t1503 Lake Road Ontario, New York 14519-9364 585.771.3000 Constellation Energy R.E. Ginna Nuclear Power Plant, LLC October 7, 2004 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555
Subject:
Emergency Operating Procedures R.E. Ginna Nuclear Power Plant Docket No. 50-244 As requested, enclosed are Ginna Station Emergency Operating Procedures.
Very truly yours, Thomas A. Marlow TAM/jdw xc:
U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 Ginna USNRC Senior Resident Inspector Enclosure(s):
ATT Index ATT-5.2, Rev 4
NPSP0200 E66429 C
Ginna Nuclear Power Plant PROCEDURE INDE)
C t
Tue 10/1212004 10:23:38 am Page I of 2 INPUT PARAMETERS: TYPE:
PRATT STATUSVALUE(S):
EF,QU 5 YEARS ONLY:
PRATT EOP ATTACHMENTS PROCEDURE EFFECT LAST NEXT NUMBER PROCEDURE TITLE REV DATE REVIEW REVIEW ST ATT-1.0 ATT-1.1 ATT-2.1 ATT-2.2 ATT-2.3 ATT-2.4 ATT-2.5 ATT-3.0 ATT-3.1 ATT-4.0 ATT-5.0 ATT-5.1 ATT-5.2 ATT-6.0 ATT-7.0 ATT-8.0 ATT-8.1 ATT-8.2 ATT-8.3 ATT-8.4 ATT-8.5 ATT-9.0 ATT-9.1 ATT-10.0 ATT-11.0 ATT-11.1 ATT-11.2 ATT-12.0 ATT-13.0 ATT-14.0 ATTACHMENT AT POCHER CCWAIJGNMENT ATTACHMENT NORMAL CCW FLOW ATTACHMENT MIN SW ATTACHMENT SW ISOLATION ATTACHMENT SW LOADS IN CNMT ATTACHMENT NO SW PUMPS ATTACHMENT SPUT SW HEADERS ATTACHMENT CUCIA ATTACHMENT CNMT CLOSURE ATTACHMENT CNMT RECIRC FANS ATTACHMENT COND TO S/G ATTACHMENT SAFW ATTACHMENT FIRE WATER COOUNG TO TDAFW PUMP ATTACHMENT COND VACUUM ATTACHMENT CR EVAC ATTACHMENT DC LOADS ATTACHMENT DIG STOP ATTACHMENT GEN DEGAS ATTACHMENT NONVITAL ATTACHMENT SWV ATTACHMENT LOSS OF OFFSITE POWER ATTACHMENT LETIDCOhI ATTACHMENT EXCESS L/D ATTACHMENT FAULTED S/K ATTACHMENT IA CONCERNS ATTACHMENT IA SUPPLY ATTACHMENT DIESEL AIR COMPRESSOR ATTACHMENT N2 PORVS ATTACHMENT NC ATTACHMENT NORMAL RHR COOUNG 003 02112/2003 02/12/2003 000 05/18/2000 05/18/2000 005 02/01/2001 02/03/2003 008 03106/2002 03/27/2003 004 03/06/2002 04106/2004 002 05/3012003 10/31/2001 000 06/26/2002 06126/2002 007 02/17/2004 02/1712004 005 02/17/2004 02117/2004 003 07126/1994 03/27/2003 006 10/10/2003 04/06/2004 008 05/3012002 041062004 004 10/07/2004 81120151/2 003 12/18/1996 02/03/2003 006 03/06/2002 02/03/2003 007 02/04/2004 02/04/2004 005 03/06/2002 02/03/2003 008 06/20/2002 05/28/2004 004 03/06/2002 02/03/2003 005 03/06/2002 02/03/2003 001 08/26/2003 05/02/2002 009 01/07/2004 03/06/2002 006 07/28/2004 10/31/2001 006 03/06/2002 03/27/2003 004 09/01/2004 03/27/2003 003 03/06/2002 03/27/2003 004 11/18/2002 03/10/2003 005 02/12/2003 02112/2003 003 02/12/2003 02/12/2003 003 03/06/2002 04/06/2004 02112/2008 05/18/2005 02/03/2008 03/2712008 EF EF EF EF 04/06/2009 EF 10/31/2006 EF 06/26/2007.
EF 02/1712009 EF 02117/2009 EF 03127/2008 EF 04/06/2009 EF 04/06/2009 01/28/2009 02/03/2008 02/03/2008 02/04/2009 EF EF EF 6:
6:
02103/2008 EF 05/28/2009 EF 02/03/2008 EF 02/03/2008 EF 05/02/2007 EF 03/06/2007 EF 10/31/2006 EF 03/27/2008 EF 03/27/2008 EF 03/27/2008 03/10/2008 02/12V2008 02/12/2008 04/06/2009 EF EF 6:
6:
6:
NPSP0200 E66429 (I
Ginna Nuclear Power Plant PROCEDURE INDE)
(7A Tue 10/121200410:23:38 am
{f Page 2 of 2 INPUT PARAMETERS: TYPE:
PRATT STATUSVALUE(S):
EFQU 5 YEARS ONLY:
PRATT EOP ATTACHMENTS PROCEDURE EFFECT LAST NEXT NUMBER PROCEDURE TITLE REV DATE REVIEW REVIEW ST ATT-14.1 ATTACHMENT RHR COOL 007 0910112004 0110812002 01108/2007 EF ATT-14.2 ATTACHMENT RHR ISOL 003 02112V2003 02112V2003 02112/2008 EF ATT-14.3 ATTACHMENT RHR NPSH 003 03/06/2002 01/28/2004 01/2812009 EF ATT-14.5 ATTACHMENT RHR SYSTEM 003 03/2012003 02o0312003 02103/2008 EF ATT-14.6 ATTACHMENT RHR PRESS REDUCTlON 002 03106/2002 01/28/2004 01/282009 EF ATT-14.7 ATTACHMENT ADJUST RHR FLOW 000 02117/2004 02117/2004 02117/2009 EF ATT-15.0 ATTACHMENT RCP START 009 03106/2002 03117/2000 03/17/2005 EF ATT-15.1 ATTACHMENT RCP DIAGNOSTICS 003 04/2411997 02103/2003 02103/2008 EF ATT-15.2 ATTACHMENT SEAL COOUNG 005 03/06/2002 02103/2003 02103/2008 EF ATT-16.0 ATTACHMENT RUPTUREDS/G 012 04/2912004 01/11/2000 01111/2005 EF ATT-1 6.1 ATTACHMENT SGTL 003 09101/2004 09/08/2000 09/082005 EF ATT-16.2 ATTACHMENT RCS BORON FOR SGTL 003 11/26/2003 09/08/2000 09/0812005 EF ATT-17.0 ATTACHMENT SD-1 017 09/01/2004 02/29/2000 02/28/2005 EF ATT-17.1 ATTACHMENT SD-2 007 09/01/2004 01/30/2001 01/30/2006 EF ATT-1 8.0 ATTACHMENT SFP - RWST 005 03/06/2002 02103/2003 02103/2008 EF ATT-20.0 ATTACHMENTVENTTIME 004 09/01/2004 02V03/2003 02103/2008 EF ATT-21.0 ATTACHMENT RCS ISOLATION 002 03/06/2002 02103/2003 02103/2008 EF ATT-22.0 ATTACHMENT RESTORING FEED FLOW 003 05/02/2002 01/2212002 01/22/2007 EF ATT-23.0 ATTACHMENT TRANSFER 4160V LOADS 000 02/26/1999 01/28/2004 01/2812009 EF ATT-24.0 ATTACHMENT TRANSFER BATTERY TO TSC 000 09/08/2000 09/08/2000 09/0812005 EF ATT-26.0 ATTACHMENT RETURN TO NORMAL OPERATIONS 000 10/31/2001 10/31/2001 1031/2006 EF PRATT TOTAL 51 GRAND TOTAL 51
Responsible Manager J Date 1070 CAUTION MAXIMUM ALLOWED TDAFW PUMP OPERATION WITH NO COOLING IS 2 HOURS.
NOTE:
o IF fire water is available for TDAFW pump cooling, THEN perform Part A.
o IF fire water is NOT available, THEN perform Part B.
A. Aligning Fire Water Cooling to the TDAFW Pump
- 1. Obtain the hose from the Turbine Bldg. hose locker (top floor).
- 2.
CLOSE service water root valve to the TDAFW pump thrust bearing and lube oil cooler V-4087C (located on the south side of the pump below MOV-4013).
- 5. Check OPEN instrument root valve to PI-2134 SW inlet to TDAFW oil cooler V-4288 (located at the north west corner of the oil sump).
- 6. Connect one end of the hose to PI-2134.
- 7. Connect the other end of the hose to the Fire Water Main at valve V-9226.
(V-9226 is located by the S/G blowdown CNMT Isol Valves)
NOTE:
The following action may result in an automatic start of the Diesel Driven Fire Pump.
- 8. OPEN Containment hose reel supply drain & test connection valve V-9226.
- 9. VERIFY water is being supplied to the TDAFW pump thrust bearing by observing flow past valve V-4089A TDAFW Thrust bearing SW outlet block valve.
- 10. Verify PI-2134 indicates less than 150 psig.
- 11. Notify the Control Room fire water cooling is aligned to the TDAFW pump.
_4 EDP:
TITLE:
REV4 i
ATT-5.2 ATTACHMENT FIRE WATER COOLING TO TDAFW PUMP II PAGE 2 of 2 B. Aligning Self Cooling to the TDAFW Pump CAUTION THIS ALTERNATE COOLING METHOD DEPLETES CST INVENTORY.
THEREFORE, THIS METHOD OF COOLING SHOULD BE DELAYED AS LONG AS POSSIBLE, BUT NOT TO EXCEED A TDAFP RUN TIME OF 2 HOURS WITH NO COOLING.
NOTE:
Locked valve key is required.
I
- 1.
Close service water root valve to the TDAFW pump thrust I
bearing and lube oil cooler, V-4087C (south side of pump below MOV-4013).
l
cooler, V-4085.
I
- 3.
Ensure closed SW bypass isol from TDAFW pump lube oil cooler, V-4085B.
- 4. Ensure closed V-4299D, TDAFW pump casing drain valve.
I
- 5.
Open V-4299K, TDAFW pump self cooling outer isolation valve.
I
- 6. Open V-4299L, TDAFW pump self cooing inner isolation I
valve.
- 7. Notify the Control Room that the TDAFW pump is in the I
self-cooling alignment.
I