February 23, 2005 Southern Nuclear Operating Company, Inc.
ATTN: Mr. H. L. Sumner Vice President - Hatch Project P. O. Box 1295 Birmingham, AL 35201-1295
SUBJECT:
NRC OFFICE OF INVESTIGATIONS REPORT NO. 2-2004-038 (EDWIN I.
HATCH NUCLEAR PLANT)
Dear Mr. Sumner:
Enclosed for your information is the synopsis of a Nuclear Regulatory Commission (NRC)
Office of Investigations (OI) completed report. The investigation was conducted to review the circumstances surrounding a willful failure to report an arrest by a licensed reactor operator.
As documented in OI Report No. 2-2004-038, OI did not substantiate that the licensed reactor operator deliberately withheld information relating to a 1995 arrest. The NRC staff has reviewed the OI synopsis and conclusions and agrees that the issue was not substantiated.
However, based on our review of the OI synopsis, we will perform a followup inspection regarding the emergency support managers failure to make proper notifications to Southern Nuclear Operating Company Corporate Security personnel and to the NRC. Should you have any questions concerning this letter, please contact me at (404)562-4550.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by Curtis Rapp Acting For/
Malcolm T. Widmann, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DPR-57, NPF-5
Enclosure:
Investigative Synopsis, OI Report 2-2004-038
SNC 2
Distribution w/encl:
D. White, RII C. Evans, RII EICS L. Slack, RII EICS OFFICE RII/DRP RII/EICS SIGNATURE VMM for SES for NAME LWert CEvans DATE 2/22/2005 2/18/2005 E-MAIL COPY?
YES YES NO YES NO YES NO YES NO YES NO YES NO PUBLIC DOCUMENT YES YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: E:\\Filenet\\ML050700268.wpd
NOT FOR PUBLIC DISCLOSURE WITHOUT APPROVAL OF FIELD OFFICE DIRECTOR, OFFICE OF INVESTIGATIONS, REGION II Case No. 2-2004-038 1
SYNOPSIS The investigation was initiated by the U.S. Nuclear Regulatory Commission Office of Investigations, Region II, on July 2, 2004, to determine if a reactor operator (RO) at the Georgia Power Companys (GPC) Hatch Nuclear Power Plant (Hatch), deliberately withheld information relating to a 1995 arrest and/or if the licensee had this information and failed to report it to the NRC.
Based on the evidence developed during this investigation, the allegation that a RO deliberately withheld information relating to a 1995 arrest was not substantiated. However, the investigation did substantiate that an emergency support manager (ESM) received the arrest information and failed to make proper notification to the licensee and NRC.