Pbnp Shutdown Safety Assessment and Fire Condition Checklist
ML051890456
Person / Time
Site: Point Beach 
Issue date: 04/09/2004
From: Black D
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML051890456 (3)


Text

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST Date:

April 9,2004 Time:

2230 Preparer:

David Black U

I R

28 NOTE:

Refer to base procedureNP 10.3.6for safety assessment checklist KSFdefinitions.

NOTE:

WIheneverfuel has been removedfrom the reactor vessel and refueling cavity, all key safetyfunctions are GREEN except spentfuelpool cooling.

KEY SAFETY FUNCTION CRITERIA: No/False = 0, Yes/True = I through 4 REACTIVITY Subtotal Condition I.

RCS Boron concentration = 2839 ppm a.)

For RSD, RCS boron >Refueling boron concentration specified in unit-specific COLR (TRM 2.1) b.)

For CSD and prior to RSD no fuel motion, RCS boron > boron concentration required by OP 3C (0-1)

I 0-1 RED

2.

Number of boration paths (0-2) 2 2

ORANGE

3.

No fuel motion (0-1) 1 3-4

4.

SR instrumentation operable (0-1) 1 5(G GEEN Subtotal 5

CORE COOLING Subtotal Condition

1.

Number of SG available for DHR (0-2) 0 0-1 RED

2.

Refueling cavity filled (0-1) 0 2

3.

Number of trains RHR available (0-2) 2 3

YEL

4.

RCS level above REDUCED INVENTORY (0-1) 1 4-5 RCS TEMP = I00"F; 6 days shutdown; RCS 70%

Subtotal 3

RCS Time to Boil 37 min (Applicable at Cold or Refueling Shutdown)

POWER AVAILABILITY Subtotal Condition

1.

Independent off-site power sources 1

RED available to A-05 and A-06 (totally 2

ORANGE independent at the 4160 V, 13.8 kV, 3

and 345 kV levels)

(0-2) 2 4-5

2.

G-01 or G-02/A-05/B-03 available (0-1) 1 G-03 or G-04/A-06/B-04 available (0-1) 1

3.

G-05 available, Reactor Cavity filled to 2 23 fR above the top of the reactor vessel flange, upper internals removed and RCS time to boil 2 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

(0-1) 0 Subtotal 4

INVENTORY Subtotal Condition

1.

Pressurizer level 220 percent w/head on 0-1 RED (0-1) 0 2

2.

Refueling Cavity filled (see definition)

(0-3) 0 3

(YELLOWVJ

3.

RCS level above REDUCED INVENTORY (0-1) 1 4

4.

Makeup from VCT/BLENDER and/or RWST available (0-2) 2 Subtotal 3

  • ljzu an uone record was deleted in accordance
iwith, te Freedom of Inforn ation PBF-562 Act, exePIt ios Revilsion 2 10/30/09 At J9-37

References:

NP 10.3.6 NP 10.2.1

?age I of 9

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST CONTAINMENT

1.

Containment integrity (TS 15.1.D) {Containment Operable) (ITS TS 3.6.1) set

2.

Containment Closure CL-IE maintained and closure < time to boil

3.

No fuel motion

4.

DHR Capability:

cavity flooded and internals out OR at least one SG available OR one fan cooler with Equip hatch installed and personnel hatches capable of being shut (O or 4) 0

( or 2) 2 (0-1) 1 Subtotal 0

l 2-3 4-5-6 Condition RED ORANGE (0-1) 1 Subtotal -

4 SPENT FUEL POOL COOLING (ONLY APPLICABLE when starting AND during FULL CORE OFFLOADS)

NOTE:

Take creditfor only one P-12 Independent offslte power source during periods of single X-03 or X-04 availability (*).

Subtotal Condition

1.

"A' SFP cooling pump available 0-1 RED with power available from:

2 ORANGE G-02 orG-0I via 2B-32 (0-1) n/a 3

YELLOW

-(i) an independent off-site power 4-5 GREEN source different than that for Train B below

2.

"B" SFP cooling pump available with power available from:

G-03 orG-04 via IB-42

.*)

an independent off-site power source different than that for Train A above

3.

Temporary power available to one SFP cooling pump, G-05 available, and SFP time to boil 2 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

(0-1) n/a (0-1) n/a (0-1) n/a (0-1) n/a Subtotal =

n/a SFP Temperatures:

NW n/a OF SE n/a OF SFP Average Temp n/a SFP Time to Boil n/a GIVE A BRIEF EXPLANATION OF ANY CHANGE IN SAFETY ASSESSMENT THAT TOOK PLACE:

Reactor Vessel Level Is now ABOVE reduced Inventory, therefore Core cooling and Inventory changed from orange to yellow.

PBF-1562 Revision 2 10/30102 Refcrences: NP 103.6 NP 10.2.1 Page 2 of 9

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT:

I DATE:

April 9, 2004 TIME:

2230 KEY SAFETY FUNCTIONS:

REACTIVITY:

GREEN CORE COOLING:

YELLOW POWER AVAILABLE:

GREEN CONTAINMENT:

GREEN INVENTORY:

SFP COOLING: NA YELLOW PROTECTED EOUIPMENT:

Fire Protection Condition III: Credit token for existing fire rounds RCS Time to Boil is 37 minutes RCS is at 70% Reactor Vessel Level PBF.1562 Revislon 2 10/30/02

References:

NP 103.6 NP 10.2.1 Page 5 of 9