ML052030100
| ML052030100 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 05/25/2004 |
| From: | Nuclear Management Co |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| FOIA/PA-2004-0282 | |
| Download: ML052030100 (5) | |
Text
Committed to Nucicar Ercelicncc
-e urnmn1E UF Point Beach Nuclear Plant U1R28 OCC Interactive Turnover Meeting Agenda Tuesday, May 25,,2004 Start Time:
0600 NSB Cafeteria BRIEFING NOTES ATTENDEES 4
_5
/k7 ck e
4vey -2 ej; Shift Outage Directors Shift Outage Managers (SOM)
J 3 D-ilt4t i).
Operations Coordinators (SOC)
Maintenance Coordinators (MOC)
C 4 Q/
VI 7 se l
d T
Engineer/ Projects Coordinators (EOM)
-b Rad Protection Manager (RPM)
_/ig 9
Site Safety Coordinator (SSC)
Shutdown Safety Assessor (SSA)
Site Management (SSM)
General Supervisors First Line Supervisors Agenda
- 1. Safety Issue Discussion (SSC)
- 2. Radiation Protection (RPM)
- 3. Operations Coordinator Turnover (SOC)
- 4. Shutdown Safety Assessment (SSA)
- a. Containment Fire Loading SAT /
UNSAT -+ Review Deficiencies
- 5. Maintenance Coordinator Turnover (MOC)
- 6. Engineering Coordinator Turnover (EOM)
- 7. Major Projects Update (EOM)
- 8. Schqdule Review (SOM)
- 9. Management Expectations (SSM)
- 10. ACEMAN Assessment Results (SOM)
- 11. Shift Goals (SOM)
Items Included in Daily Package:
Site dommunication W
Safety Snippet Outage Alara Report Outage Status Report Shutdown Safety Assessment Defined Critical Path Work Activity Risk Assignment Outage Schedule
{\\
,ai W
l-I I
1
Committed to Nucicar ExZIJI777 l1UR flE Y
UF anT
- M Ult8 Point Beach Nuclear Plant U1R28 Refueling Outage
-;SafetTdopicforWeiekicffMayV23 -;29, 2004 Theme for the week This week's theme deals with odds and ends for Completina the Outage. We are almost done.
A number of critical work activities will be conducted this week in containment and we will begin a major battery change out It is time to review industry OE from other sites to make sure we've learned from their experiences. Nothing will stop our progress faster than a serious injuryl
.Daily Safety Snippets Sunday
'Xs there an obstruction in your way that might not Stay OE13857 May2002, Fort Calhoun -While moving the reactor vessel head assembly during a refuering outage, the control pendant for the polar crane caught a handrail vertical support pipe, lifting the pipe out of its mount and causing It to fall 20 ft to the walkway below. Individuals were In the area at the time, but not injured. A review indicated the pendant caught on nearby equipment many times during past refueling outages and corrective actions were not put In place.
Are there any Items were our equipment gets caught during moves that we have not resolved?
Monday The biq picture do we see? And communication is the key.
OE12357 January 2001, River Bend - A worker focused on a moving load and did not pay attention to the movement of the crane. He ended up being forced against a handrail by the cab of the crane, luckily resulting only In minor Injuries.
The entire crew was focused on the load with no one person having oversight of the whole evolution.
During crane operations, do we designate an Indivdual to 'watch the big pct ure?
Tuesday "Peer checks - do we use them?'
December 1997, Byron -An electrician was taken to the hospital for treatment of second-degree bums on his hand and flash burns to his eyes as a result of a mishap. He was one of three electricians assisting a system engineer during a battery discharge test on a new battery bank when he accidentally shorted across the battery with one of the cables used to connect the battery to a resistor bank. An Investigation showed that the electricians and the system engineer had not verified the correct cable configuration. Also, the Injured electrician was not wearing low voltage gloves and had rolled up the sleeves of the long-sleeve shirt he was required to wear for this job.
WMat PPE do we wear during battery work?
Wednesday
.7ust a reminder to be told, balance that loadl' OE10902 March 2000, Seabrook - Electricians were offloading battery cells from a metal pallet on a forklift. The offload sequence went from Inside, closest to the forklift, to the outside, furthest from It The result - Instability In the load and the pallet tipped under the weight of the batteries. The cells fractured spilling 19 gallons of sulfuric acidlwater electrolyte in the switchgear room. This OE is not lust for battery removal. Balance al your loads!
Thursday "Make sure the scaffold doesn't slip and come down too quick. -
OE14551 July 2002, Davis-Besse - A diamond deck plate slipped through a gap between two pieces of floor grating and dropped 20 ft to the level below, damaging an instrument ine. The rest of ourscaffolding is coming down.
Are we aware of the potential 7holes for material to go through?
Friday "Before heat up, make sure someone has done the clean-upl' OE57698 April 2004, Palo Verde -Two mechanics received second degree bums to the face as the result of a flash fire that occurred as they began pre-heating for welding. Isopropyl alcohol was used to clean and liquid had accumulated In the casing of the equipment. The oncoming crew was not aware of this buildup as they began work.
Sattiirdav "Always remember to verify first or yew may take a ride in a hearse. "
1992, Palisades -An experienced electrical technician at Palisades was electrocuted when he failed to Install a circuit jumper before removing test equipment from a current transformer. The existing circuit configuration had not been anticipated during work planning, and the decision to use jumpers to maintain energized current transformer circuits during testing had not been reviewed by supervision.
2
Picture DAY 50 Meets Outage Radiation Performance rDnnqn't MPAt 17yrrapd.
Eon am =qLtm E WI& Mi. Ermr-w-r1reri'm 0
IThis indicator measures cumulative dose radiation eXDOSUre and I
total number of personnel-contamination events (PCE's > 5000 cpm) during refueling outages. The dose indicator is measured in Rem and individual PCE events.
Actual = 3.119 Cumulative = 77.202 Cumulative Forecast =77.389 Meets:
Exceeds:
<=92 Rem
<=88 Rem Actual Cum.
Dose:
Daily PCE goal reforecast on 4123. Daily dose reforecast on 5123/04.
Dose reforecast on 5/23/04 combining dose received for the RV Head repairs and also adding 17 rem to the outage goal to reflect the dose received for the repair.
77.202 Rem Meets: <= 18 Exceeds: <= 12 Actual PCE's:
10 0~~ *,
I s
Stu Thomas I
Personnel Contamination Events Cummulative Dose Exposure 20 18
- 16 3 14 e
j 12 10 X46 2
0 I...
, I f
__/ ---- 'It V ------------
T
]
- Actual
..Forecast Goal Actual Goal 0
5 10 15 20 25 30 35 40 45 50 55 60
NMC4 Committed to Nucdear Exce lncs P
Outage Status Report Plant:
Point Beach Unit I Day:
Tuesday Today's Date/ Time:
5/25/04 0400 Outage Duration: Day Of Refueling Outage Number U1128 Safety Status Industrial - Within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OSHA Recordables 0
First Aid cases 0
Near misses 0
Total for this outage I
Summary Radiological Dose to date 77.202 Projected to date
- 77.389 Outage Goal S92 R Difference
-.187
- Reforecast on 5/23 Number of PCEs 10 Summary: Dose reforecast on 5/23/04 combining dose received for the RV Head repairs and also adding 17 rem to the outage goal to reflect the dose received for the repair.
Nuclear Significant human performance errors and events in last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 0
Summary.
Plant Status Mode:
E Hot Standby (Mode 3)
RCS:
Temperature:
.. 0 0
Time to Boll:
Ylb6 miinutes O Hot Shutdown (mode 4)
E Cold Shutdown (Mode 5s)
E Refue g Sh Pressure:
Veunted to Atn6sphere RV Level: ('5%J
..,~ -
2 Shutdown SafeyX Assessment Protected Equipment:
Major Activities Completed in Last 24 Hours Critical Path and Near Critical Path Activities (Next 24 Hours)
- Nozzle Dam Removal
- Reactor Head Penetration #26 Relief Request Issues Move IP-1B RCP Motor to Pump Cubicle
- 'A' S/G Primnary Manway Installation
- Upper Cavity Decon
- Exit Midloop and Reduced Inventory Orange Path
- 'B' S/G Primary Manway Installation
- Commence Reactor Head Assembly
- Cavity Seal Ring Removal Significant Outstanding Issues Date Issue Due Responsibility 5/17/04 Rx Head Relief Request 5/25/04 Jim Schweitzer 5/20/04 D 105/D 106 Station Battery 5/27/04 Harv Hanneman 5/25/04
'A' S/G Hotleg Manway Bolts 5/25/04 Joe Krentz Upcoming Ma or Milestones Scheduled Actual Scheduled Actual Date Time Date Time Date Time Date Time Cooldown <200° 4/03/04 2100 4/03/04 2230 RCS Fill & Vent 4/23/04 1500 Head Lift 4/09/04 0900 4/21/04 1550 Heatup >2000 4/25/04 0900 Refueled 4/14/04 0300 5/02/04 1848 Reactor Critical 4/28/04 0800 RV Headset 4/18/04 1900 5/23/04 1338 On-Line 4/30/04 0100 a
Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT:
1 DATE: _lay 25, 2004 TIME:
0300 KEY SAFETY FUNCTIONS:
REACTIVITY:
CORE COOLING:
POWER AVAILABLE:
INVENTORY:
CONTAINMENT:
SFP COOLING:
GREEN ORANGE GREEN ORANGE GREEN NA Ly PROTECTED EOUIPMENT:
COMNINENTS: Fire Protection Condition III: Credit is taken for fire rounds as fire prevention contingency.
PBF-1562 Rcvision 2 10/30/02 Refrcrnces: NP 10.3.6 Ni' 10.2.1 Page S of 9 5