Special Report 2-SR-2005-001
ML051300346
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 04/27/2005
From: Danni Smith
Arizona Public Service Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
102-05255-DMS/DGM/DFH
Download: ML051300346 (3)


Text

Technical Specification 5.6.8 LA:PS Palo Verde Nuclear Generating Station A subsidiary of Pinnacle West Capital Corporation David M. Smith Plant Manager Nuclear Production Tel: 623-393-6116 Fax: 623-393-6077 e-mail: DSMITHIO@apsccom Mail Station 7602 PO Box 52034 Phoenix, Arizona 85072-2034 102-05255-DMS/DGM/DFH April 27, 2005 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Unit 2 Docket No. STN 50-529 Special Report 2-SR-2005-001 Attached please find Special Report 2-SR-2005-001 prepared and submitted pursuant to Technical Specifications (TS) Reporting Requirement 5.6.8. This report discusses steam generator tube plugging in Unit 2. Pursuant to Technical Specification 5.6.8, the complete results of the steam generator tube inservice inspection will be submitted by April 17, 2006. Copies of the Special Report are being forwarded to the Regional Administrator, NRC Region IV and the PVNGS Resident Inspector.

No commitments are being made to the NRC by this letter.

If you have any questions, please contact Daniel G. Marks at (623) 393-6492.

Sincerely,/

DMS/DGM/DFH/ca Attachment cc:

(with attachment)

B. S. Mallett M. B. Fields G. G. Warnick NRC Region IV Regional Administrator NRC NRR Project Manager NRC Senior Resident Inspector for Palo Verde A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway 0 Comanche Peak 0 Diablo Canyon 0 Palo Verde 0 South Texas Project 0 Wolf Creek

'kP 04

  • I Attachment Special Report No. 2-SR-2005-001

Palo Verde Nuclear Generating Station Unit 2 Steam Generator Tube Plugging Docket No. STN 50-529 Special Report No. 2-SR-2005-001 This Special Report is being provided pursuant to Palo Verde Unit 2 Technical Specifications (TS) Reporting Requirement 5.6.8 to report the number of steam generator tubes plugged and/or repaired as a result of inservice inspection activities.

On April 17, 2005, Unit 2 was in Mode 6 during a refueling outage when an inservice inspection of both steam generators was completed. The inspection resulted in the plugging of 8 tubes in Steam Generator No. 1 and 7 tubes in Steam Generator No. 2.

Pursuant to Technical Specification 5.6.8, the complete results of the steam generator tube inservice inspection will be submitted by April 17, 2006.