NRC Slides for Public Meeting with PSEG on SCWE Update Activities at Salem & Hope Creek
ML043480237
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 12/02/2004
From: Doug Tifft
NRC Region 1
To:
Cobey, Eugene W. RI/DRP/PB3 610-337-5171
Shared Package
ML043220044 List:
References
Download: ML043480237 (8)


Text

1 NRC & PSEG Meeting Salem and Hope Creek December 2, 2004 Nuclear Regulatory Commission-Region I King of Prussia, PA

2 NRC Representatives

  • S. Collins, Regional Administrator, Region I
  • A. Randolph Blough, Director, Division of Reactor Projects
  • E. Cobey, Chief, Projects Branch 3
  • R. Lorson, Chief, Materials & Structural Engineering Branch
  • C. Holden, Director, Project Directorate I, Nuclear Reactor Regulation
  • D. Orr, Senior Resident Inspector, Salem
  • G. Malone, Resident Inspector, Salem
  • M. Gray, Senior Resident Inspector, Hope Creek
  • M. Ferdas, Resident Inspector, Hope Creek
  • J. Persensky, Senior Human Factors Specialist
  • A. Kock, Assistant Agency Allegations Advisor, Office of Enforcement

3 Agenda

  • NRC Introduction
  • NRC/PSEG Discussion
  • NRC/PSEG Meeting Conclusion
  • Break
  • Public Comments to NRC

4 NRC Assessment Results

  • No Serious Safety Violations Identified 3/4Plants continue to operate safely
  • Substantive Cross-Cutting Issues Exist 3/4Problem, Identification and Resolution Last four assessment letters dated March 3, 2003, August 27, 2003, March 3, 2004, and August 30, 2004 3/4Safety Conscious Work Environment Assessment letter dated August 30, 2004

5

  • Late 2003 Special Review Initiated 3/4Inspection Results 3/4Assessment 3/4Allegations
  • Special Review Interim Results 3/4January 28, 2004 letter requested PSEG conduct in-depth assessment
  • March 2004 Management Meeting 3/4Discussed PSEG assessment plans
  • June 2004 Management Meeting 3/4Discussed assessment results and PSEG action plan NRC Timeline

6 NRC Timeline (continued)

  • NRC Special Review Results 3/4 July 30, 2004 letter validated work environment concern
  • Reactor Oversight Process Deviation est. Aug 23, 2004 3/4 More Inspection 3/4 More Focus 3/4 More Oversight 3/4 More SCWE Review 3/4 Increased Oversight will continue until PSEG has achieved substantial, sustainable progress
  • August 30, 2004 NRC Assessment Letter 3/4 Documented SCWE and PI&R substantive cross-cutting issues

7 December 2, 2004 NRC & PSEG Meeting

Purpose:

  • PSEG update on efforts to improve the work environment 3/4 Problem Identification & Resolution 3/4 Safety Conscious Work Environment
  • Other topics 3/4 Role and Function of Quality Assurance Organization 3/4 Human Performance 3/4 Quality of Engineering Products

8 Reference Sources

  • Public Document Room 1-800-397-4209 (Toll Free)
  • Public Affairs Office (610) 337-5331