MONTHYEARPMNS20230163, Notice of Meeting with NextEra Energy Seabrook, LLC2023-02-22022 February 2023 Notice of Meeting with NextEra Energy Seabrook, LLC PMNS20221209, Meeting with the U.S. Nuclear Regulatory Commission Petition Review Board and C-10 Research & Education Foundation Regarding a 2.206 Petition Submitted on October 4, 20222022-11-29029 November 2022 Meeting with the U.S. Nuclear Regulatory Commission Petition Review Board and C-10 Research & Education Foundation Regarding a 2.206 Petition Submitted on October 4, 2022 PMNS20220534, Notice of Meeting with NextEra Energy Seabrook, LLC2022-05-17017 May 2022 Notice of Meeting with NextEra Energy Seabrook, LLC PMNS20220468, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-05-0404 May 2022 Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20220108, Notice of Meeting with NextEra Energy Seabrook, LLC2022-02-0909 February 2022 Notice of Meeting with NextEra Energy Seabrook, LLC PMNS20220063, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-02-0101 February 2022 Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20210441, Notice of Meeting with NextEra Energy Seabrook, LLC2021-04-15015 April 2021 Notice of Meeting with NextEra Energy Seabrook, LLC PMNS20201308, Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters2020-11-0505 November 2020 Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters ML19098A6402019-04-0808 April 2019 April 24, 2019 Notice of Public Meeting to Present the NRCs Assessment of Safety Performance at the Seabrook Station, Unit 1, for 2018 ML18313A2672018-11-0909 November 2018 Agenda - Plant License Renewal Subcommittee Meeting - November 15, 2018 ML18295A1362018-10-31031 October 2018 Agenda - Plant License Renewal - Seabrook - October 31, 2018 ML13330A5842013-11-26026 November 2013 Public Meeting Notice for (ASR) Seabrook Station ML13254A0042013-09-10010 September 2013 10/9/2013 - Notice of Public Meeting with NextEra Regarding Concrete Degradation Caused by Alkali-Silica Reaction at Seabrook Station ML13099A2152013-04-18018 April 2013 Forthcoming Meeting with Nextera Energy Seabrook, LLC (Nextera) Regarding a Pre-Submittal for a Fixed Incore Detector License Amendment Request ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML13038A6242013-02-0808 February 2013 02/21/2013 Forthcoming Meeting with Nextera Energy Seabrook, LLC (Nextera) Regarding License Renewal for the Seabrook Station ML12324A2182012-11-19019 November 2012 Notice of Public Meeting with NRC and NextEra Energy, Seabrook, LLC, to Discuss the Safety Implications and Status of Its Review of Commitment Actions Related to the Alkali-Silica Reaction (ASR) Conditions ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12174A0582012-06-0404 June 2012 Concrete Degradation - Region I Engineering Branch No. 1 (Eb 1); Seabrook Concrete Degradation & Implications to Part 50 & 54, September 8, 2011, 3:00 Pm to 4:00 Pm ML12111A1992012-04-20020 April 2012 Updated: 4/26/2012 - Seabrook Notice of Public Meeting No. 12-013 with NextEra Energy Seabrook, LLC ML1208600492012-03-23023 March 2012 Corrected Notice of Forthcoming Meeting with NextEra Energy Seabrook, LLC (NextEra) Regarding Seabrook Station Concrete Degradation ML12174A0422011-12-0909 December 2011 Strategy Meeting Seabrook ASR 10:00am 12/9/11; Seabrook Concrete Degradation ML1128401852011-10-14014 October 2011 Notice of Closed Meeting with NextEra Energy Seabrook, LLC Regarding Flow Erosion Testing Performed at Alion Specific to Seabrook Station, Unit No. 1 ML11153A1642011-08-0303 August 2011 09/15/11 - Notice of Meeting with the Public to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Seabrook Station ML1114306252011-05-23023 May 2011 Notice of Public Meeting with NextEra Energy Seabrook, LLC, Seabrook, Unit 1 to Discuss Nrc'S Assessment of Safety Performance ML1108206992011-03-22022 March 2011 3/22/11 Revised Pre-application Meeting Slides Regarding NFPA 805 License Amendment Request ML1103502052011-02-0404 February 2011 Forthcoming Public Teleconference with NextEra Energy Seabrook, LLC, to Discuss Planned Testing for Seabrook Specific Erosion ML1036201602010-12-28028 December 2010 Notice of Forthcoming Public Teleconference with Nextera Energy Seabrook, LLC, to Discuss Potential License Amendment Request for Seabrook Station to Utilize Alternate Steam Generator Tube Plugging Criteria ML1019000132010-07-20020 July 2010 08/19/2010-Forthcoming Meeting to Discuss the License Renewal Process and Environmental Scoping for Seabrook Station License Renewal Application Review ML1008403972010-03-25025 March 2010 Notice of Meeting with NextEra Energy Seabrook, LLC Regarding the NRC Assessment of NextEra Energy Safety Performance at Seabrook for Calendar Year 2009 ML0926007142009-09-17017 September 2009 Notice of Meeting, Seabrook Regulatory Conference with NRC to Discuss Preliminary-White Finding Identified During Baseline Inspection Completed in July 2009 ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0910701012009-04-17017 April 2009 Notice of Meeting with FPL Energy Seabrook to Discuss NRC Assessment Safety Performance of for Cy 2008 ML0807100082008-03-11011 March 2008 Notice of Meeting with Arizona Public Service, Entergy Operations, Inc., Exelon Generation Co., FPL Energy, Luminant Generation Co., South Carolina Electric & Gas Co., STP Electric Generating Co., & Southern Nuclear Operating Co ML0718410512007-07-0303 July 2007 Notice of Meeting with Florida Power (FPL) and Light to Discuss Fpl'S Plans for Independent Spent Fuel Storage Installations at St. Lucie, Seabrook, and Turkey Point Sites ML0711502952007-04-26026 April 2007 Notice of Meeting with Industry to Discuss a Reactor Oversight Process Performance Indicator Frequently Asked Question ML0707204152007-03-13013 March 2007 Meeting Notice for Annual Assessment Meeting with FPL Energy Management to Discuss Nrc'S Assessment of the Safety Performance of the Seabrook Station for Calendar Year 2006 ML0606605732006-03-10010 March 2006 Notice of Meeting with Florida Power & Light Co, Annual Assessment Meeting, to Discuss Nrc'S Assessment of the Safety Performance of the Seabrook Station for Calendar Year 2005 ML0601201352006-01-19019 January 2006 Notice of Meeting with Florida Power and Light Re Proposed Submittal to Adopt a Common Quality Assurance Topical Report Format ML0533502202005-12-0101 December 2005 Meeting with Energy Seabrook, LLC and Cadon to Discuss Seabrook, Unit 1 Measurement Uncertainty Recapture Power Uprate License Amendment Request ML0507302062005-03-14014 March 2005 NRC Slides for Public Meeting of Seabrook Station Annual Assessment ML0507302542005-03-14014 March 2005 Revised Notice of Meeting with FPL Entergy Seabrook, LLC, to Discuss the Annual Assessment of the Safety Performance of the Seabrook Station for Calendar Year 2004 ML0506703272005-03-0909 March 2005 Forthcoming Meeting with FPL Energy Seabrook LLC, Regarding Interpretation of Seabrook Nuclear Generating Station Technical Specification 3/4.8.1.1, A.C. Sources, Operating. ML0506203572005-03-0303 March 2005 Notice of Meeting with FPL Entergy Seabrook, LLC, to Discuss the Annual Assessment of the Safety Performance of the Seabrook Station for Calendar Year 2004 ML0426701862004-09-27027 September 2004 Summary of Public Meeting with Fple on Power Uprate License Amendment Application for Seabrook ML0412100022004-05-0404 May 2004 Notice of Meeting with FPL Energy Seabrook LLC, Re.: Power Uprate License Amendment Request for Seabrook Station, Unit No. 1 ML0407200912004-03-12012 March 2004 Agenda for Nrc'S Annual Assessment Meeting for Seabrook Station ML0406304312004-03-0303 March 2004 Powerpoint Presentation Slides for Meeting with Florida Power & Light Company Regarding Planned Power Uprate Request for Seabrook Station, Unit No. 1 ML0402800132004-02-0202 February 2004 Meeting Notice, Forthcoming Meeting with Florida Power & Light Company Regarding Planned Power Uprate Request for Seabrook Station, Unit No. 1 2023-02-22
[Table view] Category:Meeting Summary
MONTHYEARML23187A4432023-07-11011 July 2023 6/27/2023, Annual Assessment Meeting for Seabrook Station - Meeting Summary ML23086B9962023-04-0404 April 2023 Summary of March 7, 2023, Meeting with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Revise Emergency Action Level Due to Modification to Containment Fire Detection Equipment ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22146A3422022-06-13013 June 2022 February 23, Summary of Meetings with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Update Pressure-Temperature Limits Curves Period of Applicability ML22153A1672022-06-0202 June 2022 Annual Assessment Meeting for Seabrook Station - Meeting Summary ML21336A4072021-12-0707 December 2021 Summary of Conference Call Regarding the Fall 2021 Steam Generator Tube Inspections ML21168A1522021-06-22022 June 2021 Annual Assessment Meeting Summary ML20174A2682020-06-22022 June 2020 June 3, 2020, Seabrook Annual Assessment Summary ML19073A0172019-03-21021 March 2019 Summary of Meeting with Nextera Energy Seabrook, LLC, on Proposed Relief Requests for the Containment Spray System for the Seabrook Station, Unit No. 1 ML19046A3832019-02-26026 February 2019 Meeting Summary of February 13, 2019, Public Meeting in Hampton, New Hampshire Alkali-Silica Reaction License Amendment Request and License Renewal Application ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18135A2462018-05-31031 May 2018 Summary of April 24, 2018, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of License Amendment Request to Adopt Standard Technical Specification 3.0.6 ML18142A2932018-05-21021 May 2018 2018 Annual Assessment Meeting Summary ML17340A1862017-12-14014 December 2017 Summary of November 17, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction - Requests for Additional Information (CAC No. MF8260; EPID L-2016-LLA-0007) ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17278A7482017-10-13013 October 2017 Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17172A1322017-06-20020 June 2017 Summary of Annual Assessment Meeting for Seabrook Station, Unit 1, Held on 6/7/2017 ML17137A0292017-06-0505 June 2017 Summary of Meeting Held on May 9, 2017, Between the USNRC Staff and NextEra Representatives to Discuss the Seabrook License Renewal Application (CAC No. ME4028) ML16341B9022017-03-0707 March 2017 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16342C4672017-03-0101 March 2017 12/01/2016 Summary of Teleconference Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Requests for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16204A2612016-07-29029 July 2016 June 15, 2016 Summary of Pre-Submittal Meeting with NextEra Energy Regarding Proposed License Amendment on Alkali Silica Reaction for the Seabrook Station, Unit No. 1 ML16190A1812016-07-0808 July 2016 Summary of Public Annual Assessment Meeting ML16168A4122016-06-15015 June 2016 Slides for Public Meeting with NextEra Energy Regarding Seabrook Station ASR License Amendment ML16146A1762016-06-0808 June 2016 April 28, 2016, Summary of Public Meeting with NextEra Energy Seabrook, LLC Regarding Aging Management of Alkali-Silica Reaction Pertaining to the License Renewal of Seabrook Station, Unit 1 ML15343A1862016-01-0707 January 2016 License Renewal Call Summary - December 3, 2015 ML15357A3262015-12-23023 December 2015 Memo-Seabrook Conference Call on Dec. 22, 2015-with NextEra Concerning a Request for Additional Information Pertaining to Seabrook Station Operability Determinations for the Alkali-Silica Reaction (ASR)-affected Containment Enclosure Buildi ML15328A1392015-12-0404 December 2015 November 23, 2015, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Nextera Energy Seabrook, LLC, Concerning Requests for Additional Information Pertaining to the Seabrook Station ML15190A0872015-07-0707 July 2015 June 18, 2015, Summary of Meeting - Seabrook Annual Assessment ML14190B0132014-07-0909 July 2014 June 24, 2014, Summary of Annual Assessment Meeting Regarding Seabrook Station ML14035A2362014-01-30030 January 2014 Seabrook, Unit 1 - Summary of Meeting Between the U.S. Nuclear Regulatory Commission and NextEra Regarding the Status of Alkali-Silica Reaction Testing Program ML13352A5112013-12-27027 December 2013 13-12-18 Seabrook Conference Call Re SAMA RAI ML13133A2412013-06-12012 June 2013 5/9/2013 - Summary of Meeting with NextEra Energy Seabrook, LLC on Pre-Submittal of a Fixed Incore Detector License Amendment Request ML13158A1972013-06-0707 June 2013 5/30/2013 Summary of Teleconference Between NRC Staff and NextEra Energy Staff Regarding Decommissioning Funding Status Report for Seabrook ML13099A2582013-04-0909 April 2013 3/27/2013: Seabrook - Summary of Annual Assessment Meeting with NextEra Energy ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML13004A1782013-01-0404 January 2013 December 11, 2012 Summary of Meeting Regarding Status of Degraded Concrete on Seabrook Station, Unit 1, ML12278A2502012-11-0101 November 2012 Summary of Telephone Conference Call Held Between NRC and NextEra Seabrook, Concerning the RAIs Pertaining to the Seabrook Station, LRA ML12264A6482012-10-16016 October 2012 8/31/2012, Telecon Summary Between NRC and NextEra Seabrook ML12242A5612012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 28, 2012, Between NRC and NextEra Sebrook, LLC, Concerning the Drai Pertaining to the Seabrook, LRA ML12339A2742012-09-13013 September 2012 Concrete Summary 4-12 ML12195A1112012-07-31031 July 2012 Summary of Telephone Conference Call Held on July 3, 2012, Between the NRC and NextEra Energy Seabrook, LLC, Concerning the Draft Request for Additional Information Pertaining to the Seabrook Station, LRA Er ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA ML12164A7562012-06-22022 June 2012 Summary of Telephone Conference Call Between NRC and NextEra Seabrook ML12165A7422012-06-21021 June 2012 Summary of Telephone Conference Call Held on April 10, 2012, Between NRC and Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA ML12142A0422012-05-21021 May 2012 Summary of Public Meeting to Discuss the Nrc'S Annual Assessment of Nextera'S Safety Performance at Seabrook in 2011 ML12054A7662012-03-26026 March 2012 022312, Telecon Summary Between NRC and NextEra Seabrook, Discussing RAIs Response ML12066A1392012-03-20020 March 2012 Summary of Telephone Conference Call Held on March 1, 2012 Between the NRC and NextEra Energy Seabrook Llc., Concerning the Drai Pertaining to the Seabrook Station, LRA Environmental Review 2023-07-11
[Table view] |
Text
September 27, 2004 LICENSEE: FPL Energy Seabrook, LLC (FPLE)
FACILITY: Seabrook Station, Unit 1 (Seabrook)
SUBJECT:
SUMMARY
OF SEPTEMBER 15, 2004, PUBLIC MEETING WITH FPLE ON POWER UPRATE LICENSE AMENDMENT APPLICATION On September 15, 2004, the U.S. Nuclear Regulatory Commission (NRC) staff held a meeting at the NRC Headquarters, One White Flint North, Rockville, Maryland, with representatives from FPLE. Pursuant to the Commissions Policy Statement on "Enhancing Public Participation in NRC Meetings," (67 FR 36920), dated May 28, 2002, the meeting was open to the public for observation and provided an opportunity to communicate with the NRC staff following the business portion of the meeting. No members of the public were in attendance. A list of attendees and the meeting agenda is provided as Attachment 1. The draft of a supplement to FPLE's March 17, 2004, application is provided as Attachment 2.
The meeting was used to discuss additional information related to FPLE's power uprate license amendment request for Seabrook. The meeting provided the NRC staff an opportunity to ensure the licensee has a clear understanding of the information the NRC staff needs to complete its acceptance review of FPLE's application. FPLE plans to submit its formal supplemental information within a few weeks of the meeting. No NRC staff decisions were made during the meeting.
Please direct any inquiries to Scott P. Wall at 301-415-2855, or spw@nrc.gov.
Sincerely,
/RA/
Scott P. Wall, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-443 Attachments: 1. List of Attendees and Agenda
- 2. FPLEs Draft Supplemental Information cc w/encls: See next page
September 27, 2004 LICENSEE: FPL Energy Seabrook, LLC (FPLE)
FACILITY: Seabrook Station, Unit 1 (Seabrook)
SUBJECT:
SUMMARY
OF SEPTEMBER 15, 2004, PUBLIC MEETING WITH FPLE ON POWER UPRATE LICENSE AMENDMENT APPLICATION On September 15, 2004, the U.S. Nuclear Regulatory Commission (NRC) staff held a meeting at the NRC Headquarters, One White Flint North, Rockville, Maryland, with representatives from FPLE. Pursuant to the Commissions Policy Statement on "Enhancing Public Participation in NRC Meetings," (67 FR 36920), dated May 28, 2002, the meeting was open to the public for observation and provided an opportunity to communicate with the NRC staff following the business portion of the meeting. No members of the public were in attendance. A list of attendees and the meeting agenda is provided as Attachment 1. The draft of a supplement to FPLE's March 17, 2004, application is provided as Attachment 2.
The meeting was used to discuss additional information related to FPLE's power uprate license amendment request for Seabrook. The meeting provided the NRC staff an opportunity to ensure the licensee has a clear understanding of the information the NRC staff needs to complete its acceptance review of FPLE's application. FPLE plans to submit its formal supplemental information within a few weeks of the meeting. No NRC staff decisions were made during the meeting.
Please direct any inquiries to Scott P. Wall at 301-415-2855, or spw@nrc.gov.
Sincerely,
/RA/
Scott P. Wall, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-443 Attachments: 1. List of Attendees and Agenda
- 2. FPLEs Draft Supplemental Information cc w/encls: See next page DISTRIBUTION:
PUBLIC CHolden GMatakas, RI OGC JStang PD1-2 R/F DCollins CMiller, EDO, RI ACRS CRaynor TMarsh/JLyons SWall TMensah Accession Number: ML042670186 Meeting Announcement: ML042450067 Attachment No. 2: ML042670212 Package Number: ML042670227 OFFICE PD1-2/PM PD1-2/SC(A)
NAME SWall DCollins DATE 9/27/04 9/27/04 OFFICIAL RECORD COPY
Seabrook Station, Unit No. 1 cc:
Mr. J. A. Stall Mr. Stephen McGrail, Director Senior Vice President, Nuclear and ATTN: James Muckerheide Chief Nuclear Officer Massachusetts Emergency Management Agency Florida Power & Light Company 400 Worcester Road P.O. Box 14000 Framingham, MA 01702-5399 Juno Beach, FL 33408-0420 Philip T. McLaughlin, Attorney General Mr. Peter Brann Steven M. Houran, Deputy Attorney Assistant Attorney General General State House, Station #6 33 Capitol Street Augusta, ME 04333 Concord, NH 03301 Resident Inspector Mr. Bruce Cheney, Director U.S. Nuclear Regulatory Commission New Hampshire Office of Emergency Seabrook Nuclear Power Station Management P.O. Box 1149 State Office Park South Seabrook, NH 03874 107 Pleasant Street Concord, NH 03301 Town of Exeter 10 Front Street Mr. Gene F. St. Pierre Exeter, NH 03823 Station Director Seabrook Station Regional Administrator, Region I FPL Energy Seabrook, LLC U.S. Nuclear Regulatory Commission P.O. Box 300 475 Allendale Road Seabrook, NH 03874 King of Prussia, PA 19406 Mr. M. S. Ross, Managing Attorney Office of the Attorney General Florida Power & Light Company One Ashburton Place, 20th Floor P.O. Box 14000 Boston, MA 02108 Juno Beach, FL 33408-0420 Board of Selectmen Mr. Rajiv S. Kundalkar Town of Amesbury Vice President - Nuclear Engineering Town Hall Florida Power & Light Company Amesbury, MA 01913 P.O. Box 14000 Juno Beach, FL 33408-0420 Ms. Deborah Bell Federal Emergency Management Agency James M. Peschel Region I Regulatory Programs Manager J.W. McCormack P.O. & Seabrook Station Courthouse Building, Room 401 FPL Energy Seabrook, LLC Boston, MA 02109 PO Box 300 Seabrook, NH 03874 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019
Seabrook Station, Unit No. 1 cc:
David Moore Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Marjan Mashhadi Senior Attorney Florida Power & Light Company 801 Pennsylvania Ave., NW Suite 220 Washington, DC 20004
List of Attendees NRC Meeting with FPL Energy Seabrook, LLC Power Uprate License Amendment Request Wednesday, September 15, 2004 9:00 A.M. - 4:15 P.M.
Room: O-6B4 NAME ORGANIZATION Dan Collins* NRC/NRR/DLPM Scott Wall NRC/NRR/DLPM John Stang* NRC/NRR/DLPM Dylanne Duvigneaud* NRC/NRR/DLPM Kulin Desai* NRC/NRR/DSSA Sam Miranda* NRC/NRR/DSSA Frank Orr* NRC/NRR/DSSA Warren Lyon* NRC/NRR/DSSA Richard Lobel* NRC/NRR/DSSA Naeem Iqbal* NRC/NRR/DSSA Paul Loeser* NRC/NRR/DE Narinder Trehan* NRC/NRR/DE Neil Ray* NRC/NRR/DE Bart Fu* NRC/NRR/DE Paul Klein* NRC/NRR/DE Stewart Bailey* NRC/NRR/DE Mike OKeefe FPLE Steve Hale FPLE Robert Haemer* FPLE Howard Onorato FPLE Tom Abbatiello FPLE Greg Myersr FPLE Dave Dominicis Westinghouse Dave Dunsavage Westinghouse Scott Snider Westinghouse Melissa Lucci Westinghouse Dan Merkovsky Westinghouse NRR = Office of Nuclear Reactor Regulation DLPM = Division of Licensing Project Management DSSA = Division of Systems Safety and Analysis DE = Division of Engineering
- Part-time attendence Attachment 1
FPL ENERGY SEABROOK, LLC, U.S. NUCLEAR REGULATORY COMMISSION SEPTEMBER 15, 2004 SEABROOK POWER UPRATE LICENSE AMENDMENT REVIEW MEETING AGENDA INTRODUCTIONS 9:00 a.m. - 9:10 a.m.
REVIEW OF DRAFT RESPONSE 9:10 a.m. - 10:40 a.m.
- Electrical Engineering (Narinder Trehan)
- Vessel & Internal Integrity and Welding (Nihal Ray)
BREAK 10:40 a.m. - 10:50 a.m.
REVIEW OF DRAFT RESPONSE (CONT'D) 10:50 a.m. - 11:50 a.m.
- Fire Protection (Naeen Iqbal)
- Containment (Richard Lobel)
- Instrumentation and Controls (Paul Loeser)
- Environmental Impact PUBLIC COMMENTS 11:50 a.m. - 12:05 p.m.
LUNCH BREAK 12:05 p..m. - 1:00 p.m.
REVIEW OF DRAFT RESPONSE (CONT'D) 1:00 p.m. - 3:45 p.m.
- Pressurized Water Reactor Systems (Kulin Desai)
PUBLIC COMMENTS 3:45 p.m. - 4:00 p.m.
CONCLUSIONS 4:00 p.m. - 4:15 p.m.