s.. 11 ppa *&o TM Robert A. Saccone Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem /Boulevard Berwick, PA 18603 Tel. 570.542.3959 Fax 570.542.1504 RASaccone@pplweb.com March 11, 2005 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-PI-17 Washington, D.C. 20555-0001 SUSQUEHANNA STEAM ELECTRIC STATION MONTHLY OPERATING REPORTS Docket Nos. 50-387/NPF-14 and 50-388/NPF-22 PLA-005874 The February 2005 Monthly Operating Reports for Susquehanna SES Units I and 2 are attached;.
., I Very truly yours, Robet;accn~
JJH/cmm cc: NRC Region I NRC Sr. Resident Inspector, Mr. A. Blarney NRC Project Manager, Mr. R V. Guzman 12g-q
OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-387 One 03/11/2005 J. J. Hennings (570) 542-3747 OPERATING STATUS
- 1. Unit Name:
Susauehanna Steam Ele
- 2.
Reporting Period:
February 2005
- 3.
Design Electrical Rating (Net MWe):
1177
- 4.
Maximum Dependable Capacity (Net MWe):
ctric Station (UI) 1135
- 5.
Hours in Reporting Period
- 6.
Number of Hours Reactor Was Critical
- 7.
Hours Generator On-Line
- 8.
Unit Reserve Shutdown Hours
- 9.
Net Electrical Energy Generated (MWH)
This Month 672 672 672 0
768,728 Yr.-to-Date 1416.0 1416.0 1416.0 0
1,637,902 Cumulative 190,489.0 159,404.0 157,016.0 0
162,278,344 NOTES:
Page I of I
UNIT SHUTDOWNS DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-387 One 03/11/2005 J. J. Hennings (570) 542-3747 REPORT MONTH February 2005 No.
Date Type Duration Reason Method of Cause & Corrective Action (Hours) 2 Shutting To Prevent Recurrence Down
_Reactor 3
No Reactor shutdowns this month Summary: On 3/19/05 a power reduction was taken to perform a planned control rod sequence exchange at 70 to 75%
power. Maintenance was also performed on a Reactor Feed Pump Turbine during that period. 100% power was achieved on 3/22/05.
1.
F. Forced S. Scheduled 2.
Reason:
A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction 3.
Method:
1 - Manual 2 -Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain)
Page 1 of I
SUSQUEHANNA STEAM ELECTRIC STATION Docket Number:
50-387 Completed by: J. J. Hennings Challenges to Main Steam Safetv Relief Valves None.
Date:
03/11/05 Telephone:
(570) 542.3747
OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 03111/05 J. J. Hennings (570) 542-3747 OPERATING STATUS
- 5.
Unit Name:
Susquehanna Steam Electric Station (U2)
- 6.
Reporting Period:
February 2005
- 7. Design Electrical Rating (Net MWe):
1182
- 8. Maximum Dependable Capacity (Net MNVe):
1140
- 5.
Hours in Reporting Period
- 6.
Number of Hours Reactor Was Critical
- 7.
Hours Generator On-Line
- 8.
Unit Reserve Shutdown Hours
- 9.
Net Electrical Energy Generated (MWH)
NOTES:
This Month' 672 604.48 600.03 0
617,193 Yr.-to-Date 1,416 1,348.5 1344.0 0
1,475,438 Cumulative 175,729 154,028.2 152,036.7 0
160,290,578 Page 1 of 1
UNIT SHUTDOWNS DOCKET NO.' -
UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 03/11/05 J. J. Hennings (570) 542-3747 REPORT MONTH February 2005 No.
Date Type Duration Reason Method of Cause & Corrective Action (Hours) 2 Shutting to Prevent Recurrence Down Reactor
/3 2126/05 5
71.97 C
1 Scheduled shut down for Refueling Outage. Following the manual turbine trip, the method of shutting down was by normal control rod insertion ("soft" shut down) with no scram required.
Summary: All power changes this month were planned power reductions. The End of Cycle Coastdown continued from January until Reactor Shutdown on 2/26/05. The method of shutting down the reactor was by normal control rod Insertion ("soft' shutdown) with no scram required.
1.
2.
3.
F. Forced S. Scheduled Reason:
A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction Method:
1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain)
Page 1 of 1
SUSQUEHIANNA STEAM ELECTRIC STATION Docket Number:
50-388 Date:
03/11/05 Completed by: J. J. Hennings Telephone:
(570) 542-3747 Challenges to Main Steam Safetv Relief Valves None.