January 9, 2006
EA-06-005; EA-06-006; EA-06-007
Jeffrey S. Forbes
Vice President Operations
Arkansas Nuclear One
Entergy Operations, Inc.
1448 S.R. 333
Russellville, AR 72801-0967
SUBJECT:
Acknowledgment of Receipt of Denial of Noncited Violations and Finding in NRC
Inspection Report 05000313/2005004 AND 05000368/2005004
Dear Mr. Forbes:
Thank you for your letter dated December 19, 2005, in response to our November 19, 2005,
letter and integrated inspection report. In your letter you contested the significance of one
Green finding concerning the failure to adequately scope the effects of maintenance on
pressurizer level instrumentation. You also disagreed with the characterization that two other
findings identified as noncited violations were violations of NRC regulations. These two findings
were documented in the inspection report as a noncited violation of 10 CFR 50.65(a)(4)
concerning the failure to adequately assess risk for an isolated electromatic relief valve, and a
noncited violation involving inadequate procedures leading to reactor coolant pump seal
damage. The NRC also determined that these findings contained crosscutting aspects in the
area of human performance. You requested that the NRC withdraw the three findings along
with the associated crosscutting aspects.
The NRC is reviewing your request and will inform you of the results of our review by separate
correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and
your response (if any) will be made available electronically for public inspection in the NRC
Public Document Room or from the Publicly Available Records (PARS) component of the
NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David N. Graves, Chief
Project Branch E
Division of Reactor Projects
Entergy Operations, Inc.
-2-
Dockets: 50-313
50-368
Licenses: DPR-51
cc:
Senior Vice President
& Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Vice President
Operations Support
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Manager, Washington Nuclear Operations
ABB Combustion Engineering Nuclear
Power
12300 Twinbrook Parkway, Suite 330
Rockville, MD 20852
County Judge of Pope County
Pope County Courthouse
100 West Main Street
Russellville, AR 72801
Winston & Strawn LLP
1700 K Street, N.W.
Washington, DC 20006-3817
Bernard Bevill
Radiation Control Team Leader
Division of Radiation Control and
Emergency Management
4815 West Markham Street, Mail Slot 30
Little Rock, AR 72205-3867
James Mallay
Director, Regulatory Affairs
Framatome ANP
3815 Old Forest Road
Lynchburg, VA 24501
Entergy Operations, Inc.
-3-
Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJC1)
Senior Resident Inspector (RWD)
Branch Chief, DRP/E (DNG)
Senior Project Engineer, DRP/E (VGG)
Team Leader, DRP/TSS (RLN1)
RITS Coordinator (KEG)
Only inspection reports to the following:
J. Dixon-Herrity, OEDO RIV Coordinator (JLD)
ROPreports
ANO Site Secretary (VLH)
SISP Review Completed: __DNG____
ADAMS: : Yes
G No Initials:DNG_____
- Publicly Available G Non-Publicly Available G Sensitive
- Non-Sensitive
R:\\_REACTORS\\_ANO\\2005\\ANO IR 2005-04 Denial Acknowledgment.wpd
RIV:SPE/DRP/E
C:DRP/E
VGGaddy
DNGraves
/RA/
/RA/
1/9/06
1/9/06
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax