a SOUTHERN CALIFORNIA Daniel P. Breig, P.E.

EDISON Station Manager San Onofre An FDISM INRN477)1L Coni.pa September 26, 2005 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555

Subject:

Docket Nos. 50-361 and 50-362 Response to Regulatory Issue Summary (RIS) 2005-19 San Onofre Nuclear Generating Station, Units 2 and 3

Reference:

RIS 2005-19, "Preparation and Scheduling of Operator Licensing Examinations," dated August 24, 2005 Gentlemen:

This letter provides the Southern California Edison (SCE) response to U. S. Nuclear Regulatory Commission Regulatory Issue Summary 2005-19, "Preparation and Scheduling of Operator Licensing Examinations," dated August 24, 2005.

The schedule shown on Attachment 1, "Operator Licensing Examination Data," provides SCE's best estimate to meet our operator licensing needs through calendar year 2009.

If you have any questions, please feel free to contact me or Mr. Clay E. Williams at (949) 368-6707.

S'cerel Attachment cc: B. S. Mallet, Regional Administrator, NRC Region IV A. T. Gody, Chief, Operations Branch, NRC Region IV C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 and 3 P.O. Box 128 San Clemente, CA 92674-0128 949-368-9263/PAX 89263 II uk, Fax 949-368-6183 breigdp~)songs.sce.com

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 08/31/2008 (C82D05) Estimated burden per response to comply with this voluntary information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. his Information collection Is used to plan budgets and resources for operator examinations. Send comments renrding burden OPERATOR LICENSING estimate to the Records and FOIPrivacy Services Branch -5 F53), U.S.

Nuclear Regulatory Commisslon, Washington, DC 205554000' by Internet EXAMINATION DATA RegulatoAffairs, NEO andB-i202.

e-mail to Infocollectsenrc.gov, the 0and to(31500131). Office Office Desk Officer, of Information of Management and Budget, W ,DC 20503. I a means used to Impose an Information ollection does not display a currently vald OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the

. Information collection.

FACILITY NRC REGION SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -REGION IV A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 06 CY 07 CY 08 CY 09 ESTIMATED NUMBER OF LICENSEE-PREPARED . 1 2 EXAMINATIONS _ _

ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS 0 0 0 0 B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 06 CY07 CY08 CY 09 NUMBER OF REACTOR OPERATORS 9 6 9 NUMBER OF SENIOR REACTOR OPERATORS - INSTANT 5 2 3 2 3 NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 4 4 3/ 1 3 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 10/30/2006 05/14/2007 03/31/2008 / 05/04/2009 10/27/2008 ALTERNATE DATE 11/06/2006 06/04/2007 04/07/2008 / 05/11/2009 11/03/2008 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 06 CY 07 PROPOSED _ _

NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0 0 0 0 0 10 0 0 CANDIDATES a -