Limited Extension of Time for NJDEP to Complete Its Review of Data Submissions Documenting Consistency Certification for Federal Permit and License Applicants
ML052240045
Person / Time
Site: Oyster Creek
Issue date: 07/20/2005
From: Cowan P
AmerGen Energy Co
To: Heyl A
Office of Nuclear Reactor Regulation, State of NJ, Dept of Environmental Protection
References
%dam200604, 1500-02-0004.4 CDT050001, 2130-05-20156
Download: ML052240045 (3)


Text

AmerGen Energy Company, LLC An Exelon Company 200 Exelon Way Kennett Square, PA 18348 2130-05-20156 July 20, 2005 Mr. Andy Heyl Land Use Regulation Program Bureau of Coastal Management NJ Department of Environmental Protection 501 East Street Trenton, NJ 08625-0439

Subject:

Limited Extension Of Time For NJDEP To Complete Its Review Of Data Submissions Documenting Consistency Certification For Federal Permit and License Applicants File No. 1500-02-0004.4 CDT050001 Project: Oyster Creek Generating Station

Reference:

1) Letter, Federal Consistency Certification For Federal Permit And License Applicants, Keith Jury to Andy Heyl, dated January 20, 2005
2) Letter, Request For Necessary Data and Information for a Federal Consistency Determination, Andy Heyl to Keith Jury, dated March 31, 2005
3) Letter, Response to Request for Necessary Data and Information for a Federal Consistency Determination, Pamela Cowan to Andy Heyl, dated June 15, 2005

Dear Mr. Heyl:

This letter will confirm recent telephone conversations between our offices in which it was mutually agreed to grant the NJDEP an additional 30 days pursuant to 15 CFR 930.60(a)(3),

until August 22, 2005, for the sole purpose of completing its review of the data and information already submitted in support of our consistency certification.

Reference 1 requested concurrence from the State of New Jersey with AmerGen Energy Company, LLC's (AmerGen's) Federal Consistency Determination for Federal Permit and License Applicants.

In Reference 2 the State of New Jersey requested necessary data and information to aid the State of New Jersey in their review of Reference 1. In addition, it was stated that a decision on AmerGen's request was due on or before July 21, 2005.

In Reference 3 AmerGen supplied the data and information to the State of New Jersey that was requested in Reference 2.

NJ DEP, Land Use Regulation Program July 20, 2005 Page 2 Subsequent conversations with the State of New Jersey revealed that additional time beyond the July 21, 2005 required response date is needed to aid in their review process based on the data and information provided by AmerGen. It is not anticipated that any additional information would be required for the State to reach its determination. A mutually agreeable extension was agreed to such that a decision from the State of New Jersey would be due on or before August 22, 2005.

After your office completes their reviews, AmerGen requests a letter concurring with the previously transmitted Federal Consistency Certification for Federal Permit and License Applicants.

If you should have any questions, please contact Bill Maher at 610.765.5939.

Sincerely, Pamela B. Cowan Director, Licensing & Regulatory Affairs AmerGen Energy Company, LLC cc:

Karen Tuccillo, NJ BNE P. S. Tam, USNRC, Senior Project Manager, NRR Andrew Kugler, USNRC, Chief of Environmental Section File No. 05100

AmerGen Energy Company, LLC 200 Exelon Way Kennett Square, PA 18348 U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation One White Flint 11555 Rockville Pike Rockville, MD 20555 Attn: Andrew Kugler