ML050970295

From kanterella
Jump to navigation Jump to search
Summary of Meeting with Amergen, Licensee'S TMI-1 Steam Generator (SG) Kinetic Expansion (Ke) Inspection and Acceptance Criteria
ML050970295
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 04/28/2005
From: Colburn T
NRC/NRR/DLPM/LPD1
To:
Office of Nuclear Reactor Regulation
Colburn T, NRR/DLPM, 415-1402
References
Download: ML050970295 (7)


Text

April 28, 2005 LICENSEE: AmerGen Energy Company, LLC (AmerGen)

FACILITY: Three Mile Island Nuclear Station, Unit 1 (TMI-1)

SUBJECT:

SUMMARY

OF FEBRUARY 16-17, 2005, CATEGORY 1 WORKING-LEVEL MEETING WITH AMERGEN TO DISCUSS THE LICENSEES TMI-1 STEAM GENERATOR (SG) KINETIC EXPANSION (KE) INSPECTION AND ACCEPTANCE CRITERIA On February 16-17, 2005, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of AmerGen, the licensee for TMI-1, and Exelon Generation Company, LLC, in the NRC Headquarters, located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to conduct a working-level discussion of the licensees response to the NRC staffs issues with the licensees TMI-1 SG KE inspection and acceptance criteria report dated October 4, 2002, as supplemented August 16, 2004 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.

ML022840503 and ML042370131).

AmerGen presented information on the history and background of the installed KEs and the schedule for replacement of SGs at TMI-1. The licensee addressed the seven categories of the NRC staffs issues: (1) suitability of leaving circumferential flaws in service, (2) Leakage assessment including a thermal hydraulic analysis model, (3) the basis for the assumption of no growth/no initiation of new flaws, (4) structural integrity assessment, (5) consistency with recent industry experience, (6) inspection practices/techniques, and (7) other issues, which were enumerated in the meeting agenda attached to the meeting notice (ADAMS Accession No. ML050340182).

The discussions centered on open issues with the criteria which are related to flaws located in the expanded portion of the tube within the hot-leg tubesheet. Two of the major outstanding issues pertain to the adequacy of the assumptions and inputs into the thermal hydraulic model and whether the licensee has selected the most limiting accident for assessing the structural and leakage integrity of the tubing. These issues must be resolved before the licensee can adopt the new SG technical specifications which will be the subject of a future NRC staff generic communication.

The licensee indicated a number of new commitments which would be formalized in the next revision of the KE inspection and acceptance criteria report including plugging circumferential cracks in the pressure boundary, conducting a 100% scope inspection each outage until SG replacement, and plugging of new indications.

CONTACT: T. Colburn, NRR 301-415-1402 tgc@nrc.gov

AmerGen No members of the public other than the licensee were in attendance. No licensee attendees chose to complete any Public Meeting Feedback Forms (NRC Form 659) which were available at the meeting. is a list of the meeting attendees, and Enclosure 2 is a copy of the licensees slides presented at the meeting.

Please direct any inquiries to Timothy G. Colburn, Senior Project Manager, at 301-415-1402, or tgc@nrc.gov.

/RA/

Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-289

Enclosures:

1. List of Attendees
2. Licensees Handout cc w/encls: See next page

ML050970295 OFFICE PDI-1/PM PDI-2/LA EMCB\SC PDI-1/SC NAME TColburn MOBrien LLund RLaufer DATE 04/18/05 04/19/05 04/27/05 04/28/05 LIST OF ATTENDEES CATEGORY 1 WORKING-LEVEL MEETING WITH AMERGEN ENERGY COMPANY, LLC KINETIC EXPANSION INSPECTION AND ACCEPTANCE CRITERIA FOR THREE MILE ISLAND NUCLEAR STATION, UNIT 1, STEAM GENERATOR TUBES FEBRUARY 16-17, 2005 NAME ORGANIZATION

1. T. Colburn NRC/NRR/DLPM/PDI-1
2. E. Murphy NRC/NRR/EMCB
3. K. Karwoski NRC/NRR/EMCB
4. C. Khan NRC/NRR/EMCB
5. L. Lund NRC/NRR/EMCB
6. R. Laufer NRC/NRR/DLPM/PDI-1
7. C. Liang NRC/NRR/DSSA/SRXB
8. R. Lorson NRC/DRS/RGN-1
9. C. Smith EXELON/AMERGEN/TMI-1
10. S. Leshnoff EXELON/ENGINEERING
11. R. Freeman EXELON/AMERGEN/ENGINEERING
12. D. Helker EXELON/LICENSING
13. G. Navratil EXELON/AMERGEN/NDE SERVICES
14. D. Distel EXELON/LICENSING Enclosure 1

MEETING SLIDES Enclosure 2

Three Mile Island Nuclear Station, Unit 1 cc:

Site Vice President - Three Mile Island Nuclear Director - Licensing and Regulatory Affairs Station, Unit 1 AmerGen Energy Company, LLC AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-E P. O. Box 480 Kennett Square, PA 19348 Middletown, PA 17057 Rich Janati, Chief Senior Vice President - Nuclear Services Division of Nuclear Safety AmerGen Energy Company, LLC Bureau of Radiation Protection 4300 Winfield Road Department of Environmental Protection Warrenville, IL 60555 Rachel Carson State Office Building P.O. Box 8469 Vice President - Operations, Mid-Atlantic Harrisburg, PA 17105-8469 AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-N Plant Manager - Three Mile Island Nuclear Kennett Square, PA 19348 Station, Unit 1 AmerGen Energy Company, LLC Vice President - Licensing and Regulatory Affairs P. O. Box 480 AmerGen Energy Company, LLC Middletown, PA 17057 4300 Winfield Road Warrenville, IL 60555 Regulatory Assurance Manager - Three Mile Island Nuclear Station, Unit 1 Regional Administrator AmerGen Energy Company, LLC Region I P.O. Box 480 U.S. Nuclear Regulatory Commission Middletown, PA 17057 475 Allendale Road King of Prussia, PA 19406 Arthur Burritt, Region I U.S. Nuclear Regulatory Commission Chairman 475 Allendale Road Board of County Commissioners King of Prussia, PA 19406 of Dauphin County Dauphin County Courthouse Michael A. Schoppman Harrisburg, PA 17120 Framatome ANP Suite 705 Chairman 1911 North Ft. Myer Drive Board of Supervisors Rosslyn, VA 22209 of Londonderry Township R.D. #1, Geyers Church Road Vice President, General Counsel and Secretary Middletown, PA 17057 AmerGen Energy Company, LLC 2301 Market Street, S23-1 Senior Resident Inspector (TMI-1) Philadelphia, PA 19101 U.S. Nuclear Regulatory Commission P.O. Box 219 Mr. Christopher M. Crane Middletown, PA 17057 President and Chief Executive Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555

Three Mile Island Nuclear Station, Unit 1 cc:

Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 Eric Epstein TMI Alert 4100 Hillsdale Road Harrisburg, PA 17112 Correspondence Control Desk AmerGen Energy Company, LLC P.O. Box 160 Kennett Square, PA 19348 Manager Licensing - Three Mile Island Nuclear Station, Unit 1 Exelon Generation Company, LLC 200 Exelon Way, KSA 3-E Kennett Square, PA 19348 Associate General Counsel AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555