ML042370380
| ML042370380 | |
| Person / Time | |
|---|---|
| Site: | Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png |
| Issue date: | 08/24/2004 |
| From: | Connecticut Yankee Atomic Power Co |
| To: | NRC/FSME |
| Shared Package | |
| ML042370290 | List: |
| References | |
| -RFPFR | |
| Download: ML042370380 (22) | |
Text
1 Decommissioning, and LTP Update Meeting with USNRC August 17, 2004
2 Discussion Topics
- Decommissioning Update
- Groundwater Monitoring Results Update
- Building Characterization Results
- Status of Biennial LTP Update
- LTP Amendment Approach
- Conceptual Model
- Dose Calculation Methodology
- Implementation
- Summary and Schedule
3 Decommissioning Update
- FSS of 400 Acres - Class 2 and 3 Areas Complete
- ORISE Inspection of 400 Acres Complete
- FSS of Landfill Area - Class 1 & 2 Areas Complete
- 13 of 43 Canisters Located at the ISFSI 8/12
- Secondary Side Building Removal Begun
- Complete Tank Farm Soil Removal 11/04
- Start RCA Building Removals 8/04
- Complete Fuel Transfer 1/05
- Complete Physical Decommissioning 12/06
- Release Non-ISFSI Areas From License Mid-2007
4 Biennial LTP Update
- 10 CFR 50.71(e) requires an update of the LTP at least every 24 months
- LTP Update Issuance expected by the End of August
- Changes are the same as discussed on 3/9/04
- No changes have triggered Prior NRC Approval due to the LTP License Conditions or 10CFR 50.59 Criteria
5 Tritium Trend NRC Criteria (25 mrem/yr) = 652,000 pCi/L EPA Drinking Water Standard = 20,000 pCi/l 0
20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03 Jan-04 Jan-05 Concentration in pCi/L MW-105S MW-109D MW-102D MW-103D
6 Strontium-90 Trend NRC Criteria (25 mrem/yr) = 251 pCi/l EPA Drinking Water Standard = 8 pCi/l 0
50 100 150 200 250 6/01 12/01 7/02 1/03 8/03 2/04 9/04 Concentration in pCi/L 105S 103S 106S
7 X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X XX X
X X
X X
X X
X X
X X
X X
PAB TK 25-1A TK 25-1B SWITCHGEAR BLDG. "B" TK-20 TK-62 FUEL BUILDING REACTOR CONTAINMENT RADWASTE REDUCTION FACILITY 115KV SWITCHYARD SERVICE BUILDING BOILER ROOM DIESEL TURBINE BUILDING AUX.
BAY X
X X
X SOIL AFFECTING GROUNDWATER SOIL REMOVAL REQUIRED BUT NOT AFFECTING GROUNDWATER NO SUBSURFACE REMEDIATION REQUIRED GW Source Identification
8 Above/below grade structure removed 6 layer of popcorn concrete Below grade structure remaining Bed Rock El. 21-6 El. 17-6 El. 121-0 El. 48-6 El. 22-0 El. 1-6 El. 6 El. 6 El. 6 Fuel Transfer Tube El. 6 El. 0 Yetter\\BNL_SFB00.cdr March 10, 2004 NOT TO SCALE / FOR PRESENTATION PURPOSES ONLY El. 21-6 El. 48-6 El. 21-6 El. 35-0 SPENT FUEL POOL FUEL RACKS El. 47-0 NEW FUEL STORAGE El. 17-6 El. 6 El. 13-6 Fuel Transfer Tube CONNECTICUT YANKEE ATOMIC POWER COMPANY GENERAL ARRANGEMENT DRAWING POTENTIALLY CONTAMINATED BELOW GROUND CONCRETE REACTOR CONTAINMENT BUILDING SPENT FUEL BUILDING
9 Building/Pipe Characterization
- Concrete Cores Taken In:
- RHR Pit
- Cable Vault
- Containment Walls and Mat (Also Bedrock Cores)
- In-Core Sump
- Analyzed for:
- Gamma Radionuclides
- Tritium
- Selected Samples analyzed for
- Transuranic Radionuclides
- Other Hard to Detect Radionuclides
10 Building Characterization Results
- RHR Pit of the Primary Auxiliary Building
- Significant Interior Surface Contamination
- H-3 Volumetric Contamination of Pit Wall near to Former RWST Area below 25 mrem/yr DCGLs
- Decision: Remove Entirely
- Cable Vault
- Low Internal Surface Contamination
- H-3 & Sr-90 Volumetric Contamination of Walls and Floors below 25 mrem/yr DCGLs
- Decision: Remove to 4 foot Below Grade
11 Building Characterization (Cont.)
- Containment Areas other than In-Core Sump
- Significant Surface Contamination of Internal Floors
- Volumetric Contamination of Concrete outside of the Containment Liner below 25 mrem/yr DCGLs:
- Primarily H-3, Other Radionuclides well below DCGLs
- Decision: Remove Concrete to Containment Liner
- Containment In-Core Sump
- One Sample (Area of expected highest activation under Reactor)
- Estimates of Levels of H-3 in Concrete to Remain Significantly Higher then Current Volumetric DCGL
- Decision: Difficult Remediation - Use Basement Fill Model
12 Building Characterization (Cont.)
- Initial Contamination Levels Approximately 1 Million dpm/100cm2
- Pipe Decon conducted using 40,000 psi Hydrolazer
- 9 Full Passes of Embedded Pipe
- Post Decon Survey: No Contamination over
Background
- FSS of pipe to be conducted when exterior soil has been removed in October 2004 time frame
13 LTP Revision 1a Demolition Approach
- Decontaminate Building to Surface and Volumetric DCGLs
- Conduct Final Status Survey with Building Standing
- Buildings Demolished to 3 foot below grade
- Demolition Debris used to backfill the basement
14 Dose Modeling and Final Status Surveys
- Land Areas
- Three Dose Pathways Included
- Soil
- Existing Groundwater
- Areas Impacted by Aquifer Plume
- Buildings
- Groundwater from Buried Debris Resident Farmer is GWfromDebr GW Existing Soil Total D
D D
D yr mr
+
+
=
/
25
15 Revised Demolition Approach Containment Basement:
- Remove Internal Concrete to the Containment Liner
- Perform Final Status Survey of Surfaces and Volumetric Contamination to Building Occupancy DCGLs Except for Inaccessible Areas;
- Piping to be grouted
- In-core Sump rendered inaccessible with Flowable Fill
- Calculate Future Groundwater Dose with Basement Fill Model
- Backfill Basement w/Clean Fill to Approximately 3 ft below grade (includes a protective membrane covered with 1 foot of fill)
- Dispose of Building above 4 ft below grade, membrane and sacrificial fill above membrane as Rad Material
- Survey Surface of fill remaining at 4 ft below grade
- Backfill to grade with clean fill and conduct Surface and Subsurface Final Status Surveys after Isolation and Controls established
16 Revised Demolition Approach (Cont.)
- Fuel Building Spent Fuel Pit: Same Approach as Containment except that liner is to be removed
- Other RCA Building Basements to Remain (such as B Switchgear & Cable Vault with very low contamination history)
- Characterization Results indicate that Decontamination of Basement may not be required
- Membrane and Sacrificial fill layer may not be required due to low contamination history of structure above 4 foot below grade
- Otherwise approach is same as Fuel Building
17 Basement Fill Model
- Calculates Dose from Future Groundwater
- Determines Total Activity Inventory Available for Release to Groundwater from:
- Liner and Embedded Piping Inside Surfaces
- Radioactivity Released from Volumetric Contamination Controlled by Diffusion Rate thru Basement Walls and Flowable Fill (Based on Brookhaven Lab Diffusion Study) for:
- Containment Walls and Floor Mat
- In-Core Sump (Includes Flowable Fill)
- Spent Fuel Pit
18 Basement Fill Model (Cont.)
- Equilibrium Calculated between Backfill Soil and Groundwater for each Basement
- Assumptions of Basement Fill Model:
- Backfill Material Kd to be determined by Testing of Actual Backfill Soil Samples at Brookhaven Lab
- No Recontamination of Liner Walls
- No Credit for Containment Liner
19 Basement Fill Model (Cont.)
- Resulting Groundwater Concentration will be compared to the Groundwater DCGL in HNP LTP Revision 1a to determine dose from Future Groundwater
- For Land Areas which include a Building Basement, Sum of Doses to Show compliance Includes:
- Soil Dose (per HNP LTP Revision 1a)
- Existing Groundwater Dose (per HNP LTP Revision 1a)
- Future Groundwater Dose calculated by Basement Fill Model (Per Proposed License Amendment)
20 Chapters Effected By LTP Amendment
- Chapter 2 - Summary of Concrete Characterization Results
- Chapter 5
- Core Samples Required for Future GW dose calculation:
(See Table at right)
- Additional Buried Pipe Release Values for Additional Pipe Sizes 6
7 Cable Vault 6
6 Planned Spent Fuel Pool 4
1 Taken 4 Planned In-Core Sump 6
8 Containment Mat 6
4 Containment Walls FSS Samples Charact.
Samples Building
21 Chapters Effected by LTP Amendment (Cont.)
- Chapter 6
- Details of Basement Fill Model
- Method of Calculation of Dose - Basement Fill Model
- Summary of Brookhaven Concrete Diffusion Study
- Summary of Brookhaven Backfill Soil Kd Study
22 Summary and Schedule
- Submittal of Amendment in September
- Will Include
- Method to be used to Calculate Future Groundwater
- Estimate of Future Groundwater Dose based on Characterization Results to Date
- Approval Needed by May 2005 to support Demolition Schedule
- Questions/Discussion