March 18, 2005 Mr. Jeff Forbes Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
REVISION OF SCHEDULE FOR THE REVIEW OF THE ARKANSAS NUCLEAR ONE, UNIT 2, LICENSE RENEWAL APPLICATION
Dear Mr. Forbes:
Enclosed is a revised schedule for the review of the Arkansas Nuclear One, Unit 2, license renewal application. This schedule has been revised to reflect a change in the meeting date for the Advisory Committee on Reactor Safeguards (ACRS) Full Committee. The revised schedule includes the dates for issuance of the final supplemental environmental impact statement and the final safety evaluation report. If you have any questions on the revised review schedule, please contact me at 301-415-1124 or e-mail gxs@nrc.gov.
Sincerely,
/RA/
Gregory F. Suber, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-368
Enclosure:
As stated cc w/encl: See next page
March 18, 2005 Mr. Jeff Forbes Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE ARKANSAS NUCLEAR ONE, UNIT 2, LICENSE RENEWAL APPLICATION
Dear Mr. Forbes:
Enclosed is a revised schedule for the review of the Arkansas Nuclear One, Unit 2, license renewal application. This schedule has been revised to reflect a change in the meeting date for the Advisory Committee on Reactor Safeguards (ACRS) Full Committee. The revised schedule includes the dates for issuance of the final supplemental environmental impact statement and the final safety evaluation report. If you have any questions on the revised review schedule, please contact me at 301-415-1124 or e-mail gxs@nrc.gov.
Sincerely,
/RA/
Gregory F. Suber, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-368
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page Adams Accession No: ML050770393 Document Name: E:\\Filenet\\ML050770393.wpd OFFICE LA:RLEP PM:RLEP PM:RLEP SC:RLEP NAME MJenkins T. Kenyon ( w/comments)
A. Williamson for G. Suber S. Lee DATE 03/15/05 03/18/05 03/15/05 03/18/05 OFFICIAL RECORD COPY
Enclosure Arkansas Nuclear One, Unit 2 License Renewal Application Review Schedule Revision 2 Milestone Schedule Actual Receive license renewal application 10/15/03 10/15/03 Federal Register Notice (FRN) published for receipt and availability 10/24/03 10/24/03 FRN published for acceptance/rejection/opportunity for hearing 11/24/03 11/24/03 FRN published for intent/environmental scoping meeting 12/22/03 12/2203 Deadline for filing hearing requests and petitions for intervention 12/24/03 12/24/03 Scoping and screening methodology audit completed 01/20/04 01/23/04 Environmental scoping meeting 02/03/04 02/03/04 Environmental scoping period ends 02/20/04 02/20/04 Aging Management Review audit completed 03/24/04 03/24/04 Environmental requests for additional information (RAIs) issued 03/26/04 02/24/04 Environmental RAIs responses received 05/14/04 07/15/04 Draft supplemental environmental impact statement (SEIS) issued 09/03/04 08/30/04 FRN published for availability/comment on draft SEIS 09/03/04 08/30/04 Public meeting to discuss draft SEIS 10/21/04 10/21/04 Safety evaluation report (SER) with open items issued 11/0/04 11/05/04 End of draft SEIS comment period 11/17/04 11/24/04 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 12/04 12/01/04 meeting on Draft SER Draft SER responses received 12/17/04 12/13/04 Final SEIS issued 04/22/05 FRN published for availability of final SEIS 04/22/05 SER issued 04/08/05 ACRS Full Committee meeting on SER 05/05/05 ACRS letter issued 05/05 Staff Recommendation to Director, NRR 07/05/05 Decision - Director, NRR (license issued, if approved) 07/12/05
DISTRIBUTION: Ltr. to J. Forbes, Re: ANO-2, Dated: March 18, 2005 Adams Accession No.: ML050770393 HARD COPY RLEP RF Project Manager E-MAIL:
PUBLIC J. Craig D. Matthews F. Gillespie C. Grimes RidsNrrDe E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair S. Black B. Boger D. Thatcher R. Pettis G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff J. Minns R. Gramm A. Howell T. Alexion Linda Smith RIV
Arkansas Nuclear One, Unit 2 cc:
Executive Vice President
& Chief Operating Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Director, Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Mr. Mike Schoppman Framatome ANP, Richland, Inc.
Suite 705 1911 North Fort Myer Drive Rosslyn, VA 22209 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 72801 Vice President, Operations Support Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 Garry Young 1448 SR 333 Russellville, AR 72802 Mr. Fred Emerson Nuclear Energy Institute 1776 I St., N.W., Suite 400 Washington, DC 20006-3708