Inspection / Activity Plan, 03/01/2005 - 09/30/2006
ML050610529
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/02/2005
From:
Division Reactor Projects II
To:
Carolina Power & Light Co
Shared Package
ML050610521 List:
References
IR-05-001
Download: ML050610529 (2)


Text

Harris Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2005 11:48:02 Report 22 2

OL RQ

- REQUAL INSPECTION Baseline Inspections 03/07/2005 03/11/2005 Licensed Operator Requalification Program IP 7111111B 1

3 PS2-EP

- EMERGENCY EXERCISE Baseline Inspections 04/04/2005 04/08/2005 Exercise Evaluation IP 7111401 1

Baseline Inspections 04/04/2005 04/08/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 1

Baseline Inspections 04/04/2005 04/08/2005 Performance Indicator Verification IP 71151 1

2 MTN-HS

- HEAT SINK Baseline Inspections 05/23/2005 05/27/2005 Heat Sink Performance IP 7111107B 1

4 PB4-PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 06/13/2005 06/17/2005 Identification and Resolution of Problems IP 71152B 1

Baseline Inspections 06/27/2005 07/01/2005 Identification and Resolution of Problems IP 71152B 1

4 EB2-TFP

- FIRE PROTECTION-TRIENNIAL PRE INSP VISIT Baseline Inspections 07/25/2005 07/29/2005 Fire Protection IP 7111105T 1

4 PS-RP

- RP PUBLIC Baseline Inspections 08/01/2005 08/05/2005 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 08/01/2005 08/05/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1

Baseline Inspections 08/01/2005 08/05/2005 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1

Baseline Inspections 08/01/2005 08/05/2005 Radiological Environmental Monitoring Program IP 7112203 1

Baseline Inspections 08/01/2005 08/05/2005 Performance Indicator Verification IP 71151 1

4 EB2-TFP

- FIRE PROTECTION-TRIENNIAL Baseline Inspections 08/15/2005 08/19/2005 Fire Protection IP 7111105T 1

Baseline Inspections 08/29/2005 09/02/2005 Fire Protection IP 7111105T 1

2 OL PREP

- INITIAL EXAM PREP Not Applicable 01/09/2006 01/13/2006 HARRIS/EXAMS AT POWER FACILITIES V23233 1

3 OL EXAM

- INITIAL EXAM Not Applicable 01/23/2006 02/03/2006 HARRIS/EXAMS AT POWER FACILITIES V23233 1

3 EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 02/06/2006 02/10/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 1

Baseline Inspections 02/06/2006 02/10/2006 Permanent Plant Modifications IP 7111117B 1

1 PS2-EP

- EP INSPECTION Baseline Inspections 04/03/2006 04/07/2006 Alert and Notification System Testing IP 7111402 1

Baseline Inspections 04/03/2006 04/07/2006 Emergency Response Organization Augmentation Testing IP 7111403 1

Baseline Inspections 04/03/2006 04/07/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1

Baseline Inspections 04/03/2006 04/07/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1

Baseline Inspections 04/03/2006 04/07/2006 Performance Indicator Verification IP 71151 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Harris Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2005 11:48:02 Report 22 3

PS1-RP

- RP BASELINE OCCUPATIONAL WK1 Baseline Inspections 04/10/2006 04/14/2006 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 04/10/2006 04/14/2006 ALARA Planning and Controls IP 7112102 1

Baseline Inspections 04/10/2006 04/14/2006 Radioactive Material Processing and Transportation IP 7112202 1

Baseline Inspections 04/10/2006 04/14/2006 Performance Indicator Verification IP 71151 1

1 MTN-ISI

- INSERVICE INSPECTION Baseline Inspections 04/17/2006 04/21/2006 Inservice Inspection Activities - PWR IP 7111108P 1

3 PS1-RP

- RP BASELINE OCCUPATIONAL WK2 Baseline Inspections 04/24/2006 04/28/2006 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 04/24/2006 04/28/2006 ALARA Planning and Controls IP 7112102 1

Baseline Inspections 04/24/2006 04/28/2006 Radioactive Material Processing and Transportation IP 7112202 1

Baseline Inspections 04/24/2006 04/28/2006 Performance Indicator Verification IP 71151 1

1 MTNSGISI

- STEAM GENERATOR ISI Baseline Inspections 04/24/2006 04/28/2006 Inservice Inspection Activities - PWR IP 7111108P 1

1 MTN-MR

- MR EFFECTIVENESS Baseline Inspections 06/26/2006 06/30/2006 Maintenance Effectiveness IP 7111112B 1

2 EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 09/18/2006 09/20/2006 Safety System Design and Performance Capability IP 7111121 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.