Inspection/Activity Plan - 09/01/05 - 03/31/07
ML052420311
Person / Time
Site: Robinson, 07200003  Duke Energy icon.png
Issue date: 08/30/2005
From:
NRC/RGN-II/DRP/RPB4
To:
Carolina Power & Light Co
Shared Package
ML052420305 List:
References
Download: ML052420311 (2)


Text

Robinson Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2005 07:31:03 Report 22 3

MTN-HEAD - REACTOR HEAD REPLACEMENT Other Routine 09/12/2005 09/15/2005 Reactor Vessel Head Replacement Inspection IP 71007 2

2 EB3-MR

- MR EFFECTIVENESS Baseline Inspections 09/06/2005 09/09/2005 Maintenance Effectiveness IP 7111112B 2

1 PS1-RP

- RP OCCUPATIONAL INSP / HD REPL WK1 Safety Issues 09/18/2005 09/22/2005 Transportation of Reactor Control Rod Drives in Type A Packages IP 2515/161 2

Other Routine 09/18/2005 09/22/2005 Reactor Vessel Head Replacement Inspection IP 71007 2

Baseline Inspections 09/18/2005 09/22/2005 Access Control to Radiologically Significant Areas IP 7112101 2

Baseline Inspections 09/18/2005 09/22/2005 ALARA Planning and Controls IP 7112102 2

Baseline Inspections 09/18/2005 09/22/2005 Performance Indicator Verification IP 71151 2

2 EB3-ISI

- U2 INSERVICE INSPECTION Baseline Inspections 09/27/2005 09/30/2005 Inservice Inspection Activities - PWR IP 7111108P 2

1 PS1-RP

- RP OCCUPATIONAL BASELINE WK2 Baseline Inspections 10/03/2005 10/07/2005 Access Control to Radiologically Significant Areas IP 7112101 2

Baseline Inspections 10/03/2005 10/07/2005 Performance Indicator Verification IP 71151 2

4 EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 01/30/2006 02/03/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 2

Baseline Inspections 01/30/2006 02/03/2006 Permanent Plant Modifications IP 7111117B 2

1 PS1-RP

- RP PREINSPECTION/ ISFSI Baseline Inspections 05/30/2006 06/01/2006 Access Control to Radiologically Significant Areas IP 7112101 2

3 PS1-RP

- RP BASELINE OCCUPATIONAL Baseline Inspections 06/26/2006 06/30/2006 Access Control to Radiologically Significant Areas IP 7112101 2

Baseline Inspections 06/26/2006 06/30/2006 ALARA Planning and Controls IP 7112102 2

Baseline Inspections 06/26/2006 06/30/2006 Radioactive Material Processing and Transportation IP 7112202 2

Baseline Inspections 06/26/2006 06/30/2006 Performance Indicator Verification IP 71151 2

1 PS2-EP

- EP INSP Baseline Inspections 06/26/2006 06/30/2006 Alert and Notification System Testing IP 7111402 2

Baseline Inspections 06/26/2006 06/30/2006 Emergency Response Organization Augmentation Testing IP 7111403 2

Baseline Inspections 06/26/2006 06/30/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 2

Baseline Inspections 06/26/2006 06/30/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 2

Baseline Inspections 06/26/2006 06/30/2006 Performance Indicator Verification IP 71151 2

2 EB3-HS

- HEAT SINK Baseline Inspections 08/14/2006 08/18/2006 Heat Sink Performance IP 7111107B 2

4 DRP/BR4

- PI&R Baseline Inspections 10/02/2006 10/20/2006 Identification and Resolution of Problems IP 71152B 2

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Robinson Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2005 07:31:03 Report 22 3

OL PREP

- INITIAL EXAM PREP Not Applicable 01/08/2007 01/12/2007 ROBINSON/EXAM AT POWER FACILITIES V23242 2

3 OL EXAM

- INITIAL EXAM Not Applicable 02/05/2007 02/16/2007 ROBINSON/EXAM AT POWER FACILITIES V23242 2

2 OL RQ

- REQUAL INSPECTION Baseline Inspections 02/26/2007 03/02/2007 Licensed Operator Requalification Program IP 7111111B 2

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.