Calvert Cliffs Nuclear Power Plant Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 Constellation I
Energy Group April 14, 2005 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
SUBJECT:
Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. I & 2; Docket Nos. 50-317 & 50-318 March 2005 Monthly Operating Reports The subject reports are being sent to you as required by Technical Specification 5.6.4.
Should you have questions regarding this matter, we will be pleased to discuss them with you.
Very truly yours David A. Holm Plant General Manager DAH/CAN/bjd
Attachment:
March 2005 Monthly Operating Reports cc:
R. V. Guzman, NRC S. J. Collins, NRC Resident Inspector, NRC R. I. McLean, DNR S. Mainieri, INPO K. N. Larson, ANI
,, j 7>1-,
ATTACHMENT MARCH 2005 MONTHLY OPERATING REPORTS Calvert Cliffs Nuclear Power Plant, Inc.
April 14, 2005
i MONTHLY OPERATING REPORT Docket No. 50-3 17 Calvert Cliffs Unit 1 April 5, 2005 Prepared by Herman 0. Olsen Telephone: (410) 495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
MARCH 2005 845 870 Year-Cumulative to-Date to Date
- 1. NUMBER OF HOURS REACTOR WAS CRITICAL
- 2. HOURS GENERATOR ON LINE
- 3. UNIT RESERVE SHUTDOWN HOURS
- 4. NET ELECTRICAL ENERGY GENERATED (MWH)
This month 720.3 710.4 0.0 629,136 2,136.3 2,126.4 0.0 1,900,752 202,260.6 199,047.2 0.0 163,574,449
UNIT SHUTDOWNS DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-317 Calvert Cliffs - U!
April 4, 2005 Herman 0. Olsen (410) 495-6734 REPORTING MONTH March 2005 TYPE METHOD OF CAUSE/CORRECTIVE ACTIONS NO.
DATE F:
FORCED DHOURSA REASON SHUTTING S:
SCHEDULED (H
)
DOWN 2 COMMENTS05-001 05/03/01 F
33.6 A
2 On 03/01/2005 a reduction in power was in progress in preparation for shutting down to repair a steam leak on the II Moisture Separator Reheat (MSR) Drain Tank vent line. Turbine vibration was noted to be increasing.
and continued to increase until it reached the manual trip criteria. The reactor was manually tripped from 15%
power at 0043. The 11 MSR Drain Tank vent line was replaced. The reactor was taken critical and the unit was paralleled to the grid on 03/02/2005 at 1019. No problems or vibration issues were noted on the startup and loading of the Main Turbine.
l Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2
Method:
I - Manual 2 - Manual Scram.
3 - Automatic Scram.
4 - Continued 5 - Other
DOCKET NO. 50-317 CALVERT CLIFFS - UNIT I April 4, 2005
SUMMARY
OF OPERATING EXPERIENCE March 2005 The unit began the month at 30% reactor power in the process of shutting down to repair a steam leak on 11 Moisture Separator Reheater Drain Tank vent line.
On 03/02/2005 at 0016 Turbine vibration was noted to be increasing. At 0039 vibration was at 10 mils and increasing. The reactor wvas tripped at 0043 from 15% power.
The 11 Moisture Separator Reheater Drain Tank vent was replaced and the unit was started up from Mode 3. The reactor was critical on 03/02/2005 at 0028 and the unit was paralleled to the grid at 1019.
Reactor power was returned to 100% at 2000.
The unit continued to operate at 100% power for the remainder of the month.
MONTHLY OPERATING REPORT Docket No. 50-318 Calvert Cliffs Unit 2 April 5, 2005 Prepared by Herman 0. Olsen Telephone: (410) 495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
MARCH 2005 845 858 Year-Cumulative to-Date to Date This month
- 1. NUMBER OF HOURS REACTOR WAS CRITICAL
- 2. HOURS GENERATOR ON LINE
- 3. UNIT RESERVE SHUTDOWN HOURS
- 4. NET ELECTRICAL ENERGY GENERATED (MWH) 416.6 380.8 0.0 321,510 1,685.9 1,649.8 0.0 1,424,968 195,147.1 193,217.6 0.0 159,720,456
.D UNIT ShUTDOWNS DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-318 Calvert Cliffs-U2 April 4. 2005 Herman 0. Olsen (410) 495-6734 REPORT MONTH March 2005 TYPE DURATION METHOD OF CAUSE/CORRECTIVE ACTIONS NO.
DATE F:
FORCED DURA REASON' SHUTTING S:
SCHEDULED (HOURS)
DOWN 2 COMMENTS05-001 05/02/22 S
363.2 C
2 The unit began the month in mode 6 as part of the planned refueling outage. The unit was heated up and paralleled to the grid on 03/16/2005 at 0312.
l Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2
Method:
1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 - Other
DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 April 4, 2005
SUMMARY
OF OPERATING EXPERIENCE March 2005 The unit began the month in mode 6.
The following significant work was completed during the month:
Reactor was refueled.
Reactor vessel head was inspected.
Alloy 600 inspections were completed.
Plant heat up and start up were performed and the reactor was critical on 03/14/2005 at 1526. The unit was paralleled to the grid on 03/15/2005 at 0312. Reactor power was increased and reached 100% on 03/17/2005 at 2250.
The unit operated at 100% reactor power for the remainder of the month.