ML050910127

From kanterella
Jump to navigation Jump to search
IR 05000298-04-014, Final Significance Determination for Cooper Nuclear Station
ML050910127
Person / Time
Site: Cooper Entergy icon.png
Issue date: 03/31/2005
From: Howell A
NRC/RGN-IV/DRP
To: Edington R
Nebraska Public Power District (NPPD)
References
EA-04-131, FOIA/PA-2006-0007 IR-04-014
Download: ML050910127 (10)


See also: IR 05000298/2004014

Text

March 31, 2005

EA-04-131

Randall K. Edington, Vice

President-Nuclear and CNO

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

SUBJECT:

COOPER NUCLEAR STATION - NRC INSPECTION REPORT

05000298/2004014 - FINAL SIGNIFICANCE DETERMINATION FOR A

PRELIMINARY GREATER THAN GREEN FINDING

Dear Mr. Edington:

The purpose of this letter is to provide you the final results of our significance determination of

the preliminary Greater than Green finding identified in the subject inspection report dated

August 12, 2004. The finding involved the failure to restore the Cooper Nuclear Station

Division 2 service water gland seal water supply to a normal alignment following maintenance

on the discharge strainer. This error, which occurred on January 21, 2004, resulted in

Division 2 of the service water system and Emergency Diesel Generator 2 being inoperable for

21 days. The finding was documented in NRC Inspection Report 05000298/2004014.

In the cover letter of the subject report we informed Nebraska Public Power District (NPPD) of

the NRCs preliminary conclusion and provided NPPD an opportunity to request a regulatory

conference on this matter. On September 27, 2004, a regulatory conference was conducted at

the NRC Region IV office in Arlington, Texas. During this meeting NPPD described their

assessment of the findings, including a detailed discussion of a service water pump test that

determined the impact of running the pump without gland seal water. Additionally, NPPD stated

they agreed with the apparent violation related to this finding and described the corrective

actions taken for the underlying performance deficiency.

The NRC has considered the information developed during the inspection, the additional

information you provided in your letter dated August 9, 2004, the information you provided at

the Regulatory Conference, and the information you provided in your October 7, 2004, letter

following the conference. After evaluating this information, the NRC concluded that a more

realistic failure probability for the service water system should be used. This new probability

reflected the results of your testing, as well as the inherent capabilities of the system.

Additionally, the NRC reviewed information you provided regarding the change in large early

release frequency (LERF) that resulted from the performance deficiency. NRC Inspection

Manual Chapter 0609, Appendix H, defines LERF as The frequency of those accidents leading

Nebraska Public Power District

-2-

to a significant, unmitigated release from containment in a time frame prior to effective

evacuation of the close-in population such that there is a potential for early health effects.

NPPD provided information asserting that effective evacuation of the close-in population could

be achieved prior to a release of radioactivity during the dominant accident sequences. After

review of accident progression timing, the staff determined that the dominant sequences

affected by this finding were not LERF contributors.

On the basis of this information, the NRC has concluded that the inspection finding is of very

low safety significance (Green). The final significance determination is attached as an

enclosure to this letter. The NRC has also determined that a violation was associated with this

issue involving the failure of Clearance Order SWB-1-4324147 SW-STNR-B to provide

adequate instructions to restore the service water system to an operable configuration following

completion of maintenance activities on January 21, 2004. This violation is being treated as a

noncited violation, consistent with Section VI.A of the Enforcement Policy.

If you contest the violation or its significance, you should provide a response within 30 days of

the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the

Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611 Ryan Plaza

Drive, Suite 400, Arlington, Texas 76011-4005; the Director, Office of Enforcement, U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident

Inspector at the Cooper Nuclear Station facility.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter

and its enclosures will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ by AVegel for

Arthur T. Howell III, Director

Division of Reactor Projects

Docket: 50-298

License: DPR-46

cc:

Michael T. Boyce, Nuclear Asset Manager

Nebraska Public Power District

1414 15th Street

Columbus, NE 68601

Nebraska Public Power District

-3-

John C. McClure, Vice President

and General Counsel

Nebraska Public Power District

P.O. Box 499

Columbus, NE 68602-0499

P. V. Fleming, Licensing Manager

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

Michael J. Linder, Director

Nebraska Department of

Environmental Quality

P.O. Box 98922

Lincoln, NE 68509-8922

Chairman

Nemaha County Board of Commissioners

Nemaha County Courthouse

1824 N Street

Auburn, NE 68305

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Ronald A. Kucera, Deputy Director

for Public Policy

Department of Natural Resources

P.O. Box 176

Jefferson City, MO 65101

Director

State Emergency Management Agency

P.O. Box 116

Jefferson City, MO 65102-0116

Nebraska Public Power District

-4-

Chief, Radiation and Asbestos

Control Section

Kansas Department of Health

and Environment

Bureau of Air and Radiation

1000 SW Jackson, Suite 310

Topeka, KS 66612-1366

Daniel K. McGhee

Bureau of Radiological Health

Iowa Department of Public Health

401 SW 7th Street, Suite D

Des Moines, IA 50309

William J. Fehrman, President

and Chief Executive Officer

Nebraska Public Power District

1414 15th Street

Columbus, NE 68601

Jerry C. Roberts, Director of

Nuclear Safety Assurance

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

Chief Technological Services Branch

National Preparedness Division

Department of Homeland Security

Emergency Preparedness & Response Directorate

FEMA Region VII

2323 Grand Boulevard, Suite 900

Kansas City, MO 64108-2670

Nebraska Public Power District

-5-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (KSW)

Senior Resident Inspector (SCS)

Branch Chief, DRP/C (MCH2)

Senior Project Engineer, DRP/C (WCW)

Team Leader, DRP/TSS (RLN1)

RITS Coordinator (KEG)

RidsNrrDipmIipb

DRS STA (DAP)

J. Dixon-Herrity, OEDO RIV Coordinator (JLD)

CNS Site Secretary (SLN)

W. A. Maier, RSLO (WAM)

G. F. Sanborn, D:ACES (GFS)

K. S. Fuller, RC (KSF)

F. J. Congel, OE (FJC)

OE:EA File (RidsOeMailCenter)

SISP Review Completed: __mch____

ADAMS: / Yes

G No Initials: _mch__

/ Publicly Available G Non-Publicly Available G Sensitive

/ Non-Sensitive

R:\\_CNS\\2004\\CN2004-14RP Final Determination.wpd

RIV:C:DRP/C

SRA:DRS

D:ACES

D:DRP

MCHay;df

DPLoveless

GFSanborn

ATHowell III

/RA/

/RA/

/RA/

AVegel for

3/15/05

3/22/05

3/21/05

3/31/05

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

Enclosure

Final Significance Determination

Cooper Nuclear Station

Service Water Gland Seal Water Configuration Deficiency

The NRC reviewed the information provided by the licensee in their analysis, PSA-ES63,

Revision 0, "Temporary Alignment of Service Water Division I Gland Water Supply to SW

Pumps in Both Divisions," dated August 9, 2004, plus additional information provided in a letter

dated August 9, 2004, and presented during the Regulatory Conference held on September 27,

2004. Using the additional data provided by the licensee, as well as evaluations and input from

the NRC staff, a final significance determination was performed by modifying the preliminary

evaluation, as appropriate. The documentation that follows is not a stand-alone evaluation.

The reader must also be familiar with the preliminary significance determination documented in

NRC Special Inspection Report 05000298/2004014, Section 1R04.b(3), "Analysis."

I.

Internal Events:

The NRC reviewed the testing data and other pertinent information provided by the

licensee. The following characterizes each of the changes made to the assumptions in

the NRCs preliminary significance determination:

a.

The service water pumps at Cooper will fail to run 50 percent of the time if gland

water is lost for 30 minutes or more. If gland water is recovered within

30 minutes of loss, the pumps will continue to run for their mission time, given

their nominal failure rates.

The NRC determined that the test conducted by NPPD on a representative pump

indicated that service water pumps, when run without gland water, would not

always fail as originally assumed. However, uncertainties in the data and

differences identified between the test configuration and the actual plant

indicated that a significant potential remained that a pump would fail if gland

water were lost for greater than 30 minutes. Therefore, a bounding value of

50 percent was used.

b.

Vital battery depletion is best represented as occurring at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> following a

station blackout rather than at 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> as modeled in the Standardized Plant

Analysis Risk (SPAR) Model for Cooper. This assumption was based on

resident inspector review of the licensees calculation provided following the

regulatory conference.

c.

The probability of operators failing to properly diagnose the need to restore

Division II service water gland water to the running pump upon a loss of

Division I service water is 0.4. The NRC calculated this value in the preliminary

significance determination. However, the value was applied to both pumps in the

preliminary significance determination. The NRC applied this value only to the

operating pump in the final significance determination because there would have

been additional time to recover gland water for the standby pump.

-2-

1Odds ratio is a method of accounting for the number of successes as well as failures

when calculating a condition human error probability. This method of accounting for

uncertainties associated with individual performance shaping factors is described in draft

NUREG-CR-XXXXX (INEEL/EXT-02-10309), SPAR-H METHOD, and tends to provide a less

conservative result.

d.

The probability of operators failing to properly diagnose the need to restore

Division II service water gland water to the standby pump upon failure of the

running pump is 0.05. This results in a conditional probability of recovering gland

water to the standby pump, given a failure to recover gland water to the running

pump, of 0.125.

For this calculation, the NRC used the same performance shaping factors used

in the case of the running pump with the following exceptions: the available time

was changed from barely adequate to extra time (0.1) because the time to

perform this action was now greater than 60 minutes, and Odds ratio1 was

applied to better quantify the multiple performance shaping factors.

e.

The conditional probability that Division II service water fails to survive upon

demand given that Division I fails is 2.65 x 10-2.

The NRC developed an event tree to better model the failure of the service water

system without gland water available. This model indicated that, upon a failure

of the running pump, the availability and reliability of the standby pump should be

evaluated. Additionally, the degradation of the test pump observed during the

licensees testing was assumed to reduce the capability of the pumps to fulfill

their mission after running without gland water for any period longer than

30 minutes. The event tree also included a small probability that the pumps

would continue to run for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without any gland seal water as indicated by

the licensees testing. The NRC then quantified this event tree to obtain the

probability.

The NRC used Assumption b to adjust the baseline SPAR model. The resulting

baseline core damage frequency, CDFbase, was 5.05 x 10-9/hr.

The NRC changed the modified SPAR model discussed in the preliminary significance

determination to account for all changes in assumption discussed above. The NRC

changed the recovery action value from the preliminary determination to the conditional

probability that Division II service water fails to survive upon demand given that

Division I fails provided in Assumption e. The modified SPAR model was requantified

with the resulting current case conditional core damage frequency, CDFcase, of 6.26 x

10-9/hr.

The change in core damage frequency (CDF) from the revised models was calculated

as follows:

CDF = CDFcase - CDFbase = 6.26 x 10-9 - 5.05 x 10-9 = 1.21 x 10-9/hr.

-3-

Therefore, the total change in core damage frequency over the exposure time that was

related to this finding was calculated as:

CDF = 1.21 x 10-9/hr * 24 hr/day * 21 days = 6.10 x 10-7 for 21 days

The final risk significance of this finding is presented in the following table. The

dominant cutsets from the internal risk model were essentially the same as provided in

the preliminary significance determination.

Table I

Final Significance Determination

Evaluation Model Results

Model

Result

Core Damage

Frequency

SPAR 3.03, Revised

(and modified for

final determination)

Baseline: Internal Risk

5.1 x 10-9/hr

Internal Events Risk

6.3 x 10-9/hr

TOTAL Internal Risk (CDF)

6.1 x 10-7

TOTAL External Risk (CDF)

2.3 x 10-7

TOTAL Internal and External Change (CDF)

8.4 x 10-7

II.

External Initiators:

The NRC made no changes to the models, techniques, and assumptions used in

evaluating the external initiators contribution to the CDF from those presented in the

preliminary significance determination. However, the NRC used the changes in

assumption to the internal events evaluation and the revised SPAR model to requantify

the core damage frequency related to internal fires. Internal fire was the only external

initiator determined to affect the CDF in the preliminary significance determination.

The revised values are presented in Table II.

-4-

Table II

Final Significance Determination

External Initiators (Internal Fire) Results

Fire Areas:

Fire Type

CDF

Switchgear 1F

Shorts Bus

4.65 x 10-10/hr

Service Water Pump Room

One Pump

1.45 x 10-15/hr

Both Pumps

1.04 x 10-14/hr

CDF for All Fires Affecting the Service Water System:

4.65 x 10-10/hr

Exposure Time (21 days):

5.04 x 102 hrs

Total External Events CDF over the Exposure Period:

2.34 x 10-7

III.

Large Early Release Frequency (LERF):

The NRC reevaluated the portions of the preliminary significance determination related

to the change in LERF. In the regulatory conference, the licensee stated that the

dominant sequences were not contributors to the LERF. Therefore, there was no

change in LERF resulting from the subject performance deficiency. The licensee

indicated that the postulated core damage sequence took more time than the average to

progress to core damage. This provided additional time to core damage and the

relatively short time estimated to evacuate the close-in population surrounding Cooper

Nuclear Station.

LERF is defined in NRC Inspection Manual Chapter 0609, Appendix H, "Containment

Integrity Significance Determination Process" as: "the frequency of those accidents

leading to significant, unmitigated release from containment in a time frame prior to the

effective evacuation of the close-in population such that there is a potential for early

health effect." The NRC noted that the dominant core damage sequences documented

in the preliminary significance determination were long sequences that took greater than

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to proceed to reactor pressure vessel breach. The shortest calculated interval

from the time reactor conditions would have met the requirements for entry into a

general emergency (requiring the evacuation) until the time of postulated containment

rupture was 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The licensee stated that the average evacuation time for Cooper

from the declaration of a General Emergency was 62 minutes.

The NRC determined that, based on a 62-minute average evacuation time, effective

evacuation of the close-in population could be achieved within 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. Therefore, the

dominant core damage sequences affected by the subject performance deficiency were

not LERF contributors. As such, the NRCs best estimate determination of the change

in LERF resulting from the performance deficiency was zero.

-5-

IV.

Conclusion:

Based on reanalysis of the preliminary significance determination, the NRC concluded

that the subject inspection finding was of very low safety significance (Green). This

result was based on a more realistic failure probability for the service water system

derived using the results of the licensees testing program, as well as the inherent

capabilities of the system. The total change in CDF, after adjusting for this revised

system failure probability, was estimated to be 8.4 x 10-7. Additionally, the NRC

determined that there was no change in LERF because, during the dominant accident

sequences, effective evacuation of the close-in population could be achieved prior to the

release.