Mid-Cycle Performance Review and Inspection Plan - Clinton Power Station
ML052420427
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/30/2005
From: Ring M
NRC/RGN-III/DRP/RPB1
To: Crane C
Exelon Generation Co
References
Download: ML052420427 (5)


Text

August 30, 2005 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

CLINTON POWER STATION

Dear Mr. Crane:

On August 9, 2005, the NRC staff completed its performance review of the Clinton Power Station for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.

Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only reactor oversight process (ROP) baseline inspections at your facility through March 31, 2007.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2007. Please note that the plan contains a Safety System Design and Performance inspection scheduled for November 2005 and a Problem Identification and Resolution inspection scheduled for March 2007. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.

C. Crane In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Clinton Power Station Inspection/ Activity Plan See Attached Distribution DOCUMENT NAME: G:\\Branch TSS\\ALL MOC\\midcycle 2004 to 2005\\MOC letters\\clin.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII E

NAME MRing:dtp DATE 08/25/05 OFFICIAL RECORD COPY

C. Crane cc w/encl:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Illinois Department of Nuclear Safety Clinton Police Department Mayor of Clinton Mayor of Weldon DeWitt County Board Chairman DeWitt County Sheriff Coordinator, DeWitt County Emergency Preparedness Mayor of Wapella McLean County Board Chairman McLean County Sheriff Director, McLean County ESDA Piatt County Board Chairman Piatt County Sheriff Director, Piatt County ESDA Macon County Board Chairman Macon County Sheriff Director, Macon County ESDA INPO

C. Crane ADAMS Distribution:

DWW Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG KGO RML2 SRI Clinton DRSIII DRPIII PLB1 JRK1

Clinton Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 08/29/2005 10:59:58 Report 22 2

71114

- EP EXERCISE & EP PI INSP Baseline Inspections 10/03/2005 10/07/2005 Exercise Evaluation IP 7111401 1

Baseline Inspections 10/03/2005 10/07/2005 Performance Indicator Verification IP 71151 1

5 SSDPC

- SAFETY SYSTEM DESIGN & PERFORMANCE Baseline Inspections 11/14/2005 12/02/2005 Safety System Design and Performance Capability IP 7111121 1

3 71111.11

- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 11/14/2005 11/18/2005 Licensed Operator Requalification Program IP 7111111B 1

1 IP 71121

- RAD ACCESS CONTROL & ALARA Baseline Inspections 11/28/2005 12/02/2005 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 11/28/2005 12/02/2005 ALARA Planning and Controls IP 7112102 1

1 ISI

- CLINTON ISI INSPECTION Baseline Inspections 02/06/2006 02/10/2006 Inservice Inspection Activities - BWR IP 7111108G 1

2 7112102

- ALARA OUTAGE INSP Baseline Inspections 02/06/2006 02/10/2006 ALARA Planning and Controls IP 7112102 1

1 71114

- BASELINE EP INSPECTION Baseline Inspections 03/20/2006 03/24/2006 Alert and Notification System Testing IP 7111402 1

Baseline Inspections 03/20/2006 03/24/2006 Emergency Response Organization Augmentation Testing IP 7111403 1

Baseline Inspections 03/20/2006 03/24/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1

Baseline Inspections 03/20/2006 03/24/2006 Performance Indicator Verification IP 71151 1

1 HS

- HEAT SINK INSPECTION Baseline Inspections 03/27/2006 03/31/2006 Heat Sink Performance IP 7111107B 1

1 7112202

- TRANSPORTATION & RADWASTE Baseline Inspections 05/22/2006 05/26/2006 Radioactive Material Processing and Transportation IP 7112202 1

1 7112101

- RADIOLOGICAL ACCESS CONTROL Baseline Inspections 08/28/2006 09/01/2006 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 08/28/2006 09/01/2006 Performance Indicator Verification IP 71151 1

2 M50.59

- MOD 50.59 INSPECTION Baseline Inspections 09/18/2006 10/06/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 1

1 ME

- MAINTENANCE RULE INSPECTION Baseline Inspections 11/13/2006 11/17/2006 Maintenance Effectiveness IP 7111112B 1

1 7112201

- RADIOLOGICAL EFFLUENTS Baseline Inspections 12/11/2006 12/15/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1

Baseline Inspections 12/11/2006 12/15/2006 Performance Indicator Verification IP 71151 1

4 PI&R

- PROBLEM IDENITFICATION AND RESOLUTION Baseline Inspections 03/24/2007 04/11/2007 Identification and Resolution of Problems IP 71152B 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.