November 12, 2004 LICENSEE:

Nuclear Management Company, LLC FACILITY:

Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE ON SEPTEMBER 13, 2004, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING DRAFT REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATIONS The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on September 13, 2004, to discuss and clarify the staffs draft requests for additional information (D-RAI) concerning the Point Beach Nuclear Plant License Renewal Applications. The conference call was useful in clarifying the intent of the staffs D-RAIs. provides a list of the meeting participants. Enclosure 2 contains a listing of the D-RAIs discussed with the applicant, including a brief description on the status of the items.

The applicant has had an opportunity to review and comment on this summary.

/RA/

Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301

Enclosures:

As stated cc w/encls: See next page

ML043170664 DOCUMENT NAME: E:\\Filenet\\ML043170664.wpd OFFICE PM:RLEP GE:RLEP LA:RLEP SC:RLEP NAME M.Morgan M.Heath MJenkins SLee DATE 11/12/04 11/8/04 11/5/04 11/12/04

DISTRIBUTION: Summary of Telecon with NMC Re: Draft requests for additional information Dated: November 12,2004, Adams Accession No: ML043170664 HARD COPY RLEP RF M. Morgan (PM)

M. Heath E-MAIL:

RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li M, Itzkowitz (RidsOgcMailCenter)

R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. (Renee) Li RLEP Staff P. Lougheed, RIII W. Ruland D. Spaulding L. Raghavan A. Vegel, RIII T. Mensah OPA

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esq.

Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. F. D. Kuester President and Chief Operating Officer WE Generation 231 West Michigan Street Milwaukee, WI 53201 Regulatory Affairs Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffrey Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Site Director of Operations Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Kenneth Westlake Chief, Environmental Planning and Evaluation Branch U.S. EPA Mail Code B-195 77 W. Jackson Blvd.

Chicago, IL 60604 Mr. Fred Emerson Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Mr. James E. Knorr 6610 Nuclear Road Two Rivers, WI 54241 LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION September 13, 2004 PARTICIPANTS AFFILIATION Devender Reddy U.S. Nuclear Regulatory Commission (NRC)

Maurice Heath NRC Jim E. Knorr Nuclear Management Company, LLC (NMC)

Todd Mielke NMC Brad Fromm NMC Bill Herman NMC POINT BEACH NUCLEAR POWER PLANT, UNITS 1 AND 2 REVIEW OF LICENSE RENEWAL APPLICATION FOR DRAFT REQUESTS FOR ADDITIONAL INFORMATION (D-RAI)

September 13, 2004 D-RAI 2.2-1 The Point Beach Nuclear Plant Updated Final Safety Analysis Report (PBNP UFSAR)

Section 6.5.1 Leakage Detection Systems states, Means shall be provided to detect significant uncontrolled leakage from the reactor coolant pressure boundary (GDC 16). Positive indications in the control room of leakage of coolant from the reactor coolant system to the containment are provided by equipment which permits continuous monitoring of containment air activity and humidity, and of runoff from the air recirculation units and containment floor drains to containment Sump A. This equipment provides indication of normal background which is indicative of a basic level of leakage from primary systems and components. Any increase in the observed parameters is an indication of change within the containment, and the equipment provided is capable of monitoring this change. The basic design criterion is the detection of deviations from normal containment environmental conditions including air particulate activity, gaseous activity, humidity, condensate and floor drain runoff and, in addition, in the case of gross leakage, the liquid inventory in the process systems and containment sump.

The Point Beach license renewal application (LRA) Sections 2.5.13 and 2.5.13 addresses the radiation monitoring system portion of the RCS leakage monitoring system. However, the humidity detection and runoff from the air recirculation units and containment floor drains to the containment sump could not be found in the LRA. The licensee is required to monitor RCS leakage and take actions in accordance with the facility Technical Specifications. A large leak in the reactor coolant system pressure boundary, which does not flow into another closed loop, would result in reactor coolant flowing into the containment sump. Consistent with GDC 16 the entire RCS leakage system should be available to the operator in the control room. The licensee is requested to provide justification as to why the humidity detection and containment sump portions of the RCS leakage detection systems did not need to be addressed in the LRA or provide feedback as to where it was addressed, or amend the application to include these portions of the system.

Discussion: The applicant indicated the information is contained in the LRA Scoping Drawings on LR-684J971 Sheet 1, Section B-9 and based on the FSAR 6.5.2. Therefore, this question is WITHDRAWN and will not be sent as a RAI.