Duke SAFEGUARDS INFORMATION HENRY B. BARRON W
'PowerR Group VP, Nuclear Generation and Chief Nuclear Officer Abke Energy Company Duke Power EC07H / 526 South Church Street Charlotte, NC 28202-1802 Mailing Address:
P. 0. Box 1006 - EC07H Charlotte, NC 28201-1006 October 21, 2004 704 382 2200 U.S. Nuclear Regulatory Commission 704 382 6056 fax ATTN: Document Control Desk hbarron~duke-energy.com Washington, DC 20555-0001
Subject:
Duke Energy Corporation Oconee Nuclear Station, Units 1, 2, and 3 NRC Docket Nos. 50-269, 50-270, 50-287 McGuire Nuclear Station, Units 1 and 2 NRC Docket Nos. 50-369, 50-370 Catawba Nuclear Station, Units 1 and 2 NRC Docket Nos. 50-413, 50-414 Supplemental Response to April 29, 2003 NRC Order Requiring Compliance With Revised Design Basis Threat For Operating Power Reactors (EA-03-086)
The U.S. Nuclear Regulatory Commission ("NRC") issued an Order dated April 29, 2003 requiring compliance with Revised Design Basis Threat ("Order EA-03-086") and other security related Orders (collectively "Orders") in Docket Nos. 50-269, 50-270, 50-287, Oconee Nuclear Station, 50-369, 50-370, McGuire Nuclear Station, and 50-413, 50-414, Catawba Nuclear Station. On June 2, 2003 pursuant to 10 CFR §50.4 and Conditions III A.1, B.1 and B.2, Duke Energy Corporation ("Duke") submitted its response to Order EA-03-086. On April 27, 2004 Duke submitted a supplemental response to Order EA-03-086.
Duke responded to Requests for Additional Information ("RAI") in letters dated July, 7, 2004, July 13, 2004, July 22, 2004, August 9, 2004 (two separate letters, both dated August 9, 2004),
and August 12, 2004. In each letter, Duke made the following commitment, "upon resolution of this and forthcoming NRC RAI, Duke will submit a revision to the April 27, 2004 submittal."
On September 8, 2004 Duke submitted revision 1 to the Physical Security Plan as a second supplemental response to Order EA-03-086.
On September 20, 2004, September 23, 2004, September 30, 2004, and October 20, 2004 in telephone calls between the NRC and Duke, additional changes to the Physical Security Plan were discussed. On September 30, 2004 Duke submitted revision 2 to the Physical Security Plan as a third supplemental response to Order EA-03-086. On October 15, 2004 Duke submitted revision 3 to the Physical Security Plan as a fourth supplemental response to Order EA-03-086. In accordance with 10 CFR §50.4, Duke hereby submits its fifth supplemental response to Order EA-03-086. This supplement includes changes reflected as revision 4 to the Physical Security Plan based on the aforementioned discussions between the NRC and Duke.
O00yca SAFEGUARDS INFORMATION Heritage
- Service
- Vision 6
NOTE: TIHE ATTACHMENT TO TIlS LETTER CONTAINS "SAFEGUARDS INFORMIATION" AND MIUST BE www.dukepower.com PROTECTED ACCORDINGLY. UPON SEPARATION OF TIIE ATTACIhINIENT, TIlS LETTER IS "DECONTROLLED."
'V SAFEGUARDS INFORMATION U.S. Nuclear Regulatory Commission October 21, 2004 Page 2 The attached information contains Safeguards Information and is subject to the restrictions described in 10 CFR §73.21.
If you have any questions regarding this submittal, please contact Randall D. Hart, Catawba Nuclear Station, at (803) 831-3622.
Sincerely,
/Je' 17 Henry B. Barron Group Vice President, Nuclear Generation and Chief Nuclear Officer Attachments SAFEGUARDS INFORMATION NOTE: TIlE ATTACHMENT TO THIS LETTER CONTAINS "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF TIIE ATTACHMNENT, THIS LETTER IS "DECONTROLLED."