November 8, 2004 Mr. Garry L. Randolph Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251
SUBJECT:
CALLAWAY PLANT, UNIT 1 - WITHDRAWAL OF DEFENSE-IN-DEPTH AND DIVERSITY ASSESSMENT FOR DIGITAL UPGRADE OF INSTRUMENTATION AND CONTROL SYSTEMS (TAC NO. MC2287)
Dear Mr. Randolph:
By letter dated March 4, 2004 (ULNRC-04945), you submitted a defense-in-depth and diversity (D3) assessment for the Framatome Advanced Nuclear Power (FANP) TELEPERM XS system to be installed in the Callaway Plant. The D3 assessment was submitted in a proprietary and a non-proprietary version. The FANP TELEPERM XS system was to replace the current analog-based instrumentation and control (I&C) systems, including the reactor trip system and engineered safety features actuation systems, with a digital-based system, and the D3 assessment was to support license amendment requests for the planned I&C system replacements at Callaway. This D3 assessment was submitted jointly with the Wolf Creek Nuclear Operating Corporation, and review of this D3 assessment was requested by December 1, 2004.
A meeting that included representatives of the Wolf Creek Nuclear Operating Corporation was held on April 15, 2004, in which the NRC staff recommended that your staff consider submitting an alternative to the D3 assessment if approval was needed by December 1, 2004. The meeting summary was issued by the NRC on April 22, 2004. A letter accepting the proprietary information submitted in the letter of March 4, 2004, was issued by the NRC on April 22, 2004.
In the letter of September 24, 2004 (ULNRC-05061), your staff stated that, based in part on the discussion in the April 15, 2004, meeting, it has decided to withdraw the D3 assessment and submit a new D3 assessment at a later date. In addition, the implementation schedule for the FANP TELEPERM XS modifications at Callaway has been postponed. Based on the letter of September 24, 2004, we have closed out our review of the D3 assessment of the FANP TELEPERM XS system and TAC No. MC2287 is closed.
Sincerely,
/RA/
Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 cc: See next page
November 8, 2004 Mr. Garry L. Randolph Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251
SUBJECT:
CALLAWAY PLANT, UNIT 1 - WITHDRAWAL OF DEFENSE-IN-DEPTH AND DIVERSITY ASSESSMENT FOR DIGITAL UPGRADE OF INSTRUMENTATION AND CONTROL SYSTEMS (TAC NO. MC2287)
Dear Mr. Randolph:
By letter dated March 4, 2004 (ULNRC-04945), you submitted a defense-in-depth and diversity (D3) assessment for the Framatome Advanced Nuclear Power (FANP) TELEPERM XS system to be installed in the Callaway Plant. The D3 assessment was submitted in a proprietary and a non-proprietary version. The FANP TELEPERM XS system was to replace the current analog-based instrumentation and control (I&C) systems, including the reactor trip system and engineered safety features actuation systems, with a digital-based system, and the D3 assessment was to support license amendment requests for the planned I&C system replacements at Callaway. This D3 assessment was submitted jointly with the Wolf Creek Nuclear Operating Corporation, and review of this D3 assessment was requested by December 1, 2004.
A meeting that included representatives of the Wolf Creek Nuclear Operating Corporation was held on April 15, 2004, in which the NRC staff recommended that your staff consider submitting an alternative to the D3 assessment if approval was needed by December 1, 2004. The meeting summary was issued by the NRC on April 22, 2004. A letter accepting the proprietary information submitted in the letter of March 4, 2004, was issued by the NRC on April 22, 2004.
In the letter of September 24, 2004 (ULNRC-05061), your staff stated that, based in part on the discussion in the April 15, 2004, meeting, it has decided to withdraw the D3 assessment and submit a new D3 assessment at a later date. In addition, the implementation schedule for the FANP TELEPERM XS modifications at Callaway has been postponed. Based on the letter of September 24, 2004, we have closed out our review of the D3 assessment of the FANP TELEPERM XS system and TAC No. MC2287 is closed.
Sincerely,
/RA/
Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 DISTRIBUTION:
PUBLIC RidsNrrDlpmPdiv (HBerkow) cc: See next page PDIV-2 Reading RidsNrrDlpmPdiv2 (RGramm)
RidsNrrPMJDonohew RidsNrrLAEPeyton RidsOgcRp RidsAcrsAcnwMailCenter RidsRegion4MailCenter (D. Graves) EMarinos ACCESSION NO.: ML043090016 NRR-106 OFFICE PDIV-2/PM PDIV-2/LA EEIB-A/SC PDIV-2/SC NAME JDonohew:mp EPeyton EMarinos RGramm DATE 11/8/04 11/4/04 11/8/04 11/8/04 DOCUMENT NAME: E:\\Filenet\\ML043090016.wpd OFFICIAL RECORD COPY
Callaway Plant, Unit 1 cc:
Professional Nuclear Consulting, Inc.
19041 Raines Drive Derwood, MD 20855 John ONeill, Esq.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W.
Washington, D.C. 20037 Mr. Mark A. Reidmeyer, Regional Regulatory Affairs Supervisor Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 U.S. Nuclear Regulatory Commission Resident Inspector Office 8201 NRC Road Steedman, MO 65077-1302 Mr. Chris Younie Manager, Quality Assurance AmerenUE P.O. Box 620 Fulton, MO 65251 Manager - Electric Department Missouri Public Service Commission 301 W. High P.O. Box 360 Jefferson City, MO 65102 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Mr. Ronald A. Kucera Deputy Director for Public Policy Department of Natural Resources P.O. Box 176 Jefferson City, Missouri 65102 Mr. Rick A. Muench President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839 Mr. Dan I. Bolef, President Kay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, MO 63130 Mr. Lee Fritz, Presiding Commissioner Callaway County Court House 10 East Fifth Street Fulton, MO 65151 Mr. David E. Shafer Superintendent, Licensing Regulatory Affairs AmerenUE P.O. Box 66149, MC 470 St. Louis, MO 63166-6149 Mr. Keith D. Young Manager, Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 Mr. Scott Clardy, Director Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Certrec Corporation 4200 South Hulen, Suite 630 Fort Worth, TX 76109