Plans for Submittal of Preliminary Decommissioning Cost-Estimate
ML042890218
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 09/30/2004
From: Spina J
Constellation Energy Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NMP1L 1869
Download: ML042890218 (2)


Text

.

Constellation Energy-Nine Mile Point Nuclear Station P.O. Box 63 Lycoming, New York 13093 September 30, 2004 NMPIL 1869 U.S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, DC 20555

SUBJECT:

Nine Mile Point Unit 1

__ Docket No. 50-220 Facility Operating License No. DPR-63 Plans for Submittal of Preliminary Decommissioning Cost Estimate Gentlemen:

This letter responds to the NRC letter dated September 16, 2004, regarding our plans for submittal of a preliminary decommissioning cost estimate for Nine Mile Point Unit 1 (NW 1).

10 CFR 50.75, "Reporting and recordkeeping for decommissioning planning," paragraph (f)(2),

requires power reactor licensees to submit, at or about 5 years prior to the projected end of operations, a preliminary decommissioning cost estimate which includes an up-to-date assessment of the major factors that could affect the cost to decommission. The current NMP1 operating license expires on August 22, 2009.

Nine Mile Point Nuclear Station, LLC, will submit a preliminary decommissioning cost estimate for NMPI, in accordance with 10 CFR 50.75(f)(2), by December 31, 2004.

Very truly ours, J

es A. Spina

/jvice President Nine Mile Point D

E

-m JAS/DEV/jm'.'-

-ri.

I'

.1 I!

I

.1 N

1h

Page 2 NMP1L 1869 cc:

Mr. S. J. Collins, NRC Regional Administrator, Region I Mr. G. K. Hunegs, NRC Senior Resident Inspector Mr. P. S. Tam, Senior Project Manager, NRR (2 copies)