MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] |
Text
September 6, 2005 J.A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company LLC P.O. Box 355 Pittsburgh, Pennsylvania 15230-0355
SUBJECT:
WESTINGHOUSE ELECTRIC COMPANY, REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. MC8078 AND MC8079)
Dear Mr. Gresham:
By letter dated August 12, 2005, Southern Nuclear Operating Company (SNC) submitted an affidavit dated August 11, 2005, executed by J. S. Galembush, you requested that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 2, Section 2.390:
LTR-CDME-05-151-P, Limited Inspection of the Steam Generator Tube Portion Within the Tubesheet at Vogtle 2, dated July 2005. This letter is included in the SNCs request for license amendment (NL-05-1420) dated August 12, 2005.
A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(4)(ii)(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouses competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.
(4)(ii)(c) Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1055.
Sincerely,
/RA/
Christopher Gratton, Sr. Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No.05-424 and 05-425 cc: See attached
ML052370442 NRR-084 OFFICE PDII-1/PM PDII-1/PM DE/EMCB(A) PDII-1/SC NAME CGratton CHawes PKlein EMarinos DATE 8/29/05 8/29/05 8/29/05 9/6/05 Vogtle Electric Generating Plant, Units 1 & 2 cc:
Mr. N. J. Stringfellow Attorney General Manager, Licensing Law Department Southern Nuclear Operating Company, Inc. 132 Judicial Building P.O. Box 1295 Atlanta, GA 30334 Birmingham, AL 35201-1295 Mr. Laurence Bergen Mr. T. E. Tynan, General Manager Oglethorpe Power Corporation Vogtle Electric Generating Plant 2100 East Exchange Place Southern Nuclear Operating Company, Inc. P.O. Box 1349 7821 River Road Tucker, GA 30085-1349 Waynesboro, GA 30830 Arthur H. Domby, Esquire Mr. Jeffrey T. Gasser Troutman Sanders Executive Vice President Nations Bank Plaza Southern Nuclear Operating Company, Inc. 600 Peachtree Street, NE P.O. Box 1295 Suite 5200 Birmingham, AL 35201-1295 Atlanta, GA 30308-2216 Mr. Steven M. Jackson Resident Inspector Senior Engineer - Power Supply Vogtle Plant Municipal Electric Authority of Georgia 8805 River Road 1470 Riveredge Parkway, NW Waynesboro, GA 30830 Atlanta, GA 30328-4684 Office of the County Commissioner Mr. Reece McAlister Burke County Commission Executive Secretary Waynesboro, GA 30830 Georgia Public Service Commission 244 Washington St., SW Mr. Harold Reheis, Director Atlanta, GA 30334 Department of Natural Resources 205 Butler Street, SE, Suite 1252 Atlanta, GA 30334