MONTHYEARML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary BYRON 2024-0046, Cycle 27 Core Operating Limits Report2024-09-19019 September 2024 Cycle 27 Core Operating Limits Report RS-24-088, Relief Requests Associated with the Fifth Inservice Inspection Interval2024-09-13013 September 2024 Relief Requests Associated with the Fifth Inservice Inspection Interval ML24250A1182024-09-0606 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information 05000454/LER-2024-001, Both Trains of Control Room Ventilation Temperature Control System Inoperable2024-09-0505 September 2024 Both Trains of Control Room Ventilation Temperature Control System Inoperable ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit IR 05000454/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Byron Station, Units 1 and 2 (Report 05000455/2024005 and 05000454/2024005) ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000454/20240112024-08-0808 August 2024 Phase 2 Post- Approval License Renewal Report 05000454/2024011 IR 05000454/20240022024-07-26026 July 2024 Integrated Inspection Report 05000454/2024002 and 05000455/2024002, and Exercise of Enforcement Discretion ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions RS-24-066, Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller2024-06-25025 June 2024 Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller ML24170A7652024-06-19019 June 2024 Confirmation of Initial License Examination RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report BYRON 2024-0031, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-05-16016 May 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation IR 05000454/20240012024-05-10010 May 2024 Integrated Inspection Report 05000454/2024001; 05000455/2024001 and 07200068/2024001 BYRON 2024-0028, Annual Radiological Environmental Operating Report (AREOR)2024-05-0909 May 2024 Annual Radiological Environmental Operating Report (AREOR) BYRON 2024-0022, 2023 Regulatory Commitment Change Summary Report2024-05-0202 May 2024 2023 Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A1192024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) ML24113A2892024-04-22022 April 2024 Notification of NRC Baseline Inspection and Request for Information BYRON 2024-0020, Annual Dose Report for 20232024-04-18018 April 2024 Annual Dose Report for 2023 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition BYRON 2024-0021, Registration of Use of Cask to Store Spent Fuel2024-04-11011 April 2024 Registration of Use of Cask to Store Spent Fuel RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors IR 05000454/20244012024-04-0303 April 2024 Cyber Security Inspection Report 05000454/2024401 and 05000455/2024401 (Public) RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report BYRON 2024-0019, Registration of Use of Cask to Store Spent Fuel2024-03-28028 March 2024 Registration of Use of Cask to Store Spent Fuel RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds IR 05000454/20230112024-03-20020 March 2024 Fire Protection Team Inspection Report 05000454/2023011 and 05000455/2023011 IR 05000454/20240102024-03-15015 March 2024 Comprehensive Engineering Team Inspection Report 05000454/2024010 and 05000455/2024010 IR 05000454/20230062024-02-28028 February 2024 Annual Assessment Letter for Byron Station, Units 1 and 2 (Report 05000455/2023006 and 05000454/2023006) IR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code IR 05000454/20233012023-11-27027 November 2023 NRC Initial License Examination Report 05000454/2023301 and 05000455/2023301 BYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) IR 05000454/20230032023-11-13013 November 2023 Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion 2024-09-06
[Table view] |
Text
May 17, 2005 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
UPCOMING BYRON PROBLEM IDENTIFICATION AND RESOLUTION (PI&R)
INSPECTION
Dear Mr. Crane:
On June 13, 2005, the NRC will begin the biennial problem identification and resolution (PI&R) inspection at your Byron Nuclear Power Station. This inspection will be performed in accordance with the NRC baseline inspection procedure 71152.
Experience has shown that these inspections are extremely resource intensive both for the NRC inspectors and the utility staff. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection.
The documents requested are copies of condition reports and lists of information, necessary in order to ensure the inspection team is adequately prepared for the inspection. The documents should be ready for NRC review by May 31, 2005. Mr. Nirodh Shah, the lead inspector, will contact your staff to determine the best method of providing the information to the inspectors.
If there are any questions about the material requested, or the inspection in general, please call Nirodh Shah at 815-458-2852.
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David Passehl, Acting Chief Branch 3 Division of Reactor Projects Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66
Enclosure:
Request for Information Regarding PI&R Inspection cc w/encl: Site Vice President - Byron Station Plant Manager - Byron Station Regulatory Assurance Manager - Byron Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer, State of Illinois State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission B. Quigley, Byron Station DOCUMENT NAME: E:\Filenet\ML051370271.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII NAME DPassehl:dtp DATE 05/17/05 OFFICIAL RECORD COPY
C. Crane ADAMS Distribution:
GYS GFD RidsNrrDipmIipb GEG KGO RAS DRPIII DRSIII PLB1 JRK1
Requested Information to Support Problem Identification and Resolution (PI&R) Inspection
- 1. A copy of administrative procedure(s) for the corrective action process, trending program, quality assurance audit program, self-assessment program, corrective action effectiveness review program, and industry operating experience review program.
- 2. Scheduled date/time/location of all meetings associated with implementation of the corrective action program, such as CR screening meetings, corrective action review board meetings, etc.
- 3. A copy of nuclear quality assurance audits and self-assessments of the corrective action program completed since December 2003.
- 4. A chronological list of nuclear quality assurance audits and self-assessments completed for all departments since December 2003.
- 5. A chronological list of operability determinations initiated since June 2000.
- 6. A chronological list of all open apparent cause evaluations and root cause evaluations.
Include a description, date initiated, and whether there was an associated operability evaluation.
- 7. A chronological list of all closed root and apparent cause evaluations since June 2000.
Include a description, date initiated, date closed, and whether there was an associated operability evaluation.
- 8. A chronological list of condition reports initiated since December 2003 that involve inadequate or ineffective corrective actions. Include a brief description and status, whether open or closed.
- 9. A chronological list of in-service test or Technical Specification surveillance test failures since December 2003, with a brief description of the component/system which failed.
- 10. A copy of the latest corrective action program performance indicators.
- 11. Any performance indicators associated with backlog of corrective maintenance items.
- 12. A chronological list of operating experience documents received since June 2000 and any associated condition reports.
- 13. A chronological list of condition reports and work documents written since June 2000 associated with the Auxiliary Feedwater and Emergency Diesel Generator Systems.
- 14. A chronological list of condition reports associated with human performance errors since June 2000.
Enclosure
- 15. A chronological list of condition reports issued since June 2000 where the NRC was the identifying organization.
- 16. A list of condition reports associated with Non-Cited Violations from NRC Inspection Reports received since June 2000.
- 17. A chronological list of all Licensee Event Reports issued since June 2000, with a brief description of the affected components or systems.
- 18. Have available for review and use a copy of the Quality Assurance manual.
- 19. Have available for review and use a copy of the latest organization chart and phone listing.
Enclosure