April 13, 2005 Mr. Christopher M. Crane, President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - CORRECTION TO ISSUANCE OF AMENDMENTS (TAC NOS. MC3413 AND MC3414)
Dear Mr. Crane:
On March 15, 2005, the Nuclear Regulatory Commission (Commission) issued Amendment No.
224 to Facility Operating License No. DPR-29 and Amendment No. 219 to Facility Operating License No. DPR-30 for the Quad Cities Nuclear Power Station, Units 1 and 2, respectively.
The amendments revised the Technical Specifications (TSs) in response to your application dated June 10, 2004, as supplemented by letters dated July 19 and July 21, 2004, and January 21, 2005.
Based on discussions between your staff and the Commission staff on April 1, 2005, we are reissuing a corrected copy of TS page 3.3.6.1-5 to reflect previous changes made to this page per Amendment Nos. 219 and 213 issued on February 18, 2004. The TS page markup submitted on June 10, 2004, that was used for Amendment Nos. 224 and 219 did not have the previously approved changes made to the Main Steam Line Pressure-Low allowable value. The enclosed TS page 3.3.6.1-5 corrects this allowable value to be "> 791 psig" as previously reviewed and approved.
We regret any inconvenience this may have caused.
Sincerely,
/RA/
Lawrence Rossbach, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-254 and 50-265
Enclosure:
As stated cc w/encl: See next page
April 13, 2005 Mr. Christopher M. Crane, President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - CORRECTION TO ISSUANCE OF AMENDMENTS (TAC NOS. MC3413 AND MC3414)
Dear Mr. Crane:
On March 15, 2005, the Nuclear Regulatory Commission (Commission) issued Amendment No.
224 to Facility Operating License No. DPR-29 and Amendment No. 219 to Facility Operating License No. DPR-30 for the Quad Cities Nuclear Power Station, Units 1 and 2, respectively.
The amendments revised the Technical Specifications (TSs) in response to your application dated June 10, 2004, as supplemented by letters dated July 19 and July 21, 2004, and January 21, 2005.
Based on discussions between your staff and the Commission staff on April 1, 2005, we are reissuing a corrected copy of TS page 3.3.6.1-5 to reflect previous changes made to this page per Amendment Nos. 219 and 213 issued on February 18, 2004. The TS page markup submitted on June 10, 2004, that was used for Amendment Nos. 224 and 219 did not have the previously approved changes made to the Main Steam Line Pressure-Low allowable value. The enclosed TS page 3.3.6.1-5 corrects this allowable value to be "> 791 psig" as previously reviewed and approved.
We regret any inconvenience this may have caused.
Sincerely,
/RA/
Lawrence Rossbach, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-254 and 50-265
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION:
PUBLIC OGC, O15B18 PD3-2 r/f ACRS, T2E26 AMohseni GHill (4), T5C3 GSuh TBoyce, O-12H2 LRossbach MRing, RIII PCoates ADAMS Package: ML050970128 Correction Ltr: ML050970125 TS Page: ML0501050432 OFFICE PM:LPD3-2 PM:LPD3-2 LA:LPD3-2 SC:LPD3-2 NAME WMacon MBanerjee PCoates GSuh DATE 4/12/05 4/12/05 4/12/05 4/13/05 OFFICIAL RECORD COPY
Quad Cities Nuclear Power Station Units 1 and 2 cc:
Site Vice President - Quad Cities Nuclear Power Station Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Quad Cities Nuclear Power Station Plant Manager Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Regulatory Assurance Manager - Quad Cities Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Quad Cities Resident Inspectors Office U.S. Nuclear Regulatory Commission 22712 206th Avenue N.
Cordova, IL 61242 David C. Tubbs MidAmerican Energy Company One River Center Place 106 E. Second, P.O. Box 4350 Davenport, IA 52808-4350 Vice President - Law and Regulatory Affairs MidAmerican Energy Company One River Center Place 106 E. Second Street P.O. Box 4350 Davenport, IA 52808 Chairman Rock Island County Board of Supervisors 1504 3rd Avenue Rock Island County Office Bldg.
Rock Island, IL 61201 Regional Administrator U.S. NRC, Region III 801 Warrenville Road Lisle, IL 60532-4351 Illinois Emergency Management Agency Division of Disaster Assistance &
Preparedness 110 East Adams Street Springfield, IL 62701-1109 Document Control Desk - Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President - Nuclear Services Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President of Operations - Mid-West Boiling Water Reactor Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Director - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Associate General Counsel Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Dresden, Quad Cities and Clinton Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555