ML052870516

From kanterella
Jump to navigation Jump to search
Slides from CAL Public Meeting 10/12/05
ML052870516
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 10/12/2005
From:
NRC/RGN-III
To:
FirstEnergy Nuclear Operating Co
References
Download: ML052870516 (12)


Text

Perry Nuclear Power Plant Confirmatory Action Letter Public Meeting Nuclear Regulatory Commission - Region III Lisle, Illinois 1

October 12, 2005

Purpose of Todays Meeting z Provide a public forum for the discussion of Perry Nuclear Power Plant performance z NRC discussion of the September 28, 2005 Confirmatory Action Letter z Perry management discussion of commitments and plans to address cross-cutting issues z Receive comments and questions from the public 2

www.nrc.gov

Agenda z Introduction z Review of Performance at Perry z Overview of Confirmatory Action Letter (CAL) z Overview of CAL Inspection Activities z Licensee Response and Remarks z Adjourn NRC Meeting with FENOC

<Break>

z Public Comments and Questions of NRC z Adjourn Meeting 3 www.nrc.gov

Review of Perry Performance August 2004 - Perry entered the NRC Action Matrix Multiple/

Repetitive Degraded Cornerstone Column January 2005 - IP 95003 Supplemental Inspection Started May 2005 - Public Exit Meeting of IP 95003 Inspection Results July 2005 - IP 95003 Inspection Report Issued (05000440/2005003)

August 2005 - FENOC Response to IP 95003 Inspection Issues September 2005 - NRC Issues Confirmatory Action Letter 4

www.nrc.gov

Review of Perry Performance (continued)

Perry is Being Operated Safely Challenge Areas:

- Corrective Action Program Implementation

- Human Performance Continued Supplemental Regulatory Oversight Warranted 5

www.nrc.gov

Confirmatory Action Letter FENOC committed to sustained improvements in:

  • Corrective Action Program
  • Human Performance

www.nrc.gov

Inspection Activities for Perry CAL NRC inspection activities will:

  • Review Licensees Assessment Activities &

Corrective Action Development

  • Review Corrective Action Implementation
  • Review Corrective Action Effectiveness 7

www.nrc.gov

Contacts for Additional Information Regional Public Affairs Officer

  • Phone: (630) 829-9663 or 829-9662 Perry Resident Inspector Office
  • Ray Powell, Senior Resident Inspector
  • Phone: (440) 259-3610 8

www.nrc.gov

Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free) 9 www.nrc.gov

FirstEnergy Nuclear Operating Company (FENOC)

Presentation 10 www.nrc.gov

Summary Perry Nuclear Power Plant continues to Operate Safely.

Due to the performance trend at Perry, the NRCs process has led to increased Regulatory interaction.

The NRC continues to monitor performance.

11 www.nrc.gov

Questions and Comments From the Public 12 www.nrc.gov