ML043070449

From kanterella
Jump to navigation Jump to search

TS Page for Southtexas, Unit 2
ML043070449
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 10/21/2004
From:
NRC/NRR/DLPM
To:
References
TAC MC4468
Download: ML043070449 (1)


Text

REACTOR COOLANT SYSTEM RELIEF VALVES SURVEILLANCE REQUIREMENTS 4.4.4.1 In addition to the requirements of Specification 4.0.5, each PORV shall be demonstrated OPERABLE at least once per 18 months by:

a.

Performing a CHANNEL CALIBRATION on the actuation channel, and

b.

Operating the valve through one complete cycle of full travel.

4.4.4.2 Each block valve shall be demonstrated OPERABLE at least once per 92 days by operating the valve through one complete cycle of full travel unless the block valve is closed in accordance with the ACTIONS of Specification 3.4.4.

I SOUTH TEXAS - UNIT 2

3/4 4-11 Unit 2 - Amendment No.-44, 153