Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss the Licensee'S Amendment Request Dated May 5, 2004 for Davis-Besse Unit 1
ML050870572
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/07/2005
From: Hopkins J
NRC/NRR/DLPM/LPD3
To:
FirstEnergy Nuclear Operating Co
Hopkins J, DLPM/NRR, 415-3027
References
TAC MC3084
Download: ML050870572 (5)


Text

April 7, 2005 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF OCTOBER 12, 2004, MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY TO DISCUSS THE LICENSEES MAY 5, 2004, AMENDMENT REQUEST (TAC NO. MC3084)

On October 12, 2004, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of FirstEnergy Nuclear Operating Company (the licensee), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, MD. The purpose of the meeting was to discuss the licensees amendment request dated May 5, 2004, regarding the Safety Features Actuation System Instrumentation Setpoints. A list of attendees is provided as Attachment 1.

The licensee discussed the difference between their old and new relays which necessitated the setpoint change request. The old relays were electro-mechanical devices from General Electric whereas the new relays are solid-state devices from Asea Brown Boveri. The licensee stated that there is little vendor data for the old relays unlike the new relays. The licensee and NRC staff discussed the loss-of-voltage and degraded voltage values for the relays.

In reviewing the differences between the old and new relays, the NRC staff inquired on the effect of the new relay settings on plant equipment. Specifically, the staff requested the licensee provide additional information regarding locked rotor situations. The licensee stated that they would provide the requested information.

Members of the public were not in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to Jon B. Hopkins at 301-415-3027, or JBH1@nrc.gov.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Attachment:

As stated cc w/att: See next page

April 7, 2005 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF OCTOBER 12, 2004, MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY TO DISCUSS THE LICENSEES MAY 5, 2004, AMENDMENT REQUEST (TAC NO. MC3084)

On October 12, 2004, a category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of FirstEnergy Nuclear Operating Company (the licensee), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, MD. The purpose of the meeting was to discuss the licensees amendment request dated May 5, 2004, regarding the Safety Features Actuation System Instrumentation Setpoints. A list of attendees is provided as Attachment 1.

The licensee discussed the difference between their old and new relays which necessitated the setpoint change request. The old relays were electro-mechanical devices from General Electric whereas the new relays are solid-state devices from Asea Brown Boveri. The licensee stated that there is little vendor data for the old relays unlike the new relays. The licensee and NRC staff discussed the loss-of-voltage and degraded voltage values for the relays.

In reviewing the differences between the old and new relays, the NRC staff inquired on the effect of the new relay settings on plant equipment. Specifically, the staff requested the licensee provide additional information regarding locked rotor situations. The licensee stated that they would provide the requested information.

Members of the public were not in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to Jon B. Hopkins at 301-415-3027, or JBH1@nrc.gov.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Attachment:

As stated cc w/att: See next page DISTRIBUTION:

PUBLIC AMohseni DClarke CLipa, RIII RSmith TMensah PDIII-2 Reading GSuh OGC HGarg AGarmoe EDO, RGNIII TMarsh/JLyons JHopkins ACRS/ACNW NPatel GRoach GMorris Package No.: ML052020361 Notice: ML042740124 ADAMS Accession Number: ML050870572 OFFICE PDIII-2/PM PDIII-2/LA PDIII-2/SC NAME JHopkins DClarke GSuh DATE 4/7/05 4/6/05 4/7/05 OFFICIAL RECORD COPY

ATTENDANCE LIST NRC MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY OCTOBER 12, 2004 NRC FENOC J. Hopkins M. Hess H. Garg P. Jacobsen N. Patel C. Rupp G. Morris H. Hegrat R. Smith A. Garmoe G. Roach ATTACHMENT

Davis-Besse Nuclear Power Station, Unit 1 cc:

Mary E. O'Reilly Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-2206 Manager - Regulatory Affairs Zack A. Clayton FirstEnergy Nuclear Operating Company DERR Davis-Besse Nuclear Power Station Ohio Environmental Protection Agency 5501 North State - Route 2 P.O. Box 1049 Oak Harbor, OH 43449-9760 Columbus, OH 43266-0149 Director, Ohio Department of Commerce State of Ohio Division of Industrial Compliance Public Utilities Commission Bureau of Operations & Maintenance 180 East Broad Street 6606 Tussing Road Columbus, OH 43266-0573 P.O. Box 4009 Reynoldsburg, OH 43068-9009 Attorney General Office of Attorney General Regional Administrator 30 East Broad Street U.S. Nuclear Regulatory Commission Columbus, OH 43216 801 Warrenville Road Lisle, IL 60523-4351 President, Board of County Commissioners of Ottawa County Michael A. Schoppman Port Clinton, OH 43252 Framatome ANP 24 Calabash Court President, Board of County Rockville, MD 20850 Commissioners of Lucas County One Government Center, Suite 800 Resident Inspector Toledo, OH 43604-6506 U.S. Nuclear Regulatory Commission 5503 North State Route 2 David Lochbaum, Nuclear Safety Engineer Oak Harbor, OH 43449-9760 Union of Concerned Scientists 1707 H Street NW, Suite 600 Barry Allen, Plant Manager Washington, DC 20006 FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station The Honorable Dennis J. Kucinich 5501 North State - Route 2 United States House of Representatives Oak Harbor, OH 43449-9760 Washington, D.C. 20515 Dennis Clum The Honorable Dennis J. Kucinich Radiological Assistance Section Supervisor United States House of Representatives Bureau of Radiation Protection 14400 Detroit Avenue Ohio Department of Health Lakewood, OH 44107 P.O. Box 118 Columbus, OH 43266-0118 Davis-Besse Nuclear Power Station, Unit 1

cc:

Mr. James P. Riccio Nuclear Policy Analyst Greenpeace 702 H. Street, NW, Suite 300 Washington, DC 20001 Paul Gunter Director Nuclear Watchdog Project Nuclear Information & Resource Service 1424 16th Street NW Suite 401 Washington, DC 20009 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760 Mr. Mark B. Bezilla Vice President-Nuclear, Davis-Besse Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760