MONTHYEARML0421201472004-07-29029 July 2004 G20040511 - Paul M. Blanch and Arnold Gundersen Ltr. Re 2.206 - Vermont Yankee - Enforcement Action for Clarification to 10CFR50, Appendix a Project stage: Request ML0428704772004-08-26026 August 2004 Transcript of August 26, 2004, Meeting Vermont Yankee Project stage: Request ML0428200902004-09-29029 September 2004 Entergy'S Answer to the New England Coalition'S Request for Hearing Project stage: Request ML0511003702005-01-0707 January 2005 G20050008 - Proposed Director'S Decision Re 2.206 - Vermont Yankee - Clarification of Design Basis Conformance Project stage: Other ML0425901432005-01-17017 January 2005 G20050008 - Paul Blanch and Arnold Gunderson Ltr 2.206 - Vermont Yankee - Enforcement Action for Clarification to 10 CFR 50, Appendix a Project stage: Other ML0511004182005-05-13013 May 2005 Request for Information Revision to Updated Final Safety Analysis, Appendix F Project stage: RAI ML0511801182005-05-17017 May 2005 G20050008 - Michael Kansler Ltr Re 2.206 - Vermont Yankee - Clarification of Design Basis Conformance - Request for Licensee Comments on Proposed Director'S Decision Project stage: Other ML0511003472005-05-17017 May 2005 G20050008 - Paul Blanch and Arnold Gundersen Ltr Re 2.206 - Vermont Yankee - Clarification of Design Basis Conformance - Request for Comments on Proposed Director'S Decision Project stage: Other BVY 05-065, Response to Request for Information Regarding Updated Final Safety Analysis Report, Appendix F2005-06-14014 June 2005 Response to Request for Information Regarding Updated Final Safety Analysis Report, Appendix F Project stage: Response to RAI ML0521702062005-08-16016 August 2005 G20050008 - Final Director'S Decision Paul Blanch and Arnold Gundersen 2.206 Petition - Vermont Yankee - Clarification of Design Basis Conformance Project stage: Other ML0521702172005-08-16016 August 2005 G20050008 - Federal Register Notice Paul Blanch and Arnold Gundersen 2.206 Petition - Vermont Yankee - Clarification of Design Basis Conformance Project stage: Other ML0521701992005-08-16016 August 2005 G20050008 - Paul Blanch and Arnold Gundersen Ltr Re. 2.206 Petition - Vermont Yankee - Clarification of Design Basis Conformance Project stage: Other 2005-01-07
[Table View] |
|
---|
Category:Letter
MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000271/20220022023-02-22022 February 2023 Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station - NRC Inspection Report No. 05000271/2022002 BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond ML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 05000271/20224012022-12-15015 December 2022 NRC Inspection Report No. 05000271/2022401, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont (Letter Only) BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust ML22273A1492022-10-0404 October 2022 Review of Decommissioning Funding Status 2022 BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20220012022-08-0101 August 2022 NRC Inspection Report No. 05000271/2022001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate 2024-01-04
[Table view] |
Text
May 17, 2005 Mr. Paul Blanch 135 Hyde Road West Hartford, CT 06117 Mr. Arnold Gundersen 139 Killarney Drive Burlington, VT 05401
Dear Messrs. Blanch and Gundersen:
Your July 29, 2004, Petition addressed to Luis Reyes, Executive Director for Operations at the Nuclear Regulatory Commission (NRC or the Commission), has been reviewed by the NRC staff pursuant to Title 10 of the Code of Federal Regulations, Section 2.206 of the Commission's regulations. The NRC staffs proposed Directors Decision (DD) on the Petition is enclosed. Please provide comments to me on any portions of the DD that you believe involve errors or any issues in the Petition that you believe have not been fully addressed. The NRC staff is making a similar request of the licensee. The NRC staff will then review any comments provided by you and the licensee and consider them in the final version of the DD. You will have no further opportunity to comment.
Please provide your comments within 30 days of the date of this letter.
Sincerely,
/RA/
Ledyard B. Marsh, Director Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosure:
Proposed Director's Decision cc w/encl: See next page
Mr. Paul Blanch 135 Hyde Road West Hartford, CT 06117 Mr. Arnold Gundersen 139 Killarney Drive Burlington, VT 05401
Dear Messrs. Blanch and Mr. Gundersen:
Your July 29, 2004, Petition addressed to Luis Reyes, Executive Director for Operations at the Nuclear Regulatory Commission (NRC or the Commission), has been reviewed by the NRC staff pursuant to Title 10 of the Code of Federal Regulations, Section CFR 2.206 of the Commission's regulations. The NRC staffs proposed Directors Decision (DD) on the Petition is enclosed. Please provide comments to me on any portions of the DD that you believe involve errors or any issues in the Petition that you believe have not been fully addressed. The NRC staff is making a similar request of the licensee. The NRC staff will then review any comments provided by you and the licensee and consider them in the final version of the DD. You will have no further opportunity to comment.
Please provide your comments within 30 days of the date of this letter.
Sincerely,
/RA/
Ledyard B. Marsh, Director Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosure:
Proposed Director's Decision cc w/encl: See next page Package: ML051100378 Incoming: ML050100055 M. Kansler Letter - Request for Comments: ML051180118 P. Blanch/A. Gundersen Letter - Request for Comments: ML051100347 Proposed Directors Decision: ML051100370 NRR-106 OFFICE PDI-2/PM PDI-2/PM PDI-2/LA TechEd PDI-2/SC PDI/PD NAME JBoska REnnis CRaynor PKleene DRoberts CHolden DATE 5/4/05 4/27/05 4/26/05 4/28/05 5/12/05 5/6/05 OFFICE DLPM/D NRR/D NAME JLyons for TMarsh BSheron for JDyer DATE 5/13/05 5/17/05 OFFICIAL RECORD COPY
Dated: May 17, 2005 DISTRIBUTION: G20050008 PUBLIC PDI-2 Reading RidsEdoMailCenter RidsOgcMailCenter RidsNrrOD RidsNrrAdpt RidsRgn1MailCenter RidsNrrPMREnnis RidsNrrPMDSkay RidsNrrLACRaynor CHolden DRoberts LCox RidsOPAMailCenter RidsOCAMailCenter RidsAcrsAcnwMailCenter SECY (EJulian)
RidsNRRWpcMail BPoole, OGC VBucci, OIG ASLBP VYanez
Vermont Yankee Nuclear Power Station cc:
Regional Administrator, Region I U. S. Nuclear Regulatory Commission Ms. Carla A. White, RRPT, CHP 475 Allendale Road Radiological Health King of Prussia, PA 19406-1415 Vermont Department of Health P.O. Box 70, Drawer #43 Mr. David R. Lewis 108 Cherry Street Pillsbury, Winthrop, Shaw, Pittman, LLP Burlington, VT 05402-0070 2300 N Street, N.W.
Washington, DC 20037-1128 Mr. James M. DeVincentis Manager, Licensing Ms. Christine S. Salembier, Commissioner Vermont Yankee Nuclear Power Station Vermont Department of Public Service P.O. Box 0500 112 State Street 185 Old Ferry Road Montpelier, VT 05620-2601 Brattleboro, VT 05302-0500 Mr. Michael H. Dworkin, Chairman Resident Inspector Public Service Board Vermont Yankee Nuclear Power Station State of Vermont U. S. Nuclear Regulatory Commission 112 State Street P.O. Box 176 Montpelier, VT 05620-2701 Vernon, VT 05354 Chairman, Board of Selectmen Director, Massachusetts Emergency Town of Vernon Management Agency P.O. Box 116 ATTN: James Muckerheide Vernon, VT 05354-0116 400 Worcester Rd.
Framingham, MA 01702-5399 Operating Experience Coordinator Vermont Yankee Nuclear Power Station Jonathan M. Block, Esq.
320 Governor Hunt Road Main Street Vernon, VT 05354 P.O. Box 566 Putney, VT 05346-0566 G. Dana Bisbee, Esq.
Deputy Attorney General Mr. John F. McCann 33 Capitol Street Director, Nuclear Safety Assurance Concord, NH 03301-6937 Entergy Nuclear Operations, Inc.
440 Hamilton Avenue Chief, Safety Unit White Plains, NY 10601 Office of the Attorney General One Ashburton Place, 19th Floor Mr. Gary J. Taylor Boston, MA 02108 Chief Executive Officer Entergy Operations Ms. Deb Katz, Executive Director 1340 Echelon Parkway Nuclear Security Coalition Jackson, MS 39213 c/o Citizens Awareness Network Box 83 Shelburne Falls, MA 01370
Vermont Yankee Nuclear Power Station cc:
Mr. John T. Herron Mr. Ronald Toole Sr. VP and Chief Operating Officer 1282 Valley of Lakes Entergy Nuclear Operations, Inc. Box R-10 440 Hamilton Avenue Hazelton, PA 18202 White Plains, NY 10601 Ms. Stacey M. Lousteau Mr. Danny L. Pace Treasury Department Vice President, Engineering Entergy Services, Inc.
Entergy Nuclear Operations, Inc. 639 Loyola Avenue 440 Hamilton Avenue New Orleans, LA 70113 White Plains, NY 10601 Mr. James P. Matteau Mr. Brian OGrady Executive Director Vice President, Operations Support Windham Regional Commission Entergy Nuclear Operations, Inc. 139 Main Street, Suite 505 440 Hamilton Avenue Brattleboro, VT 05301 White Plains, NY 10601 Mr. William K. Sherman Mr. Michael J. Colomb Vermont Department of Public Service Director of Oversight 112 State Street Entergy Nuclear Operations, Inc. Drawer 20 440 Hamilton Avenue Montpelier, VT 05620-2601 White Plains, NY 10601 Mr. Michael Kansler Mr. John M. Fulton President Assistant General Counsel Entergy Nuclear Operations, Inc.
Entergy Nuclear Operations, Inc. 440 Hamilton Avenue 440 Hamilton Avenue White Plains, NY 10601 White Plains, NY 10601 Mr. Jay K. Thayer Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. Kenneth L. Graesser 38832 N. Ashley Drive Lake Villa, IL 60046 Mr. James Sniezek 5486 Nithsdale Drive Salisbury, MD 21801