ILTMC Research Reactor Research Park University of Missouri-Columbia Columbia, MO 65211 PtioNE (S73) 882-4211 FAX (573) 882-6360 March 15, 2005 Mr. Alexander Adams, Jr.
U.S. Nuclear Regulatory Commission Mail Stop 012-G13 Washington, DC 20555-0001
REFERENCE:
SUBJECT:
Docket No. 50-186 University of Missouri-Columbia Research Reactor Amended Facility License R-103 MURR Operations Monthly Summary
Dear Mr. Adams:
Enclosed is a copy of MURR's Monthly Operations Summary for February 2005. If you have any questions, please contact me at (573) 882-5276.
Sincerely, Leslie P. Foyto Reactor Manager LPF/djr Enclosure AN tQuAL onvoRmu~rry/ADA InSTruI1o.-
UNIVERSITY OF MISSOURI RESEARCH REACTOR
--..- OPE-RA-T-INS-MON-THLY SUMMLAR-Y February 2005 S -
Prepared by:
Operations Staff I
'INTRODUCTION The reactor operated conitinuously in February with the following exceptions: 4 shutdowns for scheduled maintenance and refueling; 1 unscheduled shutdown.
MAINTENANCE ACTIVITIES 2/7/05 Refueled - removed core 05-05, loaded core 05-06.
2/8/05
-Refueled - removed core 05-,06, loaded core 05-07.'
2/14/05 Refueled - removed core 05-07, loaded core 05-08.
2/21/05 Refueled-removed core 05-08, loaded core 05-09.
Completed Modification Record 80-5 Addendum 1 (Removal of Bulk Pool Lead Shield Facility)..
Replaced Pneumatic Tube System photo sensor collar for row 2 irradiation position as part of Modification Record 05-1 (Pneumatic Tube System Photo Sensor Collar Upgrade).
Completed Modification Record 04-5 Addendum 2 (Install Independent -13.8-kV Feeder'Lines to Cooling Tower and Laborator~' Building Transformers).
'Completed Modification Record 04-5 Addendum 3 (Replacement of 500-kVA Cooling Tower Transformer with a 1500-kVA Transformer).
e2/2805 Fcoi 05-10. -
Loaded new.pool de-ionization bed 'P'.
Completed Modification Record 05-1 (Pneumatic Tube System Photo Sensor Collar Upgrade) by replacing Pneumatic Tube System photo sensor collar for row 1 irradiation position.
Reinstalled refurbished Secondary Coolant System Flow Distribution Valve S-17.
IV UNS CHEDULED SHUTDOWNS Date No.
- Yp-Cause 2/8/05 1176
'Rod Run-In Blade 'D' Not In Contact With Magnet On February 8, a "Rod Not In Contact With Magnet Rod Run-In" was automatically initiated when control blade "ID" anvil separated from its'ma-ne~t during a routine outward shimming evolution. The reactor was shutdown and th'epull rod to housing alignment wa's checked and verified, and the anvil and magnet were cleaned The control rod was satisfactorily withdrawn to
.--- the-full out position-as part-of the retest -The reactor was refueled and subsequently returned to 10 MW operation.
OPERATION
SUMMARY
FOR MONTH OF University of Missour Research Reactor Center (MURR)
HOURS OPERATED THIS PERIOD.>.
TOTAL HOURS OPERATED, REACTOR HOURS OPERATED AT FULL POWER, THIS PERIOD TOTAL HOURS AT FULL POWER, REACTOR.
INTEGRATED POWER THIS PERIOD TOTAL INTEGRATED POWER. REACTOR Feb-05 606.49 264,496.88
.604.64 261,148.12 252.04 MWD 103,013.19 MWD
- -- 77",
I r
~~Submitted by: -
3 MWD Custodian/Reactor Physicist-Date:
3(1jOF I