October 2004 Monthly Operating Report for Oyster Creek Generating Station
ML043280522
Person / Time
Site: Oyster Creek
Issue date: 11/13/2004
From: Swenson C
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2130-04-20264, GL-97-002
Download: ML043280522 (2)


Text

AmerGen SM AmerGen Energy Company, LLC Oyster Creek US Route g South, P.O. Box 388 Forked River, NJ 08731-0388 www.exeloncorp.com An Exelon Company GL 97-02 November 13, 2004 2130-04-20264 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 - 0001 Oyster Creek Generating Station Facility Operating License No. DPR-1 6 NRC Docket No. 50-219

Subject:

Monthly Operating Report - October 2004 Enclosed is the October 2004 Monthly Operating Report for Oyster Creek Generating Station. The content and format of information submitted in this report is in accordance with the guidance provided by Generic Letter 97-02.

If any further information or assistance is needed, please contact David Fawcett at 609-971-4284.

C. N. Swenson Vice President, Oyster Creek Generating Station CNS/DIF Enclosure cc:

S. J. Collins, Administrator, USNRC Region I P. S. Tam, USNRC Senior Project Manager, Oyster Creek R. J. Summers, USNRC Senior Resident Inspector, Oyster Creek File No. 04002

, 11 11-11

OPERATING DATA REPORT DOCKET NO.

50-219 UNIT NAME Oyster Creek 1 DATE November 09, 2004 COMPLETED BY Roger B. Gayley TELEPHONE (609) 971-4406 REPORTING PERIOD:

October 2004

1.

Design Electrical Rating

2. Maximum Dependable Capacity (MWe-Net) 650.00 619.00 3.

4.

5.

6.

Number of Hours the Reactor was Critical Number of Hours Generator On-line Reserve Shutdown Hours Net Electrical Energy Generated (MWHrs)

This Month 745.00 745.00 0.00 462,856.00 Yr-to-Date 7,037.15 6,989.28 0.00 4,250,221.00 Cumulative 225,474.17 221,184.93 918.20 126,644,974.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No.

Date S: Scheduled (Hours)

Reason 1 Down 2 Comments

SUMMARY

During October, Oyster Creek generated 462,856 net MWh electric, which was 100.4% of its MDC rating.

1 2

Reason:

A Equipment Failure (Explain)

B Maintenance or Test C

Refueling D

Regulatory Restriction E

Operator Training & License Examination F

Administration G

Operational Error (Explain)

H Other (Explain)

Method:

1 Manual 2

Manual Trip/Scram 3

Automatic Trip/Scram 4

Continuation 5

Other (Explain)

Page 1 of 1