Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST Date:

May 17,2004 Time:

0200 Preparer:

Sara Scott U

1 R

28 NOTE.

Refer to base procedure NP 10.3.6for safety assessment checklist KSF definitions.

NOTE:

Wheneverfuel has been removed from the reactor vessel and refueling cavity, all key safetyfunctions are GREEN except spentfuelppool cooling.

KEY SAFETY FUNCTION CRITERIA: No/False =0, Yes/True =1 through 4 REACTIVITY Subtotal Condition

1.

RCS Boron concentration = 3007 ppm a.)

For RSD, RCS boron >Refueling boron concentration specified in unit-specific COLR (TRM 2.1) >2200 ppm b.)

For CSD and prior to RSD no fuel motion, RCS boron > boron concentration required by OP 3C (0-1) 1 0-1 RED

2.

Number of boration paths (0-2) 2 2

ORANGE

3.

No fuel motion (0-1) 1 34

4.

SR instrumentation operable (0-1) 1 5

Subtotal =

CORE COOLING Subtotal Condition

1.

Number of SG available for DHR (0-2) 0 0-1 RED

2.

Refueling cavity filled (0-1) 1 2

ORANGE

3.

Number of trains RHR available (0-2) 2 3

4.

RCS level above REDUCED INVENTORY (0-1) 1 4-5 CGREEN3 RCS Temperature = 79rF; 43 days shutdown RCS Level = Rod Latch Height; Reactor is refueled Subtotal =

4 RCS Time to Boil 30 hrs (Applicable at Cold or Refueling Shutdown)

POWER AVAILABILITY Subtotal Condition

1.

Independent off-site power sources 1

RED available to A-05 and A-06 (totally 2

ORANGE independent at the 4160 V, 13.8 kV, 3

and 345 kV levels)

(0-2) 2 4-5

2.

G-01 or G-02/A-05/B-03 available (0-1) 1 G-03 or G-041A-061B-04 available (0-1) 1

3.

G-05 available, Reactor Cavity filled to 2 23 ft above the top of the reactor vessel flange, upper internals removed and RCS time to boil 2 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

(0-1) 0 Subtotal =

4 INVENTORY Subtotal Condition 014 RED..

1.

Pressurizer level >20 percent w/head on (0-1) 0 2

ORANGE

2.

Refueling Cavity filled (see definition)

(0-3) 2 3

x

3.

RCS level above REDUCED INVENTORY (0-1) 1 4

4.

Makeup from VCTIBLENDER and/or RWST available (0-2) 1 Subtotal =

4 PBF-1S62 Revision 2 10/30102 hI ~taxe wiff Ni Freedoml of In~fomadon A4W A~z 4-1 rzl of 9

References:

NP 10.3.6 NP 10.2.1

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST CONTAINMENT

1.

Containment integrity (TS 15.1.D) (Containment Operable) (ITS TS 3.6.1) set

2.

Containment Closure CL-IE maintained and closure < time to boil

3.

No fuel motion

4.

DHR Capability:

cavity flooded and internals out OR at least one SG available OR one fan cooler with Equip hatch installed and personnel hatches capable of being shut (O or 4) 0.

( or 2) 2 (0-1) 1 Subtotal Condition 0

RED I

ORANGE 2-3 4-5-6 E

E I

(0-1) 1 Subtotal =

4 SPENT FUEL POOL COOLING (ONLY APPLICABLE when starting AND during FULL CORE OFFLOADS)

NOTE:

Take creditfor only one P-12 independent offsite power source during periods of singe X-03 or X.04 availability (*)

.Subtotal.

Condition 1..

"A" SFP cooling pump available 0-1 RED.

with power available from:

,2 ORANGE G-02 or G-01 via 2B-32 (0-1)

NA-3 YELLOW

  • (*) an independent off-site power 4-5 GREEN source different than that for Train B below
2.

"B" SFP cooling pump available with power available from:

G-03 or G-04 via IB-42

  • (*) an independent off-site power source different than that for Train A above
3.

Temporary power available to one SFP cooling pump, G-05 available, and SFP time to boil 2 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

(0-1)

NA (0-1)

NA (0-1)

NA (0-1)

NA SFP Temperatures:

NW NA 0F SE NA

°OF SFP Average Temp NA SFP Time to Boil NA Subtotal =

NA OF GIVE A BRIEF EXPLANATION OF ANY CHANGE IN SAFETY ASSESSMENT THAT TOOK PLACE:

None PBF-1562 Revision 2 10/30/02 Page 2of 9

References:

NP 10.3.6 NP 10.2.1

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT:

1 DATE:

May 17, 2004 TIME:

0200 KEY SAFETY FUNCTIONS:

REACTIVITY:

CORE COOLING:

POWER AVAILABLE:

INVENTORY:

CONTAINMENT:

SFP COOLING:

GREEN GREEN GREEN GREEN GREEN NA PROTECTED EOUIPMENT:

COMMENTS:

RCS Time to Boil is 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Using NP 10.3.6 Time To Boil curves.

Fire Protection Condition IV: Credit is taken for fire rounds as fire prevention contingency Removed Unit I Safety Injection Pump (0P-1513) from Protected Equipment list.

PBF-1562 Revision 2 10/30/02

References:

NP 10.3.6 Page 5 of 9 NP 10.2.1