ML051590443
| ML051590443 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse (NPF-003) |
| Issue date: | 06/15/2005 |
| From: | Suh G NRC/NRR/DLPM/LPD3 |
| To: | Bezilla M FirstEnergy Nuclear Operating Co |
| Macon W, NRR/DLPM,415-3965 | |
| References | |
| EA-03-086, TAC MC5713 | |
| Download: ML051590443 (4) | |
Text
NOTICE: Enclosure contains Safeguards Information. Upon separation from the Enclosure, this letter is DECONTROLLED.
SAFEGUARDS INFORMATION June 15, 2005 Mr. Mark A. Bezilla Vice President - Nuclear FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State, Route 2 Oak Harbor, OH 43449
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - CORRECTION OF ADMINISTRATIVE CHANGES TO SAFETY EVALUATION REGARDING REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN PURSUANT TO COMMISSION ORDER EA-03-086 (TAC NO. MC5713)
Dear Mr. Bezilla:
By letter dated October 28, 2004, the U.S. Nuclear Regulatory Commission (NRC) issued an administrative license change to the Davis-Besse Nuclear Power Station, Unit 1, Facility Operating License NPF-3, to incorporate the reference to the recently-revised physical security plan, training and qualification plan, and safeguards contingency plan.
By letter dated December 10, 2004, you identified inconsistencies in the safety evaluation (SE) associated with the October 28, 2004, letter. The NRC staff has reviewed the inconsistencies identified in your letter, and concluded that the inconsistencies required modification of the SE.
For the most part, the inconsistencies you identified were either editorial in nature or clarified the SE with regard to statements made in the revised security plans. The corrections made to the SE did not change the NRC staffs previous evaluation of the revised security plans.
SAFEGUARDS INFORMATION
SAFEGUARDS INFORMATION M. Bezilla SAFEGUARDS INFORMATION The corrected SE pages are enclosed. The revised portions of the SE are denoted with revision bars. The NRC staff regrets any inconvenience the inconsistencies may have caused.
If there are any further questions, please contact the NRC Project Manager, Mr. William Macon, at 301-415-3965.
Sincerely,
/RA/
Gene Y. Suh, Chief, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Corrected SE pages (SAFEGUARDS INFORMATION) cc w/o enclosure: See next page
SAFEGUARDS INFORMATION M. Bezilla SAFEGUARDS INFORMATION June 15, 2005 The corrected SE pages are enclosed. The revised portions of the SE are denoted with revision bars. The NRC staff regrets any inconvenience the inconsistencies may have caused.
If there are any further questions, please contact the NRC Project Manager, Mr. William Macon, at 301-415-3965.
Sincerely,
/RA/
Gene Y. Suh, Chief, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Corrected SE pages (SAFEGUARDS INFORMATION) cc w/o enclosure: See next page DISTRIBUTION (w/o encl):
PUBLIC RidsNrrDlpmLpdiii2 (GSuh)
RidsOgcRp SMorris RidsNrrLADClarke RidsAcrsAcnwMail WSmith RidsNrrPMWMacon RidsNrrDlpmDpr PLee RidsRgnIIIMailCenter PDIII-2 R/F Accession No.: ML051590443 Nrr-106 OFFICE PDIII-1/PM PDIII-2/LA NSIR/RSS NSIR/RSS PDIII-2/SC NAME WMacon DClarke WSmith PLee GSuh DATE 6/15/05 6/15/05 6/14/05 6/13/05 6/15/05 OFFICIAL RECORD COPY
Davis-Besse Nuclear Power Station, Unit 1 cc:
Mary E. O'Reilly FirstEnergy Corporation 76 South Main St.
Akron, OH 44308 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Regional Administrator U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60523-4351 Michael A. Schoppman Framatome ANP 24 Calabash Court Rockville, MD 20850 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Barry Allen, Plant Manager FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Office of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760