FENOC FirstEnergy Nuclear Operating Company 5501 North State Route 2 Oak Harbor, Ohio 43449 Mark B. Bezilla Fa:419-321-7582 Vice President - Nuclear fax. 419-321 7582 Docket Number 50-346 License Number NPF-3 Serial Number 3170 August 29, 2005 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
Subject:
Withdrawal of License Amendment Application to Change Design Requirements for Emergency Diesel Generators (License Amendment Request 03-0017, TAC No. MC3058)
Ladies and Gentlemen:
By letter dated May 3, 2004 (Serial Number 3006), the FirstEnergy Nuclear Operating Company (FENOC) submitted a license amendment application for the Davis-Besse Nuclear Power Station (DBNPS). The proposed amendment would have changed the facility as described in the DBNPS Updated Safety Analysis Report to modify the design requirements for the emergency diesel generators. FENOC has elected to pursue design modifications that would eliminate the need for this license amendment. Therefore, FENOC requests that this license amendment request be withdrawvn.
Enclosure I provides a list of regulatory commitments made in this submittal. If there are any questions concerning this matter, please contact Mr. Henry L. Hegrat, Supervisor -
Fleet Licensing, at (330) 315-6944.
Very truly yours, MAR Enclosure
001
Docket Number 50-346 License Number NPF-3 Serial Number 3170 Page 2 cc:
J. L. Caldwell, Regional Administrator, NRC Region III W. A. Macon, NRC/NRR Project Manager N. Dragani, Executive Director, Ohio Emergency Management Agency, State of Ohio (NRC Liaison)
C. S. Thomas, NRC Region III, DB-1 Senior Resident Inspector Utility Radiological Safety Board
Docket Number 50-346 License Number NPF-3 Serial Number 3170 Enclosure I Commitment List The following list identifies those actions committed to by FirstEnergy Nuclear Operating Company (FENOC) for the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by FENOC. They are described only as information and are not regulatory commitments. Please notify Mr. Henry L. Hegrat, Supervisor - Licensing, at (330) 315-6944 of any questions regarding this document or associated regulatory commitments.
Commitment Due Date None N/A