ML042640318

From kanterella
Jump to navigation Jump to search
Decommissioning Materials from Drop-In Visit with Sam Collins on September 7, 2004 Dated August 31, 2004
ML042640318
Person / Time
Site: Yankee Rowe
Issue date: 08/31/2004
From: Kacich R
Yankee Atomic Electric Co
To:
NRC/FSME
References
-RFPFR
Download: ML042640318 (45)


Text

Yankee Rowe Decommissioning Richard M. Kacich President, Yankee Atomic Electric Co.

Nuclear Regulatory Commission August 31, 2004

Purpose of Visit Status update on Yankee decommissioning process i Identify current and remaining regulatory issues Dialogue/feedback from NRC 2

Yankee Rowe Was a Nuclear Pioneer In 1954, 11 New England utilities formed YAEC as part of Pres. Eisenhower "Atoms for Peace" program Yankee was a four loop, 185 MWe, PWR that began construction in 1958, and was completed in 1960

- was third U.S. nuclear plant, and first in New England

- cost $39 million to build Began commercial operation in 1961 and was expected to operate for only six years Operated for over three decades, producing 44 billion kilowatt hours Permanently shutdown in 1992 3

/

I* I i

, rI

K,I"'.,i.

il, -.A 9

II Decommissioning Activities are Progressing Well Dose at 53% of the GEIS dose of 1,115 PersonRem

- 585.9 Rem at 12/31/03

- 587.2 Rem at end of 2nd Qtr. 2004

- 596.0 Projection at Project Completion r One lost time accident (LTA) in 3.5 years (1.5 million work hours) 12-month rolling recordable incident rate of 2.8 events per 200,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> compares favorably with industry averages Over 60% of the waste removed from the site Project is about 86% complete 7

Revised Project Completion Strategy i Change in strategy due to shipping accidents, and opportunity for cost savings Two approaches being pursued:

- surveying and demolition of structures suitable for use as site fill

- releasing grade level pads and foundations for direct in-place burial with appropriate drainage per MA DEP X Will avoid disposing of at least 40 million pounds of waste and 1,100 shipments to disposal facilities, at a saving of about $7M All materials will meet NRC LTP and MA DEP requirements 8

Future Major Milestones (completion dates)

Containment Removal - 9/04 Dismantle PAB - 11/04 X Spent Fuel Building Demolition - 12/04 X Demolish Reactor Support Structure - 3/05 I NRC Approves LTP - 1st Qtr. 2005 NRC Approves partial site release of non-impacted land area - 1st Qtr. 2005 I Physical Demolition Complete - 6/05 X Site Final Grading Complete - 8/05 Final Status Survey Complete - 10/05 9

Timely Regulatory Approvals are Critical Path I Site Closure Project Plan issued in 2003 I License Termination Plan submitted in Nov. 2003 X State regulations call for cumulative risk below 1x 10-5 and groundwater at drinking water std.

Extensive interaction with Mass. DEP to achieve aggressive environmental standards X State radiological remediation standard is 10 mrem/yr 10

Regulatory Permitting Process Is Complex and Multifaceted Table I Non-radiological Regulatory Summary o

Imi h k

-WIUIPI.M

_ 1T.J t II h 04 4o I t

I

- I l t t 1o" I

I Mao mn y$ _EwAi SM eowww wamm uWe"= W&VAISR aUU0h l301 aR I1)

EOO"EAot N" f- ~ %f WeOOD*sPmkd AM &OEWiP0O (310Ch 10) Cww*W0n UW3 %tl WBW Act t)EP (314OM9)

WNAc _w - S&WO40 COE 3cR323C*

tlEP (310cV 19) 1SoWlCa~q R D)EF (310CM4)

(310 4_ .U TC SuhsU CWAd EPA 40CR 761)

COmrvowal ofPOW FR o OOM~wCNba~

&Ad W~rsaWoM wM ws *rW ws Mow (18cm Amk mdo A SowOPSES) 18$-CrdW*

(40SmTitralrromd CFR122) SEPtc Ad14hw30 WueleMWMboAd (4QC$R2W1OCMR3M mo19mary1S~Mrd. _wo _~9 _0 ledry (310- X~

Pd tib_

CAR15)

Ebn N t edE

'Ad$~8 AUwaf anop" y~aned wW by Yxe Ac.4y'A m~o ww*loo WMpropbomm M)G&E ACOE- km Crap &9-~IW SEP. eeadwwD1WPlOlS fEnowmralProlCbM lF- kk8*A" PaW RAM- R MOUM

_AeMAWbW CAM- UffOrrw Acb A~tII1I Miew ER.0E*nNlrW kflPWi Rkpor M- WiAppbcatd RIP R_~dy InyOrotw F4 CAD-CopecoACOMw Desi ENF.EOmorw~wd NiC0oII Fom N0t- "OdoeO(0Vf EOEA- Euwtae D olEnWe iil Ake EPA

- US.Eoolorw" tilrded Aqwq FEOC -Fdea Engq Rqrdim Wwtw Required regulatory approvals and permits 10

The NRC Has Taken Actions Essential To Timely Project Completion Timely exemption issued to complete fuel transfer to the ISFSI Frequent stakeholder engagement at Community Advisory Board and Franklin Regional Council of Governments' meetings X Acceptance Review of LTP/lssuance of RAI Timely use of the ORISE confirmatory process Relief from requirement for 24/7 State Police presence 12 Continued Timely NRC Involvement Remains Critical to Project Completion Timely approval of License Termination Plan

' ORISE and Region I engagement in FSS activities I Timely approval of partial site releases i Policy level decision making on liability insurance requirements 13

LTP Approval by NRC is a Key Component to Project Completion I Application filed in November 2003 r RAI issued in June - Response sent August 2004 Public meeting held on June 24, 2004

- Tritium in groundwater was biggest concern

' CAN notified NRC of its intent to intervene in the LTP process - August 2004 Targeted LTP schedule for NRC approval is <50%

of previous industry best. Expected in 1St Qtr 2005 14 Future Major Milestones (completion dates)

Containment Removal - 9/04 Dismantle PAB - 11/04 Spent Fuel Building Demolition - 12/04

' Demolish Reactor Support Structure - 3/05 NRC Approves LTP - 1 st Qtr. 2005 NRC Approves partial site release of non-impacted land area - 1st Qtr. 2005 Physical Demolition Complete - 6/05 Site Final Grading Complete - 8/05 l Final Status Survey Complete - 10/05 I LTP/ASLB proceeding - 2006?

15

Total Decommissioning Expenses (1993 - 2022) are estimated at $636M I Originally budgeted for $235 million in 1992$

$446 million spent through July 2004

' $82 million projected cost from 8/04 - 12/05 Trust fund balance as of 7/31/04 - $39.6 million

  • $108 million for ISFSI operation (2006- 2022)

X Assumes DOE removes fuel from site beginning in 2020 16 Project Performance and Stakeholder Outreach

Physical Work is on Track For Completion by June 2005 i Above Ground Demolition complete: Service Bldg. And Annex, Turbine Bldg., Yard Crane And Support, Fuel Transfer Bldg., Safe Shutdown Bldg., Waste Disposal Compactor Bldg., Radwaste Warehouse, Radwaste Evaporator Bldg., Control Structure, And Auxiliary Bay Primary Water Storage Tank.

Demolition in progress: Vapor Containment, Primary Auxiliary Bldg., Spent Fuel Building, Screenwell and Discharge Structure.

Demolition not yet started: Ion Exchange Pit, Reactor Support Structure, Misc. Tanks, Sherman Pond Remediation, and Below Grade Demolition.

18 Waste Management is a Key Performance Indicator I Total project waste is 82 million pounds Over 50 million pounds shipped through end of July 2004 Waste shipping rate reduced as a result of revised strategy to retain material on site for fill and grading 19

Site closure requires the successful completion of several inter-related efforts

/ A Site\

/ / Slte \ emollto\

/ / C~haracterzto\/

Transfer LW and Final Status Stakeholder Survey Support MultiAgency Regulatory 20 The Stakeholder Outreach Campaign IsExtensive Stakeholder Meetings

- Local (CAB, FRCOG, Town of Rowe, Neighboring Towns, USGen NE)

- State (DEP, EOEA, MA AG's Office, VT ANR)

- Federal (NRC, EPA, ACOE)

' Site Closure Project Plan Updates Site Closure Website: www.yankee.com Site Closure Summary Brochure l Public Information Repository

- Greenfield Community College 21

Inter-Agency Consultations Have Proven Vital

'NRC rEPA U.S. Fish and Wildlife National Marine Fisheries Army Corps of Engineers I Executive Office of Environmental Affairs DEP

- Wetlands/Waterways

- 401 Water Quality Certifications

- Coastal Zone Management MA Department of Fisheries & Wildlife MA Natural Heritage & Endangered Species Program MA Historical Commission 22 Demolition Progress

Steam Generator:Removal From Vapor Container - 1993

re" m-.14p_ I M 7 - -, - . _ _ - __ - . - - .117 -1 I 11 .

.1993 tr. .

Steam::.Generator Leaving. Plant IDg

...w

_^~,IS Vessel C6ask Transport Entering Plant'

1996 hipping -Cask for Reactor Internals 1997 Reactor Vessel en route- to Barnwel

I E~ a , ,: I

wis 2;'o Is qM 61K Imelm loon imm02 I

-p;

.... VPM.iiA4,,

p, ;Gillette, Qgi awards 4

47 W

Vale zl`-4

I, e ...i "', " , ;: . 11 I.

. I I , I

,:, - ., t I I, I q,

",4,

-44g,

4. J

. kp I 11 e k 11, i, k, w.; - "'."

/-!

II

.^,~~~I, .s...

I I > i A, 7_-"-

'1/4 FIax

.,I, .- iUL:

!a:; :

r.>

. o: .

,,I Je,4r .

' I- 4'\;\

a.

,  :' . / I .

'* 1 . I I.,-' '.

'Ki'I I:

a - Am am P3 4w ., ;,o',F ,

r 1, 11 i ,RIII 1

", r: , "

Ill-V" . I.",z'

",l

Elm mli

.:. I ; 4.

I - ItI 11 $i

' I,:,

t 1; . S' . , f U,g ,Ij

II

,AIDS, valid, 4.v

-A41 +A

-bkiq mi MIAMI

"N?

Al WA.

.4, Frankfurt

'P Z...

I 7.7171N'17,'-,4T Q

I l

_ ~

,7~ , I.

I .

I 1.

I

Projected Schedule For Future NRC Approvals

'i License Termination Plan approved - 1 st Qtr.

2005 t, ORISE confirmatory surveys: 9/04 - Fall 2005 u" Approval of Partial Site Release of non-impacted and impacted land areas - 3/2005, 4th Qtr. 2005 r Approval of insurance exemption - late 2004 r Timely completion of ASLB proceeding

  • i 54