MONTHYEARET 23-0006, CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components2023-05-17017 May 2023 CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components ET 23-0005, 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peen2023-03-16016 March 2023 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened ET 23-0003, License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications2023-03-0101 March 2023 License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 23-0004, Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2023-01-26026 January 2023 Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0010, License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2022-08-0202 August 2022 License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0011, Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface2022-05-31031 May 2022 Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface ET 22-0005, Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-04-13013 April 2022 Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0003, CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads2022-04-0606 April 2022 CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads ET 22-0002, Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head .2022-04-0404 April 2022 Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head . ET 22-0004, Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report2022-03-15015 March 2022 Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report ET 22-0001, Removal of the Table of Contents from the Technical Specifications2022-01-12012 January 2022 Removal of the Table of Contents from the Technical Specifications ET 21-0017, Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-12-22022 December 2021 Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0009, Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage2021-11-0101 November 2021 Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage ET 21-0015, Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-20020 October 2021 Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0012, Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-11011 October 2021 Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 21-0010, License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-09-29029 September 2021 License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0005, Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-1912021-08-12012 August 2021 Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 20-0013, Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415)2020-10-26026 October 2020 Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415) ET 20-0011, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-10-0101 October 2020 Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ET 20-0007, License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers2020-06-0808 June 2020 License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers ET 20-0008, Operating Corporation Update for Full Implementation of Open Phase Detection System2020-05-20020 May 2020 Operating Corporation Update for Full Implementation of Open Phase Detection System ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) ET 20-0002, Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 12020-01-29029 January 2020 Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 1 ET 19-0021, Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-12-0909 December 2019 Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0020, Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-11-13013 November 2019 Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0019, Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-09-10010 September 2019 Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0018, Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-08-22022 August 2019 Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0014, lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 12019-08-15015 August 2019 lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 1 ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0008, Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption.2019-03-0505 March 2019 Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption. ET 19-0003, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange2019-02-25025 February 2019 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange ET 19-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-01-23023 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 ET 18-0032, Operating Corporation Change of Date for Full Implementation of Open Phase Detection System2018-12-0707 December 2018 Operating Corporation Change of Date for Full Implementation of Open Phase Detection System ET 18-0035, Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-12-0606 December 2018 Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0029, (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection2018-10-31031 October 2018 (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection ET 18-0018, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-06-19019 June 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0016, Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information2018-05-29029 May 2018 Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information ET 18-0014, Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-05-29029 May 2018 Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ET 18-0013, Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld2018-05-0202 May 2018 Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld ET 18-0011, (WCGS) - Guarantee of Payment of Deferred Premiums2018-04-30030 April 2018 (WCGS) - Guarantee of Payment of Deferred Premiums ET 18-0012, Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-04-19019 April 2018 Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0010, Financial Protection Levels2018-03-29029 March 2018 Financial Protection Levels ET 18-0007, Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-02-15015 February 2018 Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ET 18-0005, Withdrawal of License Amendment Request for Revision to the Emergency Plan2018-02-0505 February 2018 Withdrawal of License Amendment Request for Revision to the Emergency Plan ET 18-0004, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-01-29029 January 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 17-0025, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term2017-11-14014 November 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term 2023-05-17
[Table view] |
Text
WeLF CREEK NUCLEAR OPERATING CORPORATION Terry J Garrett Vice President, Engineering November 18, 2005 ET 05-0022 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Reference:
Letter ET 05-0007, dated August 26, 2005, from T. J. Garrett, WCNOC, to the NRC
Subject:
Docket No. 50-482: Response to Request for Additional Information -
Reactor Coolant System Leakage Detection Instrumentation Gentlemen:
The Reference provided Wolf Creek Nuclear Operating Corporation's (WCNOC) application requesting approval of a change to Reactor Coolant System (RCS) leak detection instrumentation system methodology. The proposed change would revise the Bases for Technical Specification (TS) 3.4.13, -RCS Operational LEAKAGE," Bases for TS 3.4.15, "RCS Leakage Detection Instrumentation," Updated Safety Analysis Report (USAR) Appendix 3A, Section 5.2.5.2.3 and Table 5.2-6. This change would clarify the requirements of the containment atmosphere gaseous radioactivity monitor with regard to its RCS leak detection capability and provide clarification that the monitor can be considered OPERABLE (in compliance with TS Limiting Condition for Operation (LCO) 3.4.15) during all applicable MODES even when reactor coolant radioactivity levels are below the levels assumed in the original licensing basis for WCGS.
On October 3, 2005, a teleconference was held between the NRC Project Manager, WCNOC personnel, and AmerenUE personnel. As a result of the teleconference, on October 12, 2005, the NRC Project Manager provided by electronic mail a request for additional information to provide clarifying information provided by the Reference.
The Attachment to this letter provides WCNOC's response to the request for additional information. The additional information provided in the Attachment does not impact the conclusions of the No Significant Hazards Consideration provided in the Reference. In accordance with 10 CFR 50.91, a copy of this submittal is being provided to the designated Kansas State official.
P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer MIF/HCINET
ET 05-0022 Page 2 of 2 There are no commitments associated with this submittal. If you have any questions concerning this matter, please contact me at (620) 364-4084, or Mr. Kevin Moles at (620) 364-4126.
-Very tnJM yours, Terry J. Garrett TJG/rlg Attachment cc: T. A. Conley (KDHE), w/a J. N. Donohew (NRC), w/a W. B. Jones (NRC), w/a B. S. Mallett (NRC), w/a Senior Resident Inspector (NRC), w/a 1.
1; il I
STATE OF KANSAS
) SS COUNTY OF COFFEY Terry J. Garrett, of lawful age, being first duly sworn upon oath says that he is Vice President Engineering of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
Byv Terry BOarrett Vice President Engineering SUBSCRIBED and sworn to before me this 18 day of nfv , 2005.
2 XLza lSIATEOAIW MODAILOSIM Notary Public STATE F IAS Myp.Exp.
MAN Expiration Date A 10112 &D9
Attachment to ET 05-0022 Page 1 of 6 RESPONSES TO REQUEST FOR ADDITIONAL INFORMATION This Attachment provides Wolf Creek Nuclear Operating Corporation's (WCNOC's) response to an electronic request dated October 12, 2005 from the NRC Project Manager for additional information.
- 1. Given the discussion in the application on the containment atmosphere (gaseous) radioactivity monitor not being able to detect I gpm reactor coolant leakage in any way close to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> for the current normal radioactivity levels in the reactor coolant, explain why this monitor is being retained in Limiting Condition for Operation (LCO) 3.4.15.
Response
Technical Specification 3.4.15, "RCS Leakage Detection Instrumentation," has a fundamental objective to support 10 CFR 50, Appendix A, General Design Criteria (GDC) 30, "Quality of Reactor Coolant Pressure Boundary." Implementing guidance recognized that a diverse set of detection methods are necessary to assure effective monitoring. Diversity for this specification, contributes to redundancy under varying plant conditions.
WCNOC letter ET 05-0007, dated August 26, 2005, states, in part:
"Given the level of radioactivity in the reactor coolant at WCGS with no or minor fuel cladding defects, evaluation has shown that the containment atmosphere gaseous radioactivity monitors would not promptly detect a one gpm leak in one hour. This conclusion is based on a realistic nominal detector background level, with the typical RCS gaseous activity associated with no fuel cladding defects. For these lower RCS activity levels, the increase in detector count rate due to leakage will be partially masked by 1) the statistical variation of the minimum detector background count rate, and 2) the Ar-41 activation activity rendering reliable detection of a 1 gpm leak in one hour uncertain."
The Wolf Creek Generating Station (WCGS) Technical Specification (TS) Bases B 3.4.15, 'RCS Leakage Detection Instrumentation," states, in part:
"This LCO requires instruments of diverse monitoring principles to be OPERABLE to provide a high degree of confidence that extremely small leaks are detected in time to allow actions to place the plant in a safe condition, when RCS LEAKAGE indicates possible RCPB degradation."
Diverse monitoring principles are necessary because one monitored parameter will always lead the others depending on the actual or postulated plant conditions. USAR Section 5.2.6, provides a reference to WCAP-7503, Rev. 1, "Determination of Design Pipe Breaks for the Westinghouse Reactor Coolant System." This WCAP indicates that the knowledge of the existence of a leak inside containment is obtained from the induced variations of particulate activity, gaseous activity, and specific humidity in containment atmosphere. These three functions are assumed to have reached a steady state. With the initiation of a leak, a transient will take place, followed by a new steady state. The values of the particulate activity, gaseous activity, and specific humidity that define these different states are functions of the leakage, the
Attachment to ET 05-0022 Page 2 of 6 time, and parameters like containment volume and temperature, activity concentrations in the coolant for the considered isotopes, cooling coil heat removal capacity, and fan flows. The performance of any means of detection depends on the way the function is affected by the leak and the sensitivity of the instrument which measures it.
Regulatory Guide 1.45, "Reactor Coolant Pressure Boundary Leakage Detection Systems,"
defines the source term as: "in analyzing the sensitivity of leak detection systems using airborne particulate or gaseous radioactivity, a realistic primary coolant radioactivity concentration assumption should be used." The expected values used in the plant environmental report would be acceptable. The chart below provides a comparison of the RCS activity level during a period in 2003 to the values specified in the plant environmental report.
1/17/03 - 5/203 WCGS RCS )X-133 Data Plant Enronmental Report I **I -.. I .l ' . I . fi . . . .. i * 'I'Wl 1.OE-05 1.OE-04 1.OE-03 1.OE-02 1.OE-01 Percent Fuel Defect An evaluation performed in 2003 using current RCS activity levels resulted in a containment gaseous concentration at the end of 60 minutes to be -3.4E-08 pCi/cm3 (see Figure 1 below).
This evaluation confirmed the insensitivity of the containment atmosphere gaseous channels to low RCS activity.
Containment Gaseous Concentration from Low Activity RCS with 1 Gallon per Minute Leak I E-6 d ~1E-7 00
'too-.' E Q / .43E-08 1E-8 0 120 240 360 480 600 720 840 960 Figure 1 Time in Minutes NUREG/CR-6582, 'Assessment of Pressurized Water Reactor Primary System Leaks,"
December 1998, recognized that the containment atmosphere gaseous monitor is inherently less sensitive than the containment air-particulate monitor and functions in the event that significant reactor coolant gaseous activity exists as a result of fuel cladding defects. Sensitivity and response time depend on several factors, including containment vessel free volume; containment background activity, which varies with RCS leakage and fuel rod failures, and corrosion products concentration.
Attachment to ET 05-0022 Page 3 of 6 The gaseous activity in the containment atmosphere increases with the duration of the leak as shown in the below figure (Figure 10-7 from NUREG/CR-6582). Figure 10-7 also illustrates the masking effect of the Ar-41 background activation in air. The data in this figure is shown for activity of Xe-133 in reactor coolant equal to 4E+4 Bq/cm 3 (-1.0 pCi/cm3 ) and containment free volume equal to 73,700 M3 . The figure shows that a 2 gpm leak may be detected in about 40 minutes and a one gpm leak in about 80 minutes. In the absence of fuel failures, the corresponding leak detection time would be longer. (Note: the Y-axis of 0.01 to 10 Bq/cm 3 corresponds to 2.7E-07 to 2.7E-04 pCi/cm3 )
C 0
8 5
iW 30 40 50 60 70 80 lime after leak occurred (min.) c, C 10-7. Time-dependent gaseous activity increases resulting from reactor coolant leakagi 991). Copyright Elsevier Science Publishers; reprinted with pernission.
171 NUJRE(
171 NUREC
Attachment to ET 05-0022 Page 4 of 6 TS Limiting Condition for Operation (LCO) 3.4.16, "RCS Specific Activity," contains specific activity limits for both DOSE EQUIVALENT 1-131 and gross specific activity. The specific activity limits are intended to limit the 2-hour dose at the site boundary to a small fraction of the 10 CFR 100 dose guideline limits. The TS B 3.4.16 Bases indicates that the noble gas activity in the reactor coolant assumes 1% failed fuel, which closely equals the LCO limit of 100/E pCi/gm for gross specific activity. While TS 3.4.16 basis is to limit the 2-hour dose at the site boundary, it would allow plant operation at a reactor coolant activity level in which the containment atmosphere gaseous radiation monitor would be capable of detecting a 1 gpm leak in one hour.
Regulatory Guide 1.45, Section B, "Discussion," suggest that since the methods differ in sensitivity and response time, prudent selection of detection methods should include sufficient systems to assure effective monitoring during periods when some detection systems may be ineffective or inoperable. Some of these systems should serve as early alarm systems signaling the operators that closer examination of other detection systems is necessary to determine the extent of any corrective action that may be required. Position 5 in Section C, 'Regulatory Position," of the regulatory guide states: "The sensitivity and response time of each leakage detection system in regulatory position 3. above employed for unidentified leakage should be adequate to detect a leakage rate, or its equivalent, or one gpm in less than one hour."
Regulatory position 9 of the regulatory guide further states: "The technical specifications should include the limiting conditions for identified and unidentified leakage and address the availability of various types of instruments to assure adequate coverage at all times."
Based upon the above information, the proposed license amendment to maintain the containment atmosphere gaseous radiation monitor in Technical Specification 3.4.15 provides for sufficient diversity for detecting leakage during plant operation with licensed levels of RCS activity as a result of minor fuel cladding defects which could potentially occur in the future.
Attachment to ET 05-0022 Page 5 of 6
- 2. If it is unlikely that the containment atmosphere (gaseous) radioactivity monitor will detect 1 gpm reactor coolant leakage in any way close to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, provide the basis for listing this monitor in LCO 3.4.15.c together with the containment air cooler condensate monitoring system which, by the application, can detect this leakage in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
Response
Regulatory Position 3. of Regulatory Guide 1.45 states:
"At least three separate detection methods should be employed and two of these methods should be (1) sump level and flow monitoring and (2) airborne particulate radioactivity monitoring. The third method may be selected from the following:
- a. monitoring of condensate flow rate from air coolers,
- b. monitoring of airborne gaseous radioactivity.
Humidity, temperature, or pressure monitoring of the containment atmosphere should be considered as alarms or indirect indication of leakage to the containment."
The WCGS Technical Specifications were based on NUREG-0452, Revision 4, "Standard Technical Specifications for Westinghouse Pressurized Water Reactors." LCO 3.4.6.1 of the standard technical specifications stated:
"The following Reactor Coolant System Leakage Detection Systems shall be OPERABLE:
- a. The Containment Atmosphere [Gaseous or Particulate] Radioactivity Monitoring System,
- b. The Containment Pocket Sump Level and Flow Monitoring System, and
- c. Either the [containment air cooler condensate flow rate] or a Containment Atmosphere [Gaseous or Particulate] Radioactivity Monitoring System."
The WCGS Technical Specifications (NUREG-1136) were issued on March 11, 1985. LCO 3.4.6.1 of the specifications stated:
"The following Reactor Coolant System Leakage Detection Systems shall be OPERABLE:
- a. The Containment Atmosphere Particulate Radioactivity Monitoring System,
- b. The Containment Normal Sump Level Measurement System, and
- c. Either the Containment Air Cooler Condensate Flow Rate or the Containment Atmosphere Gaseous Radioactivity Monitoring System."
WCAP-7503, Rev. 1, states in part: "In regard to leakage detection, the earliest indication would be given by particulate activity detectors, assuming primary coolant leakage, corrosion product activity in the coolant, and a background below the threshold of detectibility. High condensate flow and a gaseous activity equal to twice the background would follow successively.
u '"Attachment to ET 05-0022 Page 6 of 6 Therefore, the basis for listing the containment atmosphere gaseous radioactivity monitor with the containment air cooler condensate flow rate is based on and consistent with the standard technical specifications (NUREG-0452, Rev. 4) and the information in WCAP-7503, Rev. 1.