E-mail, Ennis, NRR, to Devincentis, Entergy, VY EPU Regulatory Commitments
ML052790056
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 09/03/2005
From: Richard Ennis
Office of Nuclear Reactor Regulation
To: Devincentis J
Entergy Operations
References
Download: ML052790056 (8)


Text

Rick Ennis -- V II RikEni VY EPU euaoyCmimnsPg P - Regulatory Commitments Page I I From: Rick Ennis To: Jim DeVincentis Date: 9/30/05 8:15AM

Subject:

VY EPU - Regulatory Commitments Jim, Based on my review of the VY EPU application and all supplements submitted to date (i.e Supplements 1-35), attached is a table listing all regulatory commitments made by Entergy to support the amendment request. This table will be included as Section 4.0 of the safety evaluation.

Please review the table and let me know which commitments have been completed or superceded by other commitments (e.g., some of the earlier steam dryer inspection commitments). For any completed or superceded items, please cite the documentation that supports the latest status (e.g., Supplement x, Attachment y, page z).

Your response is requested by COB 10/7.

thanks, Rick CC: Brian Hobbs; Craig Nichols; Len Gucwa; Ronda Daflucas

Ic:\tempAGW100001 .TMP Page 1 I ---------

Mail Envelope Properties (433D2C71.1C8 :11: 372)

Subject:

VY EPU - Regulatory Commitments Creation Date: 9/30/05 8:15AM From: Rick Ennis Created By: RXE(nrc.gov Recipients Action Date & Time owf4_po.WFNDO Delivered 09/30/05 8:15 AM RXE BC (Rick Ennis) Opened 09/30/05 8:15 AM entergy.com bhobbs CC (Brian Hobbs) cnichol CC (Craig Nichols) jdevinc (Jim DeVincentis)

LGUCW90 CC (Len Gucwa) rdafluc CC (Ronda Daflucas)

Post Office Delivered Route owf4po.OWFNDO 09/30/05 8:15 AM Pending entergy.com Files Size Date & Time MESSAGE 1323 09/30/05 08:15AM vy epu commitments.wpd 32662 09/30/05 08:11AM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard Reply Requested: No Return Notification: None Concealed

Subject:

No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number and date) . Ea, ct a u CL E

1 Steam dryer Inspection during RFO. BW 04-058 x Fall 2005 July 2, 2004 (Reference 9) 2 Steam dryer inspection during RFO. BW 04-058 x Spring 2007 July 2,2004 (Reference 9) 3 Steam dryer inspection during RFO. BVY 04-058 x Fall 2008 July 2,2004 (Reference 9) 4 Perform flow-induced vibration BVY 04-058 x EPU monitoring. July 2, 2004 implementation (Reference 9) 5 Implement those modifications BW 04-086 x Prior to Increasing contained In ISO New England August 25, 2005 power above CLTP letter of March 12, 2004. (Reference 13) 6 Install additional capacitor banks. BW 04-086 x Prior to exceeding August 25, 2005 630 MWe (gross)

(Reference 13) 7 Provide details regarding Action BW 04-097 x September 29, 2004 Per Reference 14, Attachment 1, page 3, Item No. 2. September 14, 2004 'Action Item No. 2" pertains to Entergy (Reference 14) providing additional details on the power ascension test plan.

8 Provide results of the acoustic BW 04-097 x September 30, 2004 analysis model to the NRC staff September 14, 2004 during a meeting. (Reference 14)

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number and date) E a>- C E 9 Perform a detailed inspection of the BW 04-097 x Fall 2005 steam dryer during the next September 14, 2004 scheduled refueling outage. The (Reference 14) inspection will be performed in accordance with the WNPS vessel internals monitoring program and recommendations of GE SIL 644, Supplement 1.

10 Perform a detailed Inspection of the BVY 04-097 x Spring 2007 and steam dryer during two subsequent September 14, 2004 Fall 2008 refueling outages. The Inspections (Reference 14) will be performed in accordance with the WNPS vessel internals monitoring program and recommendations of GE SIL 644, Supplement 1.

11 Provide the NRC staff the results of BVY 04-097 x After Fall 2005 and the steam dryer Inspections during September 14, 2004 Spring 2007 the next two refueling outage. (Reference 14) .

12 Prior to Implementing, discuss BVY 04-097 x Indeterminate changes to the long term monitoring September 14, 2004 plan for the steam dryer with the (Reference 14)

NRC staff.

13 Add the steam dryer to the VYNPS BW 04-097 x Fall 2005 Vessel Internals Inspection September 14, 2004 Program as an augmented exam. (Reference 14) .

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number and date) c

=0.

or 0< Oo0 14 Existing and new steam dryer BW 04-097 x Indeterminate indications will be evaluated using September 14, 2004 ASME Section Xl criteria as (Reference 14) guidance, along with industrial standards and practices. Fracture mechanics analysis will be incorporated into the evaluation as appropriate. Any indication predicted to result in an unacceptable failure will be repaired in accordance with approved procedures. Technical justification will be documented for all unrepaired flaw indications left in service for the next cycle.

15 Implement the BWROG guidelines BW 04-097 x Indeterminate on moisture carryover monitoring September 14, 2004 when Issued. (Reference 14) 16 Implement flow Induced vibration BVY 04-1 00 x During EPU power and steam dryer monitoring, September 23, 2004 ascension testing including associated evaluation as (Reference 16) necessary during EPU power ascension testing as described In Entergy letter BW 04-100.

17 Discuss details of the acoustic BVY 04-100 x September 30, 2004 analysis and steam dryer power September 23, 2004 ascension test acceptance criteria (Reference 16) at a meeting with NRC staff. IIII_ I I

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number 0 and date) E c 6b.2 F 0< 0t0 18 Implement BWROG operational BW 04-100 x During EPU power (moisture carryover) response September 23, 2004 ascension testing guidance. (Reference 16) 19 Revise the MOV Periodic BVY 04-101 x December 1, 2004*

  • Attachment 3 to Entergy letter Verification Program to include September 30, 2004 BVY 05-083, dated September 10. 2005 periodic at-the-valve testing and (Reference 17) (Reference 33), states that this commitment formalize the process for DC motor Is complete.

trending.

20 Verify the RCIC start time assumed BVY 04-107 x December 1, 2004* 'Entergy letter BW 04-131, dated in the SCCA and complete training September 30, 2004 December 8, 2004 (Reference 23), states of operations crews on the revised (Reference 18) that this commitment Iscomplete.

procedure.

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number E a) and date) s a 0 <

21 Entergy has established BVY 05-072 x October 31, 2005* ^ Date represents first tabletop review.

administrative controls to assure August 1, 2005 performance of a once per (Reference 31) operating cycle tabletop review of the procedures that complete the actions to repower a WNPS 4KV bus from the VHS. Pursuant to discussions with co-host REMVEC, a system-wide annual tabletop review will take place in October 2005. During this meeting Entergy will lead a tabletop review of all actions required to support the restoration of 4KV AC to WNPS.

This review will review the interfaces with the operator of VHS and the regional grid operator to verify that roles and responsibilities and timelines are understood and that there have been no changes that would impact the assumption in the WNPS SBO coping strategy.

Entergy will also provide the participants with additional Insights regarding offsite power Issues for nuclear power stations including plant response to and consequences of a SBO.

No. COMMITMENT REFERENCE TYPE SCHEDULED NRC COMMENTS COMPLETION (Entergy letter DATE number and date) E c .

22 Training on the changes to OP BVY 05-072 x October 15, 2005 2124 and OT 3122 is currently August 1, 2005 underway. Once the training cycle (Reference 31) is complete (scheduled for September 1, 2005), the procedures will be revised and issued for use.

Various operating, surveillance and administrative procedures will be revised to Incorporate a higher condensate storage tank inventory limit as either a precaution or an administrative limit by October 15, 2005.

23 Visual inspection of steam dryer. BVY 05-083 x RFO-26, RFO-27, September 10, 2005 and RFO-28 (Reference 33) 24 Modification of the four susceptible BVY 05-083 x RFO-25 isokinetic sample probes in the September 10, 2005 condensate and feedwater systems. (Reference 33)