Letter Sequence Other |
---|
|
|
MONTHYEARML0532700742005-11-13013 November 2005 G20050802/LTR-05-0570 - John Mccain Ltr Palo Verde Nuclear Generating Station - Recent Shutdown Project stage: Other ML0534004102005-12-22022 December 2005 G20050802/LTR-05-0570 - Dan Frenette Ltr Re. Palo Verde Nuclear Generating Station - Recent Shutdown Project stage: Other 2005-11-13
[Table View] |
G20050802/LTR-05-0570 - John Mccain Ltr Palo Verde Nuclear Generating Station - Recent ShutdownML053270074 |
Person / Time |
---|
Site: |
Palo Verde |
---|
Issue date: |
11/13/2005 |
---|
From: |
Mccain J US SEN (Senate) |
---|
To: |
Outlaw W Office of Congressional Affairs |
---|
Fields M B ,NRR/DLPM,415-3062 |
Shared Package |
---|
ML053400411 |
List: |
---|
References |
---|
FOIA/PA-2007-0093, FOIA/PA-2008-0118, FOIA/PA-2008-0174, FOIA/PA-2008-0201, FOIA/PA-2009-0107, G20050802, LTR-05-0570, TAC MC8958, TAC MC8959, TAC MC8960 |
Download: ML053270074 (4) |
|
|
---|
Category:Letter
MONTHYEARML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19
[Table view] Category:Congressional Correspondence
MONTHYEARML20084L1502020-03-18018 March 2020 03-18-20 Letter to Senator Jeffrey Merkley, Et Al., from NRC Secretary Annette Vietti-Cook Re Palo Verde Lt NRC-2018-0214, LTR-20-0091 Senator Jeffrey Merkley, Et Al., Letter Request for an Evidentiary Hearing with the NRC in Relation to the Acquisition of El Paso Electric by the Infrastructure Investments Fund Us Holding 22020-03-10010 March 2020 LTR-20-0091 Senator Jeffrey Merkley, Et Al., Letter Request for an Evidentiary Hearing with the NRC in Relation to the Acquisition of El Paso Electric by the Infrastructure Investments Fund Us Holding 2 ML19350A5442019-12-0909 December 2019 12-09-19 Letter to Congresswoman Escobar from Annette Vietti-Cook Regarding the Application by El Paso Electric Company for Transfer of Its Palo Verde Nuclear Generating Station and Independent Spent Fuel Storage Installation Licenses ML19330E9682019-11-26026 November 2019 LTR-19-0460 Acknowledgement Letter to Representative Escobar Indirect Transfer of Control of Licenses to Sun Jupiter Holdings ML0717302802007-06-26026 June 2007 G20070420/LTR-07-0414/EDATS: SECY-2007-0203 - Sen. Richard G. Lugar Ltr. Security at Nuclear Plants - Palo Verde ML0716602822007-06-0404 June 2007 G20070420/LTR-07-0414/EDATS: SECY-2007-0203 - Ltr. Sen. Richard G. Lugar Security at Nuclear Plants - Palo Verde ML0713703632007-05-0707 May 2007 G20070343/LTR-07-0348/EDATS:SECY-2007-0145 - Ltr. Rep. John Shadegg Re Unauthorized Access to Palo Verde Related Data ML0600605712006-01-24024 January 2006 G20050884/LTR-05-0613 - Sen. Jon Kyl Ltr Re. Concerns West Valley Facility - Palo Verde (Dan Frenette) ML0531300772005-11-22022 November 2005 G20050739/LTR-05-0519 - Rep.Trent Franks Ltr. Re. Palo Verde Nuclear Generating Station ML0532700742005-11-13013 November 2005 G20050802/LTR-05-0570 - John Mccain Ltr Palo Verde Nuclear Generating Station - Recent Shutdown ML0536202132005-11-0303 November 2005 G20050884/LTR-05-0613 - Incoming Letter from Sen. Jon Kyl Concerns West Valley Facility - Palo Verde (Dan Frenette) ML0530004242005-10-17017 October 2005 G20050739/LTR-05-0519 - Incoming LTR - Rep. Trent Franks Palo Verde Nuclear Generating Station ML0513103772005-04-29029 April 2005 End-of-Cycle Public Meeting Invitation Letter for Palo Verde ML0508705172005-03-0202 March 2005 G20050210/LTR-05-0153 - Ltr. Sen. John Mccain Re Constituent'S Concerns Regarding Water Contamination at Palo Verdi Nuclear Power Plant ML0806602012004-08-11011 August 2004 Letter to Honorable Jon Mccain Regarding Palo Verde Nuclear Station and Constituent Seth Campbell ML0915507602003-08-0505 August 2003 Letter to Mccain, Palo Verde Nuclear Power Plant (1 Page) Attaching 8/4/03 Letter to Mccain (1 Page), 8/3/03 Arizona Republic Article, A-plant Unit Down After Outage Will Resume Operation Monday (1 Page) Copyright, Fax Cover Sheet to Angel ML0807304862003-08-0505 August 2003 G20030485/LTR-03-0531 - Ltr. Robert Titlford Palo Verdo Outage ML0235701542002-12-12012 December 2002 Comment (15) Submitted by Rep. Bruce Smith on Petition for Rulemaking PRM 50-79 Re Protection for Day Care Centers and Nursery Schools in Radiological Emergency 2020-03-18
[Table view] |
Text
ED0 Principal Correspondence Control FROM : DUE: 12/14/05 ED0 CONTROL: 030050802 DOC DT: 11/13/05 FINAL REPLY:
Senator John McCain Outlaw, OCA FOR SIGNATURE OF : CRC NO: 05-0570 Reyes, ED0 DESC: ROUTING:
Palo Verde Nuclear Generating Station - Recent Reyes Shutdown (Dan Frenettel Virgilio Xane Silber Dean Cyr/Burns DATE: 11/22/05 Mallett, RIV Schmidt, OCA ASSIGNED TO: CONTACT: Shoop, OED0 NRR Dyer SPECIALI INSTRUCTIONS OR REMARKS:
Respond directly to constituent and cc: Senator McCain. POC: Undine Shoop, OEDO
OFFICE OF TllE SECRETARY CORRESPONDENCE CONTROL TICKET Date Pritrted: Nov 21,2bO5 17:17 PAPER NUhlBER: LTR-05-0570 LOGGING DATE: 1 lRlf2005 ACTION OFFICE: EDO AUTHOR: SEN John McCain AFFILIATION: CONG ADDRESEE: Wi'lliamOullaw SUBJECR Palo ~ e r h u c l e a Generaling r Slalion ACTION: Signature of ED0 DISTRIBUTION: OCA to Ack LEITER DATE 11/13/2005 ACKNOWLEDGED No SPECIAL IIANDLING:
NOTES:
FILE LOCATION: ADAMS DATE DUE: 1214R005 DATE SIGNED:
WwnAN 6353 NORTH 1 6 T H STREKT COMMITTEE ON INMAN AFFAIRS S u m 105 PMOCNIX. AZ 85016 COMMITTEE ON ARMED SERVICES (6021 951-1410 COMMlFTrE ON COMMERCE.
SCIENQ. AND TRANSWRTATlON November 13,2005 Mr. William Outlaw Director, Congressional Affairs U.S.~ u c 1 e a r ' ~ e ~ u l a tCommission ory One White Flint North Rock14lle, MD 20852-2739
Dear Mr. Outlaw:
I wish to bring to your attention a matter concerning Dan Frenette who would like some information on the Palo Verde Nuclear Generating Station.
Because the situation is under your jurisdiction, I am respecthlly referring this matter to you for consideration. I feel that this issue would be better addressed by you and request that you respond directly to Mr. Frenette.
Thank you.
Sincerely,
&gzd John McCain Bfi&
United States Senator
. .- Report: lncornintj Constituent Messaae Snqpshot C'O'I 0 7 3%
Report Dale:1011712005 Staff: dnm Address To: General Frenette
. USA URt:
Home Phone: Cell Phone:
Work Phone: Fax:
Salutation:
Dear Mr. Frenette:
In Type: EML Reply Ltr:
Interest: ERGE Organization: Letter:
Classification: Personal:
Title:
Reference #: Group:
Message Body:
I live in the West Valley (Glendale). I am concerned with'the recent shut down, if you would'answer a few ----
questions it may set my mind at ease.
What caused the 2 reactor shut down?
Are the NRC oveneacting?
How long until the plant comes back online? (are we talking about months or years)
Are employees being paid during shut d01vn7 Was it a break down in the cooling system, a flaw in design, or another problem that caused the shut down?
Why did the NRC wait until now?
What is the mood among the management at the plant (flustered, peeved, womed, other)?
Why the lack of info to the public?
Thanks Dan Frenette