ML050490456

From kanterella
Jump to navigation Jump to search
NRC Slides for Public Meeting Between PSEG and NRC Ref: Tech Issues/Sit
ML050490456
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 01/12/2005
From: Cobey E
NRC Region 1
To:
Cobey, Eugene W. RI/DRP/PB3 610-337-5171
Shared Package
ML050120400 List:
References
Download: ML050490456 (32)


Text

NRC & PSEG Meeting Hope Creek Special Inspection and Technical Issues January 12, 2005 Nuclear Regulatory Commission-Region I King of Prussia, PA

2 NRC Representatives

  • S. Collins, Regional Administrator, Region I
  • A. Randolph Blough, Director, Division of Reactor Projects
  • E. Cobey, Chief, Projects Branch 3
  • R. Lorson, Chief, Materials and Structural Engineering Branch, Division of Reactor Safety (DRS)
  • S. Pindale, Senior Reactor Inspector, DRS
  • M. Gray, Senior Resident Inspector, Hope Creek
  • C. Holden, Director, Project Directorate I, Office of Nuclear Reactor Regulation (NRR)
  • E. Imbro, Chief, Mechanical and Civil Engineering Branch, NRR
  • D. Collins, Senior Project Manager, NRR
  • T. Walker, Senior Communications Coordinator, Region I

3 Agenda

  • Introductions and NRC Opening Remarks
  • Special Inspection Team Results 3/4NRC Presentation 3/4PSEG Response
  • Additional NRC Actions Planned
  • Break
  • Public Questions and Comments to NRC Staff

4 NRC Special Inspection Team Exit Meeting (Hope Creek)

Inspection Report 50-354/2004-013 January 12, 2005

5 Introduction / Background

  • Event Chronology 3/4Moisture separator drain tank pipe failure 3/4Plant shutdown and cooldown Some equipment and operational challenges during cooldown phase
  • Special Inspection Team (SIT) 3/4Criteria 3/4Team Staffing 3/4Charter / Objectives

6 HP Turb XV1044 B CIV 2 A Moisture Separator MS Drain Tank Condenser - A LP Turb A LP Turb B LP Turb C Main Steam From Reactor XV1044 A CIV 3 XV1044 C CIV 1 LV1039A 5C Feedwater Heater 5B Feedwater Heater 5A Feedwater Heater V 024 HV 1361 A LV 1364 A HV 1361 B LV 1364 B HV 1361 C LV 1364 C 14 8

8 8

14 8

FC FC FC FO 8

System Diagram Break Location

7 Event Overview

  • Initial response prompt / appropriate
  • Licensee successful in achieving cold shutdown
  • Some operational / equipment issues represented challenges while progressing to cold shutdown conditions
  • No impact on public health and safety

8 Event Analysis

  • PSEG Actions 3/4Extensive inspections conducted 3/4Failure analysis performed by vendor 3/4Three root cause evaluations 3/4Multiple corrective actions planned and implemented (cause / equipment related)

9 Event Analysis

  • Engineering staff did not properly evaluate and recommend appropriate actions for failed moisture separator drain tank level control valve
  • Preliminary significance is low to moderate 3/4Initiating event resulted in isolation of main condenser (normal heat removal)

10 Operational / Equipment Issues

11 Radiological Assessment

  • No impact to health or safety of public
  • Radiological release - less than 2 % of Regulatory Limits

12 Conclusions

  • Event 3/4Unit was safely shutdown by operators and placed in a stable condition 3/4Radiological release well below regulatory limits 3/4No impact on public health and safety
  • Findings 3/4Improper evaluation of degraded condition caused the event 3/4Operators challenged by equipment issues, but all equipment could have performed its intended function

13 PSEG Response to Special Inspection Teams Findings

14 NRC Review of Technical Issues

  • HPCI turbine exhaust line

15 NRC Staffs Assessment of the HPCI Turbine Exhaust Line Issue Raymond K. Lorson, Chief, Materials and Structural Engineering Branch, Division of Reactor Safety (DRS)

16 HPCI Turbine Exhaust Line

  • Initial shutdown observations and testing identified a potential water hammer concern
  • System walkdowns and non-destructive testing did not identify any damage
  • Modifications and repairs implemented to minimize the potential for a water hammer event

17 NRC Staffs Assessment of the Hope Creek Reactor Recirculation Pump Issue Eugene V. Imbro, Chief, Mechanical and Civil Engineering Branch, Office of Nuclear Reactor Regulation (NRR)

18 What are the Safety Questions Related to the B Reactor Recirculation (RR) Pump Hope Creek B RR pump has exhibited high vibration levels High vibration levels may induce loads on the pump shaft and lead to shaft failure RR pumps perform a safety-related function to maintain the reactor coolant pressure boundary Shaft failure could damage pump seals and result in leakage through seals Plant operation with a likelihood of leakage through the RR pump seals is unacceptable The occurrence of a seal LOCA is a safety concern to the NRC

19 Why Is It Safe to Operate the B RR Pump with Existing Shaft?

  • The licensee is implementing an enhanced vibration monitoring program for the RR pumps 3/4Continuous monitoring of pump vibration levels 3/4Definitive alarm set-points 3/4Timely operator actions to protect the pump from shaft failure
  • The NRC staff reviewed the details of the licensees vibration monitoring plan and operating procedures
  • The NRC staff has confidence that:

3/4Critical vibration levels in RR pump shaft can be detected early 3/4Timely operator actions will be taken

20 Technical Bases for NRC Staffs Findings on the Hope Creek RR Pump The NRC staff focused on three key questions:

1) What operating plant experience exists that demonstrates RR pump shaft failure at Hope Creek is unlikely for another cycle?
2) What data exists demonstrating that cracks in the RR pump shaft can be detected in a timely manner to enable operators to take appropriate actions?
3) What are the consequences of a RR pump shaft failure during normal plant operations?

The NRC staff also reviewed the licensees vibration monitoring plan The details of the staffs technical bases are discussed in the next slides

21 Understanding the Crack Failure Mechanism in the RR Pump Shaft

  • GE Services Information Letter (SIL) 459 indicates Byron-Jackson RR pump shafts are prone to thermally induced cracking
  • Thermally induced cracks initiate in the axial direction and are relatively benign
  • Additional mechanical loads on the shaft can cause cracks to grow circumferentially and could lead to complete shaft failure
  • Length of time for axial cracks to transition to circumferential cracks depends on the magnitude of the mechanical loads
  • Circumferential cracks can grow rapidly (hours or days) prior to shaft failure
  • The magnitude of the mechanical loading on Hope Creeks shaft is unknown
  • The remaining shaft life of Hope Creeks RR pumps cannot be reasonably predicted or calculated

22

1) Operational Experience on RR Pump Vibration and Shaft Failures
  • No domestic boiling-water reactor (BWR) has experienced complete shaft failure in the RR pump
  • One BWR experienced severe RR shaft cracking that was detected prior to failure
  • Hope Creek has higher-than-average vibration levels in its B RR pump
  • Hope Creeks RR pump vibration alarm limits are consistent with vendor recommendations
  • The vibration levels of the Hope Creek RR pumps are within the range of operational experience of BWRs with similar RR pumps

23

2) Experience with Vibration Monitoring to Detect Shaft Cracking
  • A BWR and several pressurized-water reactors (PWRs) detected cracked RR pump shafts using a vibration monitoring program prior to failure
  • Experience shows that continuous monitoring of pump vibration levels can reasonably detect shaft cracking prior to complete failure
  • Hope Creeks RR pump shaft material can tolerate relatively large cracks allowing more time for detection prior to complete failure

24

3) Consequences of a RR Pump Failure
  • If the pump shaft completely fails, some damage to the seal is likely to occur
  • If a seal failure results, leakage of reactor coolant through shaft clearances will occur
  • Leakage is limited by tight shaft clearances and is bounded by a design-basis, small-break LOCA
  • The Hope Creek plant is designed to allow isolation of the RR pump with isolation valves in the RR system
  • The consequences of a RR pump shaft failure is within Hope Creeks licensing basis

25 NRC Staffs Evaluation of the Hope Creek RR Pump Vibration Monitoring Plan

  • Licensees vibration monitoring plan consists of:

3/4 Continuous monitoring of the overall pump radial vibration with alarms set at:

  • 11 mils for operators to reduce pump speed
  • 16 mils for operators to remove the pump from service 3/4 Continuous monitoring of 1X and 2X vibration amplitude and phase angle with alarms in the control room to initiate timely operator actions
  • The normal vibration levels for the RR B pump at Hope Creek are in the range of 8-10 mils
  • Continuous monitoring of pump vibration provides confidence that changes in the vibration levels can be detected early
  • The licensees operating procedures provide timely actions to prevent complete shaft failure

26 Conclusions

  • The NRC staff concludes that the licensees vibration monitoring plan for the Hope Creek RR pumps provide confidence that the RR pumps can be operated safely for the next cycle

27 PSEG Response to the NRCs Review of Technical Issues

28 Additional NRC Actions Planned

  • Issue a Confirmatory Action Letter (CAL) on PSEGs commitments regarding the B reactor recirculation pump 3/4 Implementation of a continuous vibration monitoring program 3/4 Inspection of pump components and replacement of the pump shaft no later than the next refueling outage 3/4 Notification of the NRC prior to modifying the vibration monitoring program to allow ample time for NRC review
  • Inspections throughout the operating cycle will verify that PSEG adheres to commitments
  • NRC evaluating generic aspects of recirculation pump issues

29 Additional NRC Actions Planned (Continued)

  • Substantial inspector oversight during the startup of Hope Creek from the ongoing refueling outage
  • Continue actions per Reactor Oversight Process (ROP) deviation established in August 2004 3/4 More inspection 3/4 More oversight 3/4 Increased oversight will continue until PSEG has achieved substantial, sustainable progress
  • Future meetings between NRC and PSEG which will be open to public observation 3/4 Annual assessment meeting 3/4 Semi-annual management meetings on work environment at the station

30 Reference Sources

  • Public Document Room 1-800-397-4209
  • Public Affairs Office (610) 337-5330/5331

31 Break

32 Public Questions and Comments to NRC Staff