Ltr., Project Manager Assignment
ML053010215
Person / Time
Site: Harris 
(NPF-063)
Issue date: 11/23/2005
From: Marshall M
Plant Licensing Branch III-2
To: Gannon C
Carolina Power & Light Co
Patel C P, NRR/DLPM, 415-3025
References
Download: ML053010215 (3)


Text

November 23, 2005 Mr. Cornelius J. Gannon, Vice President Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1, PROJECT MANAGER ASSIGNMENT

Dear Mr. Gannon:

The Office of Nuclear Reactor Regulation (NRR) has been reorganized to support anticipated new-reactor licensing, risk-informed regulation, and generally improve the effectiveness and efficiency of NRR's programs and processes. The new organization became effective on October 31, 2005.

The five divisions has been expanded to nine smaller divisions. Each division will be headed by a director and one or two deputy directors. The Division of Licensing Project Management (DLPM) has been designated as the Division of Operating Reactor Licensing (DORL) and will focus, primarily, on licensing activities. The director of DORL is Catherine Haney. Her deputy directors are Edwin M. Hackett and Cornelius F. Holden. Generic and programmatic issues will be managed by the Division of Policy and Rulemaking. In the new DORL, the current first-line supervisors, section chiefs, have been redesignated as branch chiefs.

There is no change to the project manager assignment for your facility. Chandu P. Patel and Michael L. Marshall continue to be the project manager and branch chief, respectively.

Mr. Patel may be contacted at (301) 415-3025 or via email at CPP@NRC.gov. Mr. Marshall may be contacted at (301) 415-2734 or via email at MXM2@NRC.gov.

Sincerely,

/RA/

Michael L. Marshall, Jr., Chief Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-400 cc: See next page

ML053010215 NRR-106 OFFICE NRR/LPLII-2/PM NRR/LPLII-2/LA NRR/LPLII-2/BC NAME CPatel CSola MMarshall DATE 11/09/05 11/08/05 11/23/05

Mr. Cornelius J. Gannon Shearon Harris Nuclear Power Plant Carolina Power & Light Company Unit 1 cc:

David T. Conley Associate General Counsel II -

Legal Department Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, North Carolina 27602-1551 Resident Inspector/ Harris NPS c/o U. S. Nuclear Regulatory Commission 5421 Shearon Harris Road New Hill, North Carolina 27562-9998 Ms. Margaret A. Force Assistant Attorney General State of North Carolina Post Office Box 629 Raleigh, North Carolina 27602 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211 Ms. Beverly Hall, Section Chief Division of Radiation Protection N.C. Department of Environment and Natural Resources 3825 Barrett Drive Raleigh, North Carolina 27609-7721 Mr. Chris L. Burton Manager Performance Evaluation and Regulatory Affairs PEB 7 Progress Energy Post Office Box 1551 Raleigh, North Carolina 27602-1551 Mr. Eric McCartney Plant General Manager Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 3 New Hill, North Carolina 27562-0165 Mr. Robert J. Duncan II Director of Site Operations Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 Mr. Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, North Carolina 27699-4326 Chairman of the North Carolina Utilities Commission Post Office Box 29510 Raleigh, North Carolina 27626-0510 Mr. Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, North Carolina 27602 Mr. Tommy Emerson, Chair Board of County Commissioners of Chatham County P. O. Box 87 Pittsboro, North Carolina 27312 Mr. Christos Kamilaris, Manager Support Services Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 Mr. David H. Corlett, Supervisor Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW.