Maria Korsnick 1503 Lake Road Vice President Ontario, New York 14519-9364 585.771.3494 585.771.3943 Fax maria.korsnick@ constellation.com Constellation Energy R.E. Ginna Nuclear Power Plant February 25, 2005 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Mail Stop P1-137 Washington, DC 20555

Subject:

Fitness for Duty Program Performance Data Report R.E. Ginna Nuclear Power Plant Docket No. 50-244 Gentlemen:

In accordance with the requirements set forth in 10 CFR 26.72(d), R.E. Ginna Nuclear Power Plant, LLC has compiled and is submitting the enclosed semi-annual Fitness for Duty (FFD) Program Performance Data Report covering the period July 1, 2004, through December 31, 2004.

Very truly yours, Mary G. Korsnick Anal

/ 6 6

Fitness for Duty Program Performance Data Personnel Subject to 10 CFR Part 26

-CONSTELLATION ENERGY GROUP - .12/31/2004'

.Company.. -- 6 Months Ending

- R.E. Ginna Nuclear .Power Plant Tammy L. Hufferi Fitness for Duty Administrator '(585) 771-5285

-. Contact Name Phone)

CUTOFFS: Screen/Confirmation (nglml) [X1 Appendix A to 10 CFR Part 26 Marijuana 50/15 Amphetamines Cocaine Phencyclidine Opiates Alcohol (% BAC)

Annual (Jan-Dec) Random testing rates: Employees & Contractors by 50%.

Long-term Short-term Testing Results Licensee Employees Contractor Personnel Contractor Personnel Average Numberwith 429 127 1 51 Unescorted Access Categories Tested Positive Tested Positive Tested Positive Pre-Access 5 0 19 0 70 2 For Cause Post-accident 0 0 0 0 0 0 Observed Behavior 0 0 0 0 0 0 Random 103 0 46 0 26 0 Follow-up 13 0 13 0 0 0 Other* 5 0 0 0 2 0 TOTAL

.- AL 126

.78..... _, 0 :78 ,.- ,. . ... , - ....... 98 -- .. . *...,..- 2 .. .. i Others:

Licensee: All pre-employment Short-Term Contractor: 2 For Cause Tests on visitors for possession of alcohol discovered in their vehicle during a security search prior to entering the protected area.

BREAKDOWN OF CONFIRMED POSITIVE TESTS FOR SPECIFIC SUBSTANCES Marijuana Cocaine Opiates Amphe- Phency- Alcohol Refusal Total tamines. . lidinetoes to test Licensee Employees 0 0 0 0 0 0 0 0 Long-Term Contractors 0 0 0 0 0 0 0 0 Short-Term Contractors 1 1 0 0 0 0 0 2 TOTAL . 1 - 00 0 0 0: - 2 Short-Term Contractors: Both individual's unescorted access was denied.

NRC Reportable Events (Per IOCFR Part 26.73)

There were no reportable events during this performance data period.