Number RR 5-8, Proposed Alternative to ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations CNRO-2020-00016, Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2020-08-12012 August 2020 Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 CNRO-2019-00002, Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 12019-01-31031 January 2019 Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 CNRO-2017-00022, Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 12017-11-17017 November 2017 Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 1 ML21067A4982017-09-0707 September 2017 Relief Request No. RR 5-4 Proposed Alternative, Weld Reference System ML17194A8072017-08-14014 August 2017 Relief Request No. RR 4-25 Limited Coverage Examinations During the Fourth 10-Year Inservice Inspection Interval ML17137A0282017-06-29029 June 2017 Relief Request Number RR 5; 5 Proposed Alternative, Under-Vessel Leakage Examination ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16022A1072016-02-0101 February 2016 Relief Request Number RR 4-23- Proposed Alternative Concerning ASME Code Depth Sizing Requirement ML15320A2442015-11-25025 November 2015 Relief Request Number 5-1, Proposed Alternative, Extend the Current ASME Code of Record Into the Fifth 10-Year ISI Interval for ISI Related Activities PNP 2015-073, Forwards Response to Request for Additional Information Regarding Relief Request Number RR 4-22 - Proposed Alternative, Use of Alternate ASME Code Case N-770-1 Baseline Examination2015-09-17017 September 2015 Forwards Response to Request for Additional Information Regarding Relief Request Number RR 4-22 - Proposed Alternative, Use of Alternate ASME Code Case N-770-1 Baseline Examination PNP 2015-075, Submittal of Relief Request Number RR 4-23, Proposed Alternative Concerning ASME Code Depth Sizing Requirement2015-09-16016 September 2015 Submittal of Relief Request Number RR 4-23, Proposed Alternative Concerning ASME Code Depth Sizing Requirement CNRO-2015-00017, Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, D2015-06-0505 June 2015 Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, Division PNP 2015-024, Requests Relief of Proposed Alternatives for the Fifth 10-Year Inservice Test Interval2015-05-19019 May 2015 Requests Relief of Proposed Alternatives for the Fifth 10-Year Inservice Test Interval PNP 2015-022, Relief Request Number RR 5-1, Proposed Alternative, Extend the Current ASME Code of Record Into the Fifth 10-year ISI Interval for ISI Related Activities2015-04-29029 April 2015 Relief Request Number RR 5-1, Proposed Alternative, Extend the Current ASME Code of Record Into the Fifth 10-year ISI Interval for ISI Related Activities ML14199A5572014-08-13013 August 2014 Relief Request Number RR-4-19, Proposed Alternative to the Requirements of ASME Code Case N-638-4 ML12258A3522012-09-26026 September 2012 Relief from Certain Requirements of the ASME Code Case N-77-1 for the Fourth 10-Year Inservice Inspection Interval CNRO-2008-00035, Follow-up to Request for Extension of Discretion for the Interim Enforcement Policy for Fire Protection Issues on 10CFR50.48(c), National Fire Protection Association Standard NFPA 8052008-11-20020 November 2008 Follow-up to Request for Extension of Discretion for the Interim Enforcement Policy for Fire Protection Issues on 10CFR50.48(c), National Fire Protection Association Standard NFPA 805 ML0824801002008-09-19019 September 2008 Acceptance of Requested Licensing Action Relief Request and Supporting Amendment to Extend the Third 10-Year Inservice Inspection Interval for Reactor Vessel Weld Examination ML0726304272007-09-21021 September 2007 Relief, Request Relief No. 1 - from Requirements of American Society of Mechanical Engineers Boiler and Pressure Vessel Code Requirements for Repair of Pressurizer Nozzle Penetrations ML0719002512007-09-12012 September 2007 Relief Request 1 for the Repair of Reactor Vessel Closure Head Penetrations ML0716201362007-09-12012 September 2007 Relief Request 2 for ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations ML0716302482007-05-31031 May 2007 Request for Relief from ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Vent Line Penetration ML0709200292007-04-30030 April 2007 Request for Relief from ASME Code Regarding Weld Reference System, Relief Request No. RR 4-11 ML0617103642006-07-0303 July 2006 Monticello Nuclear Generating Plant, Palisades Nuclear Plant, Point Beach Nuclear Plant Units 1 and 2, Prairie Island Nuclear Generating Plant, Units 1 and 2 - Use of ASME Code Case N-513-2 ML0607902512006-04-0303 April 2006 Request for Relief from ASME Code, Section XI, Requirements for Repair of Pressurizer Nozzle Penetrations ML0607900612006-04-0303 April 2006 Request for Authorization to Use Alternatives to ASME Code, Section XI, IWA-3300, IWBb-3142.4, IWB-3420, and IWB-3613 for Reactor Pressure Vessel Head Penetration Repair ML0608003192006-04-0303 April 2006 Request for Authorization to Use Alternatives to ASME Code, Section XI, IWA-4120 for Reactor Pressure Vessel Head Penetration Repair ML0605800602006-03-21021 March 2006 Request for Authorization of Relief Request Number 1 for Certain Requirements in ASME Code, Section XI, Code Case N-638-1 ML0601201042006-01-27027 January 2006 Request for Authorization to Extend the Third 10-Year ISI Interval for Reactor Vessel Visual Examination, MC6546 ML0532002962005-11-29029 November 2005 Request for Authorization to Extend the Third Inservice Inspection Interval for Reactor Vessel Weld Examination ML0520706392005-08-17017 August 2005 Revised Relief Requests 28, 30, and 31 for 3rd 10-year Pump and Valve Inservice Testing ML0436504802005-01-18018 January 2005 Relief Request to Use Code Case N-661, and Safety Evaluation ML0430901912004-11-0808 November 2004 Relief, ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations ML0430605712004-11-0303 November 2004 Verbal Authorization of Relief from ASME Section XI Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations ML0419103642004-09-14014 September 2004 Relief, Third 10-Year Interval Inservice Inspection Program Plan ML0422402492004-08-0909 August 2004 Request for Relief from ASME Section XI Code Requirements for Repair of Pressurizer Nozzle Penetrations ML0401607382004-02-26026 February 2004 Prairie, Units 1 and 2, Kewaunee, Point Beach, Units 1 and 2, Palisades, Re Request for Alternatives to ASME Section XI, Appendix Viii, Supplement 10 ML0311505002003-05-19019 May 2003 Risk-Informed Inservice Inspection Program TAC No. MB4420 ML0306906292003-03-20020 March 2003 3/20/2003, Palisades, Relief, Re Third Inservice Inspection Interval Program ML0207202292002-03-0101 March 2002 Relief Code, Relief Request for Alternate ASME Code, Section XI, Risk-Informed Inservice Inspection Program ML0207201452002-02-27027 February 2002 Code Relief, Request for Relief from ASME Code Requirements for Inservice Inspection Pressure Test Program (Relief Request PR-07) 2021-10-28
[Table view] Category:Letter
MONTHYEARML24022A1172024-01-23023 January 2024 Acceptance of Requested Licensing Action Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24012A2422024-01-16016 January 2024 Acceptance of Requested Licensing Action License Transfer Request ML23236A0042023-12-27027 December 2023 Issuance of Amendment 274 Re Changes to Perm Defueled Emergency Plan and Perm Defueled Emergency Action Level Scheme ML23355A1242023-12-26026 December 2023 Withdrawal of an Amendment Request Re License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML23192A0772023-12-26026 December 2023 Letter Exemption from the Requirements of 10 CFR 140.11(a)(4) Concerning Offsite Primary and Secondary Liability Insurance ML23191A5222023-12-22022 December 2023 Exemption Letter from the Requirements of 10 CFR 50.54(W)(1) Concerning Onsite Property Damage Insurance (EPID - L-2022-LLE-0032) ML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23291A4402023-11-0303 November 2023 Acceptance of Requested Licensing Action Request for Exemption from 10 CFR 50.82(a)(2) to Support Reauthorization of Power Operations IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23275A0012023-10-0202 October 2023 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable ML23215A2302023-08-0303 August 2023 Notice of Organization Change - Chief Nuclear Officer IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23087A0362023-05-0202 May 2023 PSDAR Review Letter ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML23038A0982023-03-15015 March 2023 Request for Withholding Information from Public Disclosure ML23095A0642023-03-14014 March 2023 American Nuclear Insurers, Notice of Cancellation Rescinded PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23052A1092023-02-17017 February 2023 FEMA Letter to NRC, Proposed Commission Paper Language for Palisades Nuclear Plant Emergency Plan Decommissioning Exemption Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) Holtec Decommissioning International, LLC, Palisades Nuclear Plant L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 ML22321A2852022-11-17017 November 2022 LLC Master Decommissioning Trust Agreement for Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance ML22292A2572022-10-25025 October 2022 Permanently Defueled Emergency Plan License Amendment RAI Letter 2024-01-23
[Table view] Category:Safety Evaluation
MONTHYEARML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML22039A1982022-05-13013 May 2022 Issuance of Amendment No. 272 Permanently Defueled Technical Specifications ML21292A1482021-12-13013 December 2021 Safety Evaluation Related to Request for Direct and Indirect Transfers of Control of Facility Operating License DPR-6 for Big Rock Point and Renewed Facility Operating License DPR-20 for Palisades Nuclear Plant and ISFSI (EPID L-2020-LLM-00 ML21292A1472021-12-13013 December 2021 Draft Conforming License Amendments - Palisades Nuclear Plant Renewed Facility Operating License DPR-20 and ISFSI and Big Rock Point Facility Operating License DPR-6 and ISFSI (EPID L-2020-LLM-0003) (Enclosure 2) ML20365A0012021-01-19019 January 2021 Relief Request 5-8 Related to ASME Code Case N-729-4 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles ML20226A2722020-08-18018 August 2020 Request to Use a Provision of a Later Edition of the ASME BPV Code, Section XI ML19317D8552019-12-30030 December 2019 Issuance of Amendment No. 271 Regarding Adoption of TSTF-425, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B ML19318E3942019-12-0202 December 2019 Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19198A0802019-08-20020 August 2019 Issuance of Amendments No. 269 Regarding Changes to NFPA 805 Modifications and Change to Full Compliance Implementation Date for the Fire Protection Program (Epids L-2018-LLA-0296 and L-2019-LLA-0049) ML19135A0502019-05-21021 May 2019 Correction to Safety Evaluation for Amendment No.268 Regarding Revision to Diesel Generator Undervoltage Start Surveillance Requirement ML19107A0532019-05-13013 May 2019 Issuance of Amendment No. 268 Regarding Revision to Diesel Generator Undervoltage Start Surveillance Requirement ML19112A3172019-04-26026 April 2019 Approval of Alternative for Repair of Reactor Pressure Vessel Head Penetrations ML18170A2192018-09-24024 September 2018 Issuance of Amendment Changes to the Emergency Plan for Permanently Defueled Condition (CAC No. MG0198; EPID L-2017-LLA-0305) ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 ML18114A4102018-06-0404 June 2018 Issuance of Amendment Regarding Administrative Controls for Permanently Defueled Condition (CAC No. MG0021; EPID L-2017-LLA-0266) ML18135A2632018-05-21021 May 2018 Relief Request No. RR 5-6 Alternate to the Reexamination Frequency for a Relevant Condition ML18039A2442018-02-27027 February 2018 Issuance of Amendment License Amendment Request to Change the Full Compliance Implementation Date for the Fire Protection Program Transition License Condition for Required Modifications ML17328B0332017-12-15015 December 2017 Issuance of Amendment Cyber Security Plan Implementation Schedule (CAC No. MF9523; EPID L-2017-LLA-0199) ML21067A4982017-09-0707 September 2017 Relief Request No. RR 5-4 Proposed Alternative, Weld Reference System ML17151A3502017-08-21021 August 2017 Approval of Certified Fuel Handler Training and Retraining Program ML17194A8072017-08-14014 August 2017 Relief Request No. RR 4-25 Limited Coverage Examinations During the Fourth 10-Year Inservice Inspection Interval ML17137A0282017-06-29029 June 2017 Relief Request Number RR 5; 5 Proposed Alternative, Under-Vessel Leakage Examination ML17121A5102017-06-0808 June 2017 Issuance of Amendment License Amendment Request for Editorial and Administrative Changes to Technical Specifications ML17082A4652017-05-30030 May 2017 Issuance of Amendment Application to Revise Technical Specifications to Adopt TSTF 545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing ML16300A0302016-12-19019 December 2016 Issuance of Amendment Revision to the Requirements for Steam Generator Tube Inspections and Repair Criteria in the Cold Leg Tube Sheet Region ML16281A4982016-10-28028 October 2016 Issuance of Amendment No. 260, Revise License Condition 2.C.(4) and Technical Specifications Related to Control Rod Drive Exercise Surveillance ML16251A6202016-09-13013 September 2016 Entergy Fleet Request for Approval of Change to the Entergy Quality Assurance Program Manual (CAC Nos. MF7086 - MF7097) ML16014A3182016-08-22022 August 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16093A0282016-05-31031 May 2016 Entergy Services, Inc., Proposed Alternative to Utilize ASME Code Case N-789-1, Relief Request RR-EN-15-1, Revision 1 ML16078A0682016-05-0202 May 2016 Issuance of Amendment Cyber Security Plan Implementation Schedule ML16043A4852016-03-14014 March 2016 Relief Request Number RR 4-24 - Proposed Alternative, Use of Alternate ASME Code Case N-770-1 Baseline Examination ML16022A1072016-02-0101 February 2016 Relief Request Number RR 4-23- Proposed Alternative Concerning ASME Code Depth Sizing Requirement ML15334A3072015-12-22022 December 2015 Relief Request Numbers RR 5-2 and 5-3, Proposed Alternative to the Requirements of the ASME OM Code for the Fifth 10-Year Inservice Test Interval ML15320A2442015-11-25025 November 2015 Relief Request Number 5-1, Proposed Alternative, Extend the Current ASME Code of Record Into the Fifth 10-Year ISI Interval for ISI Related Activities ML15103A0592015-05-18018 May 2015 Issuance of Amendment Adoption of TSTF-426, Revision 5, Revise or Add Actions to Preclude Entry Into Limiting Condition for Operation 3.0.3 - RITSTF Initiatives 6B and 6C. ML15055A1062015-04-22022 April 2015 Issuance of Amendment License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times ML15007A1912015-02-27027 February 2015 Issuance of Amendment Regarding Transition to a Risk-Informed, Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) ML14237A1442014-12-0808 December 2014 Issuance of Amendment Cyber Security Plan Implementation Schedule ML14283A2872014-10-22022 October 2014 Issuance of Amendment Application for Technical Specification Change (TSTF-427) to Add Limiting Condition for Operation 3.0.9 Regarding the Unavailability of Barriers Using the Consolidated Line Item Improvement Process ML14223B2262014-09-0404 September 2014 Proposed Alternative, Use of Alternate ASME Code Case N-770-1 Baseline Examination ML14199A5572014-08-13013 August 2014 Relief Request Number RR-4-19, Proposed Alternative to the Requirements of ASME Code Case N-638-4 ML14210A2662014-08-0808 August 2014 Arkansas, Units 1 & 2, Big Rock Point, James A. Fitzpatrick, Grand Gulf, Unit 1, Indian Point, Units 1, 2 & 3, Palisades, Pilgrim, River Bend, Unit 1, Vermont Yankee, Waterford, Safety Evaluation Quality Assurance Program Manual, Rev. 24 & ML13312A4232013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13129A2192013-05-29029 May 2013 Staff Assessment in Response to Recommendation 9.3 of the Near-Term Task Force Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident ML13025A3062013-03-14014 March 2013 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Correction to Amendments Issued on 12/28/12, Revise QA Program Manual and Staff Qualification Technical Specifications ML13056A5142013-02-28028 February 2013 Non-Proprietary Issuance of Amendment Regarding Replacement of Spent Fuel Pool Region 1 Storage Racks 2023-05-01
[Table view] |
Text
January 27, 2006 Mr. Paul A. Harden Site Vice President Nuclear Management Company, LLC Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
SUBJECT:
PALISADES NUCLEAR PLANT REQUEST FOR AUTHORIZATION TO EXTEND THE THIRD 10-YEAR INSERVICE INSPECTION (ISI) INTERVAL FOR REACTOR VESSEL VISUAL EXAMINATION (TAC NO. MC6546)
Dear Mr. Harden:
Nuclear Management Company, LLCs (NMCs) letter of March 31, 2005, submitted a request for authorization to extend the third 10-year ISI interval for the visual examination of the reactor vessel interior attachments and the core support structure for one refueling cycle at Palisades Nuclear Plant. Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(a)(3)(ii), NMC requested authorization to use an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Paragraph IWB-2412, Inspection Program B, for the Palisades Nuclear Plant.
The staff has completed its review of NMCs request, and concludes that the proposed alternative is justified on the basis that compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Furthermore, the staff concludes that NMCs proposed alterative provides reasonable assurance of structural integrity of the subject components. Therefore, NMCs request for relief is authorized pursuant to 10 CFR 50.55a(a)(3)(ii) until the end of the fall 2007, refueling outage.
Enclosed is our safety evaluation.
Sincerely,
/RA/
Timothy J. Kobetz, Acting Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
Safety Evaluation cc w/encl: See next page
January 27, 2006 Mr. Paul A. Harden Site Vice President Nuclear Management Company, LLC Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
SUBJECT:
PALISADES NUCLEAR PLANT REQUEST FOR AUTHORIZATION TO EXTEND THE THIRD 10-YEAR INSERVICE INSPECTION (ISI) INTERVAL FOR REACTOR VESSEL VISUAL EXAMINATION (TAC NO. MC6546)
Dear Mr. Harden:
Nuclear Management Company, LLCs (NMCs) letter of March 31, 2005, submitted a request for authorization to extend the third 10-year ISI interval for the visual examination of the reactor vessel interior attachments and the core support structure for one refueling cycle at Palisades Nuclear Plant. Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(a)(3)(ii), NMC requested authorization to use an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Paragraph IWB-2412, Inspection Program B, for the Palisades Nuclear Plant.
The staff has completed its review of NMCs request, and concludes that the proposed alternative is justified on the basis that compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Furthermore, the staff concludes that NMCs proposed alterative provides reasonable assurance of structural integrity of the subject components. Therefore, NMCs request for relief is authorized pursuant to 10 CFR 50.55a(a)(3)(ii) until the end of the fall 2007, refueling outage.
Enclosed is our safety evaluation.
Sincerely,
/RA/
Timothy J. Kobetz, Acting Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
Safety Evaluation cc w/encl: See next page DISTRIBUTION PUBLIC LPLIII-1 R/F OGC DWeaver MRubin ACRS THarris LPadovan TKobetz MMitchell DORL DPR CLipa, RGN-III ADAMS Accession Number: ML060120104 OFFICE NRR/LPL3-1/PM NRR/LPL3-1/LA DCI/CVIB OGC NRR/LPL3-1/BC(A)
NAME LPadovan THarris MMitchell JZorn TKobetz DATE 1/17/06 1/17/06 1/12/06 1/24/06 1/27/06 OFFICIAL RECORD COPY
Palisades Plant cc:
Robert A. Fenech, Senior Vice President Michigan Department of Attorney General Nuclear, Fossil, and Hydro Operations Special Litigation Division Consumers Energy Company 525 West Ottawa St.
1945 Parnall Rd. Sixth Floor, G. Mennen Williams Building Jackson, MI 49201 Lansing, MI 48913 Arunas T. Udrys, Esquire Michael B. Sellman Consumers Energy Company President and Chief Executive Officer 1 Energy Plaza Nuclear Management Company, LLC Jackson, MI 49201 700 First Street Hudson, MI 54016 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Jonathan Rogoff, Esquire Suite 210 Vice President, Counsel & Secretary 2443 Warrenville Road Nuclear Management Company, LLC Lisle, IL 60532-4351 700 First Street Hudson, WI 54016 Supervisor Covert Township Douglas E. Cooper P. O. Box 35 Senior Vice President - Group Operations Covert, MI 49043 Palisades Nuclear Plant Nuclear Management Company, LLC Office of the Governor 27780 Blue Star Memorial Highway P. O. Box 30013 Covert, MI 49043 Lansing, MI 48909 Stephen T. Wawro, Director U.S. Nuclear Regulatory Commission of Nuclear Assets Resident Inspector's Office Consumers Energy Company Palisades Plant Palisades Nuclear Plant 27782 Blue Star Memorial Highway 27780 Blue Star Memorial Highway Covert, MI 49043 Covert, MI 49043 Michigan Department of Environmental Quality Laurie A. Lahti, Manager Waste and Hazardous Materials Division Regulatory Affairs Hazardous Waste and Radiological Nuclear Management Company, LLC Protection Section Palisades Nuclear Plant Nuclear Facilities Unit 27780 Blue Star Memorial Highway Constitution Hall, Lower-Level North Covert, MI 49043 525 West Allegan Street P.O. Box 30241 Lansing, MI 48909-7741
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REQUEST FOR AUTHORIZATION TO EXTEND THE THIRD AMERICAN SOCIETY OF MECHANICAL ENGINEERS CODE, SECTION XI 10-YEAR INTERVAL FOR REACTOR VESSEL WELD EXAMINATION NUCLEAR MANAGEMENT COMPANY, LLC PALISADES NUCLEAR PLANT DOCKET NO. 50-255
1.0 INTRODUCTION
Nuclear Management Company, LLCs (NMCs) letter of March 31, 2005, requested authorization to extend the third 10-year inservice inspection (ISI) interval for the visual examination of the reactor vessel (RV) interior attachments and the core support structure for one refueling cycle at Palisades Nuclear Plant (Palisades). Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(a)(3)(ii), NMC requested authorization to use an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI, Paragraph IWB-2412, Inspection Program B, for the Palisades Nuclear Plant.
2.0 REGULATORY REQUIREMENTS Part 50.55a(g) requires that ISI of ASME Code Class 1, 2, and 3 components be performed in accordance with the applicable Edition of Section XI of the ASME Code and applicable Addenda, except where specific relief has been granted by the U.S. Nuclear Regulatory Commission (NRC) pursuant to 10 CFR 50.55a(g)(6)(i). The regulation at 10 CFR 50.55a(a)(3) states that alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if the applicant demonstrates that: (i) the proposed alternatives would provide an acceptable level of quality and safety, or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the preservice examination requirements, set forth in the ASME Code,Section XI, "Rules for lnservice Inspection of Nuclear Power Plant Components," to the extent practical within the ENCLOSURE
limitations of design, geometry, and materials of construction of the components. The regulations require that ISI of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of the ASME Code,Section XI incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein. The applicable ASME Code of record for the Palisades ISI program is the 1989 Edition, no addenda, of the ASME Code,Section XI. Palisades is currently in the third 10-year ISI interval, which began on May 12, 1995, and ends on December 12, 2006.
3.0 TECHNICAL EVALUATION
3.1 ASME Code,Section XI Requirement The requirements of the 1989 edition of ASME Code,Section XI, Article IWB-2412, Inspection Program B, include a visual examination of the RV interior attachments and the core support structure identified in Table IWB-2500-1, once each 10-year ISI interval. In accordance with Articles IWA-2430(d) and IWA-2430(e), the Palides third 10-year ISI interval is currently scheduled to conclude on or before December 12, 2006.
3.2 System/Component(s) for Which Relief is Requested ASME Code,Section XI, ASME Code,Section XI, Description Examination Category Item Number B-N-2 B13.50 Interior Attachments Within Beltline Region B-N-2 B13.60 Interior Attchments Beyond Beltline Region B-N-3 B13.70 Core Support Structure 3.3 Reason for Request (As stated)
An alternative is requested from the requirements of IWA-2432, Inspection Program B, that requires visual examination, of the reactor pressure vessel interior attachments and the core support structure, to be performed once each ten-year interval. Extension of the inspection interval for examination category B-N-2 and B-N-3 by one refueling cycle beyond the currently scheduled inspection is requested.
ASME Section XI requires that the visual exams of the reactor pressure vessel interior attachments and the core support structure, required by examination categories B-N-2 and B-N-3, be performed once every inspection interval. These exams are typically performed at the end of the interval during the same refueling outage as the reactor vessel mechanized exam. By letter dated March 31, 2005, NMC requested a one-cycle extension of the reactor vessel mechanized examination at Palisades Nuclear Plant.
Both of these exams require that the fuel and the core barrel be removed from the reactor vessel.
NMC is currently planning a full core offload in 2007, to allow for replacement of the reactor vessel head at Palisades Nuclear Plant. Replacement of the reactor vessel head will require a hole to be cut in the containment building, which would require all of the fuel to be removed from the vessel. The deferral of these examinations will allow them to be performed during a planned full core offload, which would reduce the dose and risk of having to perform the full core offload twice.
3.4 Proposed Alternative and Basis for Use (As stated)
The third inspection interval for Palisades started on May 12, 1995, and will end on December 12, 2006. This inspection interval includes credit for the IWA-2430(d) allowed one-year extension and an IWA-2430(e) allowed 215-day extension. The subject examinations are scheduled to be performed in the Spring 2006 refueling outage. The proposed inspection date is one refueling cycle beyond the Code-allowed inspection interval. In accordance with 10 CFR 50.55a(a)(3)(ii), this interval extension is requested on the basis that compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Examinations required by categories B-N-2 and B-N-3 involves removing all of the fuel and the core barrel from the reactor. Records indicate that when this was performed during the 1995 refueling outage, approximately 5.0 Rem of exposure was required for this exam. These visual exams of the reactor pressure vessel interior attachments and the core support structure have been performed several times at Palisades with no relevant indications noted during the examinations. These exams were last performed during the 1995 refueling outage with acceptable results. Additionally, review of industry surveys indicate that these exams have been performed many times by the industry without any reportable findings.
During the 2006 refueling outage, Palisades will be performing the ASME category B-N-1 visual examination. This includes the space above and below the reactor core that is made accessible for examination by the removal of components during normal refueling outages. This examination is required one each period and will provide reasonable assurance of structural integrity.
Therefore, in accordance with 10 CFR 50.55a(a)(3)(ii), this one-cycle interval extension is requested on the basis that compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
3.5 NRC Staff Evaluation Palisades is currently in the third 10-year ISI interval, which is 19 months beyond the original end date for the third 10-year ISI interval mandated by the ASME Code,Section XI, Article IWA-2432. Palisades previously invoked two provisions in the ASME Code,Section XI that allow for the 19-month extension in the third 10-year ISI interval. The first extension, permitted by Article IWA-2430(d) of the ASME Code,Section XI, is for 1 year beyond the original end date for the third 10-year ISI interval. The second extension, permitted by Article IWA-2430(e) of the ASME Code,Section XI, is for 215 days beyond the first 1-year extension. Therefore,
the current third 10-year ISI interval for Palisades, which began on May 12, 1995, and will end on December 12, 2006, includes both of the extensions allowed by the ASME Code,Section XI.
NMC has requested to extend the third 10-year ISI interval by one refueling cycle beyond the current end date of December 12, 2006. The requested extension applies only to the affected ASME Code,Section XI examination categories and item numbers shown in the table above.
Currently, these items, which include RV interior attachments, both within the beltline region and beyond the beltline region, as well as the core support structure, are scheduled for the ASME Code-required visual examinations during the spring 2006 refueling outage. NMC proposed that these visual examinations occur during the fall 2007 refueling outage, one refueling cycle beyond the end of the inspection interval. The third 10-year ISI interval would end at the conclusion of the fall 2007 refueling outage for the subject exams.
NMC indicated that the ASME Code-required visual examinations of the item numbers listed above would involve removing all of the fuel and the core barrel from the reactor. A full-core offload is currently planned for the fall 2007 refueling outage to facilitate replacing the RV head at Palisades. Therefore, performing the required visual examinations for the subject items during the originally-scheduled spring 2006 refueling outage would result in the need for core offloading during two consecutive refueling cycles. NMC stated that its records from the 1995 refueling outage, during which these visual examinations were last performed, indicate that approximately 5.0 Rem of exposure was required for the examinations. Performing the required visual examinations for the subject items during the originally-scheduled spring 2006 refueling outage would, therefore, likely result in relatively high accumulated dose during two consecutive refueling cycles.
NMC indicated that visual examinations of the RV interior attachments and the core support structure have been performed several times at Palisades with no relevant indications. These examinations provided acceptable results the last time they were performed during the 1995 refueling outage. Furthermore, NMC indicated that these visual examinations have been performed many times by the industry without any reportable findings.
Palisades will be performing the ASME Code,Section XI Examination Category B-N-1 visual examinations during the as-scheduled spring 2006 refueling outage. This examination will cover the regions of the RV that are accessible during normal refueling outages. It will include the areas above and below the reactor core. The ASME Code,Section XI requires this examination once each inspection period.
Based on the above considerations, the NRC staff concludes that performing these examinations as currently scheduled would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Previous examination of these components, the performance of Category B-N-1 examinations during the current third 10-year ISI interval, and NMCs proposed schedule to perform these examinations no later than the end of the fall 2007 refueling outage, collectively provide reasonable assurance of structural integrity of the subject components.
4.0 CONCLUSION
The NRC staff concludes that the ASME Code,Section XI, requirements, which set the end of the third 10-year ISI interval on December 12, 2006, pose a hardship or unusual difficulty without a compensating increase in the level of quality and safety for the subject ASME Code,Section XI, Examination Category B-N-2 and B-N-3 components. Furthermore, the staff concludes that NMCs proposed alterative provides reasonable assurance of structural integrity of the subject components. Therefore, NMCs request for relief is authorized pursuant to 10 CFR 50.55a(a)(3)(ii) until the end of the fall 2007 refueling outage. All other requirements of the ASME Code,Section XI, for which relief has not been specifically requested and approved, remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
Principal Contributor: C. Sydnor Date: January 27, 2006