Inspection / Activity Plan, 03/01/2005 - 09/30/2006
ML050610749
Person / Time
Site: Farley, 07200042  Southern Nuclear icon.png
Issue date: 03/03/2005
From:
NRC/RGN-II/DRP/RPB2
To:
Southern Nuclear Operating Co
Shared Package
ML050610747 List:
References
IR-05-001
Download: ML050610749 (3)


Text

Page 1 of 3 Farley 03/03/2005 09:31:32 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB2-TFP - TRIENNIAL FIRE PROTECTION PRE-INSP VISIT 4 1, 2 IP 7111105T Fire Protection 03/01/2005 03/03/2005 Baseline Inspections EB2-TFP - TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP 7111105T Fire Protection 03/21/2005 03/25/2005 Baseline Inspections 1, 2 IP 7111105T Fire Protection 04/04/2005 04/08/2005 Baseline Inspections ISFSI - ISFSI DRY RUN INSPECTION 4 1, 2 IP 60854 Preoperational Testing Of An ISFSI 05/12/2005 05/31/2005 Other Routine PS1-RP - RADIATION PROTECTION PRE-INSP VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 06/06/2005 06/10/2005 Baseline Inspections PB2-FP - FLOOD PROTECTION 1 1, 2 IP 7111106 Flood Protection Measures 06/27/2005 06/30/2005 Baseline Inspections PS1-RP - RP PUBLIC BASELINE 4 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 06/27/2005 07/01/2005 Baseline Inspections 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 06/27/2005 07/01/2005 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program 06/27/2005 07/01/2005 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 06/27/2005 07/01/2005 Baseline Inspections EB1-MODS - MODIFICATIONS/10CFR50.59 3 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 07/11/2005 07/15/2005 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 07/11/2005 07/15/2005 Baseline Inspections PB2-PI&R - PI&R PREINSPECTION VISIT 1 1, 2 IP 71152B Identification and Resolution of Problems 07/18/2005 07/22/2005 Baseline Inspections PB2-PI&R - BIENNIAL PI&R 4 1, 2 IP 71152B Identification and Resolution of Problems 08/08/2005 08/12/2005 Baseline Inspections 1, 2 IP 71152B Identification and Resolution of Problems 08/22/2005 08/26/2005 Baseline Inspections PS2-EP - EP INSPECTION/EXERCISE 1 1, 2 IP 7111401 Exercise Evaluation 08/22/2005 08/26/2005 Baseline Inspections 1, 2 IP 7111402 Alert and Notification System Testing 08/22/2005 08/26/2005 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 08/22/2005 08/26/2005 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/22/2005 08/26/2005 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 08/22/2005 08/26/2005 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 08/22/2005 08/26/2005 Baseline Inspections MTN-HEAD - U-2 REACTOR HEAD REPLACEMENT 3 2 IP 71007 Reactor Vessel Head Replacement Inspection 09/12/2005 09/16/2005 Other Routine MTN-ISI - U2 INSERVICE INSPECTION 2 2 IP 7111108P Inservice Inspection Activities - PWR 10/24/2005 10/28/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 3 Farley 03/03/2005 09:31:32 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type MTNTI160 - 2515/160 U-2: PZR PENTRATION NOZZLES 1 2 IP 2515/160 Pzr Pene Nozzles & Stm Space Piping Connections in U.S. PWRs [NRC Bulletin 2004-01] 10/31/2005 11/04/2005 Safety Issues PS1-RP - RP BASELINE & RX HEAD REPLACEMENT 1 1, 2 IP 71007 Reactor Vessel Head Replacement Inspection 10/31/2005 11/04/2005 Other Routine 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/31/2005 11/04/2005 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 10/31/2005 11/04/2005 Baseline Inspections MTN-MR - MR EFFECTIVENESS 1 1, 2 IP 7111112B Maintenance Effectiveness 12/05/2005 12/09/2005 Baseline Inspections MTN-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 02/13/2006 02/17/2006 Baseline Inspections PS1-RP - RP PREINSPECTION OCCUPATIONAL/ ISFSI 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/13/2006 03/15/2006 Baseline Inspections PS1-RP - RP BASELINE OCCUPATIONAL WK1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/03/2006 04/07/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/03/2006 04/07/2006 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 04/03/2006 04/07/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 04/03/2006 04/07/2006 Baseline Inspections MTN-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/10/2006 04/14/2006 Baseline Inspections MTNSGISI - U1 STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/17/2006 04/21/2006 Baseline Inspections PS1-RP - RP OCCUPATIONAL BASELINE WK2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 04/17/2006 04/21/2006 Baseline Inspections EB1SSDPC - SSDPC PRE-INSPECTION VISIT 1 1, 2 IP 7111121 Safety System Design and Performance Capability 07/31/2006 08/02/2006 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1, 2 IP 7111111B Licensed Operator Requalification Program 08/14/2006 08/18/2006 Baseline Inspections PS2-EP - EP EXERCISE 3 1, 2 IP 7111401 Exercise Evaluation 09/11/2006 09/15/2006 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 09/11/2006 09/15/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 09/11/2006 09/15/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Farley 03/03/2005 09:31:32 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY 6 1, 2 IP 7111121 Safety System Design and Performance Capability 09/11/2006 09/15/2006 Baseline Inspections 1, 2 IP 7111121 Safety System Design and Performance Capability 09/25/2006 09/29/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.